Specifications.pdf

PDF 219 KB Posted

Attached to
Replace Emergency Generator Federal contract opportunity
Solicitation number
AG-5114-S-08-AA10
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Midwest Area

About this file

Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Replace Emergency Generator, newest first.
File Type Posted
Amendment One.pdf PDF
Drawings.pdf PDF
Solicitation.pdf PDF
Return Bid Pack.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00001

PROJECT TITLE PAGE

PROJECT MANUAL

PREPARED FOR

Replace Emergency Generator

USDA-ARS,

Dairy Forage Research Center

MADISON, WI

July 30, 2008

Managing Architect:

Bailey Edward Design , Inc.

35 East Wacker, Tower Floor 28

Chicago, IL 60601

(312) 440-2300

Engineering Consultant:

KJWW Engineering

802 W. Broadway

Madison, WI 53713

(608) 223-9600

ELECTRICAL TABLE OF CONTENTS

Replace Emergency Generator, USDA-ARS 26 00 00 - 1 Dairy Forage Research Center Farm (DFRCF), Prairie du Sac, WI Bailey Edward Project Number: 0413-07-08

SECTION TITLE PAGES THRU

Section 26 05 00 Basic Electrical Requirements 26 05 00 – 12 Section 26 05 05 Electrical Demolition for Remodeling 26 05 05 – 02 Section 26 05 13 Wire And Cable 26 05 13 – 04 Section 26 05 31 Boxes 26 05 31 – 03 Section 26 05 33 Conduit 26 05 33 – 09 Section 26 05 53 Electrical Identification 26 05 53 – 05 Section 26 24 16 Panelboards 26 24 16 – 02 Section 26 32 13 Packaged Engine Generator Systems 26 32 13 – 11 Section 26 36 00 Transfer Switch 26 36 00 – 03

Replace Emergency Generator, USDA-ARS 26 05 00 - 1 Dairy Forage Research Center Farm (DFRCF), Prairie du Sac, WI Bailey Edward Project Number: 0413-07-08

SECTION 26 05 00

BASIC ELECTRICAL REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Requirements applicable to all Division 26 Sections.

B. All materials and installation methods shall conform to the applicable standards, guidelines and codes referenced in each specification section.

1.2 SCOPE OF WORK

A. This Specification and the associated drawings govern furnishing, installing, testing and placing into satisfactory operation the Electrical Systems.

B. The Contractor shall furnish and install all new materials as indicated on the drawings, and/or in these specifications, and all items required to make his portion of the Electrical Work a finished and working system.

C. Description of work:

1. Base Bid:

a. The existing generator will be replaced with a new 240 volt, 3-phase, 150KW / 187.5 KVA, 3-phase, 4-wire unit. The new generator will be located outside the building near the existing location in a sound attenuated weatherproof enclosure.

b. A new emergency distribution panel will be provided to replace the existing wireway and circuit breakers as well as backfeed the existing loads. The distribution panel will also include monitoring equipment.

c. The existing generator will be maintained until the new system is installed, tested, and ready for operation.

d. Refer to the attached One-Line Diagram for further information.

2. Bid Option #1:

a. The existing manual transfer switch (MTS-2) associated with the milking equipment will be replaced with an automatic transfer switch. The new switch will allow automatic starting of the generator.

b. Refer to the attached One-Line Diagram for further information.

3. Bid Option #2:

a. The existing manual transfer switch (MTS-3) associated with the well pump will be replaced with an automatic transfer switch. The new switch will allow automatic starting of the generator.

b. Refer to the attached One-Line Diagram for further information.

Replace Emergency Generator, USDA-ARS 26 05 00 - 2

Bailey Edward Project Number: 0413-07-08

1.3 WORK SEQUENCE

A. All work that will produce excessive noise or interference with normal building operations, as determined by the Owner, shall be scheduled with the Owner. It may be necessary to schedule such work during unoccupied hours. The Owner reserves the right to determine when restricted construction hours are required.

B. Refer to drawings for specific instructions.

1.4 DIVISION OF WORK BETWEEN CONTRACTORS

A. Division of work is the responsibility of the Contractor. Any scope of work described at any location on the contract document shall be sufficient for including said requirement in the project. The Contractor shall be solely responsible for determining the appropriate subcontractor for the described scope. In no case shall the project be assessed an additional cost for scope that is described on the contract documents on bid day.

1.5 QUALITY ASSURANCE

A. Contractor’s Responsibility Prior to Submitting Pricing/Bid Data:

1. The Contractor is responsible for constructing complete and operating systems.

The Contractor acknowledges and understands that the Contract Documents are a two-dimensional representation of a three-dimensional object, subject to human interpretation. This representation may include imperfect data, interpreted codes, utility guides, three-dimensional conflicts, and required field coordination items. Such deficiencies can be corrected when identified prior to ordering material and starting installation. The Contractor agrees to carefully study and compare the individual Contract Documents and report at once in writing to the Architect/Engineer any deficiencies the Contractor may discover. The Contractor further agrees to require each subcontractor to likewise study the documents and report at once any deficiencies discovered.

2. The Contractor shall resolve all reported deficiencies with the Architect/Engineer prior to awarding any subcontracts, ordering material, or starting any work with the Contractor’s own employees. Any work performed prior to receipt of instructions from the Architect/Engineer will be done at the Contractor’s risk.

B. Qualifications:

1. Only products of reputable manufacturers as determined by the Engineer are acceptable.

2. Contractor shall employ only workmen who are skilled in their trades.

C. Compliance with Codes, Laws, Ordinances:

1. Conform to all requirements of the authority having jurisdiction.

2. If there is a discrepancy between the codes and regulations and these specifications, the Engineer shall determine the method or equipment used.

3. If the Contractor notes, at the time of bidding, any parts of the drawings or specifications that do not comply with the codes or regulations, he shall inform the Architect/Engineer in writing, requesting a clarification.

Replace Emergency Generator, USDA-ARS 26 05 00 - 3

Bailey Edward Project Number: 0413-07-08

4. If there is a discrepancy between manufacturer's recommendations and these specifications, the Contractor shall bid plans and specifications.

5. If there are no local codes having jurisdiction, the current issue of the National Electrical Code shall be followed.

D. Permits, Fees, Taxes, Inspections:

1. Procure all applicable permits and licenses.

2. Abide by all laws, regulations, ordinances, and other rules of the State or Political Subdivision where the work is done, or as required by any duly constituted public authority.

3. Pay all charges for permits or licenses.

4. Pay all fees and taxes imposed by State, Municipal, and other regulatory bodies.

5. Pay all charges arising out of required inspections by an authorized body.

6. Pay all charges arising out of required contract document reviews associated with the project and as initiated by the Owner or authorized agency/consultant.

7. Where applicable, all fixtures, equipment and materials shall be listed by Underwriter’s Laboratories, Inc. or a nationally recognized testing organization.

E. Examination of Drawings:

1. The drawings for the electrical work are completely diagrammatic, intended to convey the scope of the work and to indicate the general arrangements and locations of equipment, outlets, etc., and the approximate sizes of equipment.

2. Contractor shall determine the exact locations of equipment and rough-ins, and the exact routing of raceways so as to best fit the layout of the job.

3. Scaling of the drawings will not be sufficient or accurate for determining these locations.

4. Where job conditions require reasonable changes in arrangements and locations, such changes shall be made by the Contractor at no additional cost to the Owner.

5. Because of the scale of the drawings, certain basic items, such as junction boxes, pull boxes, conduit fittings, etc., may not be shown, but where required by other sections of the specifications or required for proper installation of the work, such items shall be furnished and installed.

6. If an item is either shown on the drawings or called for in the specifications, it shall be included in this contract.

7. The Contractor shall determine quantities and quality of material and equipment required from the documents. Where discrepancies arise between drawings, schedules and/or specifications, the specifications shall govern.

8. Where used in electrical documents the word “furnish” shall mean supply for use, the word “install” shall mean connect up complete and ready for operation, and the word “provide” shall mean to supply for use and connect up complete and ready for operation.

Replace Emergency Generator, USDA-ARS 26 05 00 - 4

Bailey Edward Project Number: 0413-07-08

9. Any item listed as furnished shall also be installed unless otherwise noted.

10. Any item listed as installed shall also be furnished unless otherwise noted.

F. Electronic Media/Files:

1. Construction drawings for this project have been prepared utilizing AutoCAD Release 2008.

2. Contractors and Subcontractors may request electronic media files of the contract drawings and/or copies of the specifications. Specifications will be provided in PDF format.

3. Upon request for electronic media, the Contractor shall complete and return a signed “Electronic File Transmittal” form provided by KJWW.

4. If the information requested includes floor plans prepared by others, the Contractor will be responsible for obtaining approval from the appropriate Design Professional for use of that part of the document.

5. The electronic contract documents can be used for preparation of shop drawings and as-built drawings only. The information may not be used in whole or in part for any other project.

6. The drawings prepared by KJWW for bidding purposes may not be used directly for ductwork layout drawings or coordination drawings.

7. The use of these CAD documents by the Contractor does not relieve them from their responsibility for coordination of work with other trades and verification of space available for the installation.

8. The information is provided to expedite the project and assist the Contractor with no guarantee by KJWW as to the accuracy or correctness of the information provided. KJWW accepts no responsibility or liability for the Contractor’s use of these documents.

G. Field Measurements:

1. Verify all pertinent dimensions at the job site before ordering any conduit, conductors, wireways, bus duct, fittings, etc.

1.6 SUBMITTALS

A. Submittals shall be required for the following items, and for additional items where required elsewhere in the specifications or on the drawings.

1. Submittals list:

Submittal Item Referenced Specification Section

a. Panelboards 26 24 16

b. Packaged Engine Generator Systems 26 32 13

c. Transfer Switch – Bid Option #1 & #2 26 36 00

B. In addition to the provisions of Division 1, the following provisions are required:

1. Submittals shall include all fabrication, erection, layout, and setting drawings;

manufacturers' standard drawings; schedules; descriptive literature, catalogs and

Replace Emergency Generator, USDA-ARS 26 05 00 - 5

Bailey Edward Project Number: 0413-07-08 brochures; performance and test data; wiring and control diagrams; and all other drawings and descriptive data of materials of construction as may be required to show that the materials, equipment or systems and the location thereof conform to the requirements of the contract documents.

2. The Contractor shall submit eight (8) copies of each shop drawing for review by the Architect/Engineer BEFORE releasing any equipment for manufacture or shipment.

3. Review and markup air conditioning and ventilating contractor's layout drawings with electrical equipment and conduit routings for coordination.

4. Shop drawings that are larger than 11" x 17" or are plan size layout or erection drawings shall be submitted on reproducible media. Submit one reproducible and one print of each drawing or plan. All Contractor approval stamps shall be on the reproducible.

5. The Contractor shall thoroughly review and approve all shop drawings before submitting them to the Architect/Engineer. CONTRACTOR’S APPROVAL

STAMP IS REQUIRED ON ALL SUBMITTALS. APPROVAL WILL INDICATE

THE CONTRACTOR'S REVIEW of all material and a COMPLETE UNDERSTANDING OF EXACTLY WHAT IS TO BE FURNISHED. Contractor shall clearly mark all deviations from the contract documents on all submittals. IF

THE CONTRACTOR DOES NOT MARK DEVIATIONS, THEN THE ITEM

SHALL BE REQUIRED TO MEET ALL DRAWING AND SPECIFICATION

REQUIREMENTS.

6. Each data sheet shall clearly show at the top of the sheet what Material List symbol (and applicable variations and subscripts) that data sheet corresponds to.

7. Each data sheet shall show the size, rating, style, finish, material, catalog number, manufacturer name and product photos for each item to ensure compliance with these specifications.

8. Assemble all submittals in sets. All sets shall be identical and contain an index of the items enclosed with a general topic description on the cover.

9. Bind each set in a manufacturer's folder or inside of a manila file folder.

10. Where more than one model is shown on a manufacturer's sheet, clearly indicate exactly which item and which data is relevant to the work.

11. Where the manufacturer lists multiple part numbers or options on a single data sheet, the part number and options to be used shall be clearly set apart from other part numbers shown on that sheet.

12. Failure to comply with the above shall be reason to resubmit all shop drawings.

1.7 PRODUCT DELIVERY, STORAGE, HANDLING AND MAINTENANCE

A. Exercise care in transporting and handling to avoid damage to materials. Store materials on the site to prevent damage.

B. Keep all materials clean, dry and free from damaging environments.

Replace Emergency Generator, USDA-ARS 26 05 00 - 6

Bailey Edward Project Number: 0413-07-08

1.8 WARRANTY

A. Warranty requirements extend to correction, without cost to the Owner, of all work found to be defective or nonconforming to the contract documents. The Contractor shall bear the cost of correcting all damage due to defects or nonconformance with contract documents excluding repairs required as a result of improper maintenance or operation, or of normal wear as determined by the Architect/Engineer.

1.9 INSURANCE

A. This Contractor shall maintain insurance coverage as set forth in the USDA contract.

1.10 MATERIAL SUBSTITUTION

A. Where several manufacturers’ names are given, the manufacturer for which a catalog number is given is the basis of design and establishes the quality required.

B. Equivalent equipment manufactured by the other named manufacturers may be used.

Contractor shall ensure that all items submitted by these other manufacturers meet all requirements of the drawings and specifications, and fit in the allocated space. The Engineer shall make the final determination of whether a product is equivalent during the shop drawing review phase. The contractor shall be responsible for submitting sufficient information to show equivalence.

PART 2 - PRODUCTS

2.1 GENERAL

A. All items of material having a similar function shall be of the same manufacturer unless specifically stated otherwise on drawings or elsewhere in specifications.

PART 3 - EXECUTION

3.1 JOBSITE SAFETY

A. Neither the professional activities of the Engineer, nor the presence of the Engineer or his or her employees and subconsultants at a construction site, shall relieve the Contractor and any other entity of their obligations, duties and responsibilities including, but not limited to, construction means, methods, sequence, techniques or procedures necessary for performing, superintending or coordinating all portions of the work of construction in accordance with the contract documents and any health or safety precautions required by any regulatory agencies. The Engineer and his or her personnel have no authority to exercise any control over any construction contractor or other entity or their employees in connection with their work or any health or safety precautions. The Contractor is solely responsible for jobsite safety.

3.2 EXCAVATION, FILL, BACKFILL, COMPACTION

A. General:

1. Prior to the commencement of any excavation or digging, the Contractor shall verify all underground utilities with the regional utility locator. Provide notice to the locator within the time before excavations required by law.

In Wisconsin, call Diggers Hotline (800) 242-8511

Replace Emergency Generator, USDA-ARS 26 05 00 - 7

Bailey Edward Project Number: 0413-07-08

2. The Contractor shall do all excavating, filling, backfilling, compacting, and restoration in connection with his work.

B. Excavation:

1. Make all excavations to accurate, solid, undisturbed earth, and to proper dimensions.

2. If excavations are carried in error below indicated levels, concrete of same strength as specified for the foundations or thoroughly compacted sand-gravel fill, as determined by the Architect/Engineer shall be placed in such excess excavations under the foundation. Place thoroughly compacted, clean, stable fill in excess excavations under slabs on grade, at the Contractor's expense.

3. Trim bottom and sides of excavations to grades required for foundations.

4. Protect excavations against frost and freezing.

5. Take care in excavating not to damage surrounding structures, equipment or buried pipe. Do not undermine footing or foundation.

6. Perform all trenching in a manner to prevent cave-ins and risk to workmen.

7. Where original surface is pavement or concrete, the surface shall be saw cut to provide clean edges and assist in the surface restoration.

8. If satisfactory bearing soil is not found at the indicated levels, immediately notify the Architect/Engineer or their representative, and do no further work until the Architect/Engineer or their representative gives further instructions.

9. Excavation shall be performed in all ground conditions, including rock, if encountered. Bidders shall visit the premises and determine the soil conditions by actual observations, borings, or other means. The cost of all such inspections, borings, etc., shall be borne by the bidder.

10. If a trench is excavated in rock, a compacted bed with a depth of 3" (minimum) of sand and gravel shall be used to support the conduit unless masonry cradles or encasements are used.

11. Mechanical excavation of the trench to line and grade of the conduit or to the bottom level of masonry cradles or encasements is permitted, unless otherwise indicated on the electrical drawings.

12. Mechanical excavation of the trench to line and grade where direct burial cables are to be installed is permitted provided the excavation is made to a depth to permit installation of the cable on a fine sand bed at least 3 inches deep.

C. Dewatering:

1. Furnish, install, operate and remove all dewatering pumps and pipes needed to keep trenches and pits free of water.

D. Underground Obstructions:

1. Known underground piping, conduit, feeders, foundations, and other obstructions in the vicinity of construction are shown on the drawings. Review all Bid Documents for all trades on the project to determine obstructions indicated. Take great care in making installations near underground obstructions.

Replace Emergency Generator, USDA-ARS 26 05 00 - 8

Bailey Edward Project Number: 0413-07-08

2. If objects not shown on the drawings are encountered, remove, relocate, or perform extra work as directed by the Architect/Engineer.

E. Fill and Backfilling:

1. No rubbish or waste material is permitted for fill or backfill.

2. Furnish all necessary sand for backfilling.

3. Dispose of the excess excavated earth as directed.

4. Backfill materials shall be suitable for required compaction, clean and free of perishable materials, frozen earth, debris, earth with a high void content, and stones greater than 4 inches in diameter. Water is not permitted to rise in unbackfilled trenches.

5. Backfill all trenches and excavations immediately after installing of conduit, or removing forms, unless other protection is directed.

6. Around piers and isolated foundations and structures, backfill and fill shall be placed and consolidated simultaneously on all sides to prevent wedge action and displacement. Spread fill and backfill materials in 6” uniform horizontal layers with each layer compacted separately to required density.

7. Lay all conduits on a compacted bed of sand at least 3" deep. Backfill around conduits with sand, in 6" layers and compact each layer.

8. Backfill with sand up to grade for all conduits under slabs or paved areas. All other conduits shall have sand backfill to 6" above the top of the conduit.

9. Place all backfill above the sand in uniform layers not exceeding 6” deep. Place then carefully and uniformly tamp each layer to eliminate lateral or vertical displacement.

10. Where the fill and backfill will ultimately be under a building, floor or paving, each layer of fill shall be compacted to 95% of the maximum density as determined by AASHTO Designation T-99 or ASTM Designation D-698. Moisture content of soil at time of compaction shall not exceed plus or minus 2% of optimum moisture content as determined by AASHTO T-99 or ASTM D-698 test.

11. After backfilling of trenches, no superficial loads shall be placed on the exposed surface of the backfill until a period of 48 hours has elapsed.

F. Surface Restoration:

1. Where trenches are cut through graded, planted or landscaped areas, the areas shall be restored to the original condition. Replace all planting and landscaping features removed or damaged to its original condition. At least 6” of topsoil shall be applied where disturbed areas are to be seeded or sodded. All lawn areas shall be sodded unless seeding is called out in the drawings or specifications.

2. Concrete or asphalt type pavement, seal coat, rock, gravel or earth surfaces removed or damaged shall be replaced with comparable materials and restored to original condition. Broken edges shall be saw cut and repaired as directed by Architect/Engineer.

Replace Emergency Generator, USDA-ARS 26 05 00 - 9

Bailey Edward Project Number: 0413-07-08

3.3 PROJECT CLOSEOUT

A. Final Jobsite Observation:

1. In order to prevent the Final Jobsite Observation from occurring too early, the Contractor shall review the completion status of the project and certify that the job is ready for the final jobsite observation.

2. Attached to the end of this section is a typical list of items that represent the degree of job completeness expected prior to requesting a review. The Contractor shall sign the attached certification and return it to the Architect/Engineer so that the final observation can be scheduled.

B. The following shall be submitted prior to the Contractor submitting final payment application:

1. Operation and maintenance manuals with copies of approved shop drawings.

2. Record documents including marked-up drawings and specifications.

3. A report documenting the instructions given to the Owner's representatives complete with the number of hours spent in the instruction. The report shall bear the signature of an authorized agent of this Contractor and shall be signed by the Owner's representatives.

4. Provide spare parts, maintenance, and extra materials in quantities specified in individual specification sections. Deliver to project site and place in location as directed and submit receipt to Architect/Engineer.

5. Start-up reports on all equipment requiring a factory installation or start-up.

3.4 OPERATION AND MAINTENANCE INSTRUCTIONS

A. Submit three (3) properly indexed and bound copies, in “D” ring style notebooks, of the Operations and Maintenance Instructions to the Architect/Engineer. Make all corrections or additions required.

B. Operation and Maintenance Instructions shall include:

1. Notebooks shall incorporate clear vinyl sheet sleeves on the front cover and spine for slip-in labeling. “Peel and Stick” labels are not acceptable. Sheet lifters shall be supplied at the front of each notebook. Provide “Wilson-Jones” Model #85600 or equal. Size notebooks a minimum of 1/4" thicker than material for future inserts. Label the spine and front cover of each notebook. If more than one notebook is required, all shall be the same color. No other forms of binding will be acceptable.

2. Prepare binder covers (front and spine) with printed title “Operation and Maintenance Instructions”, title of project, and subject matter of binder when multiple binders are required.

3. Title page with project title, Architect, Engineer, Contractor, and Subcontractor with addresses, telephone numbers, and contacts.

4. Table of Contents describing all index tabs.

Replace Emergency Generator, USDA-ARS 26 05 00 - 10

Bailey Edward Project Number: 0413-07-08

5. Listing of all Subcontractors and major equipment suppliers with addresses, telephone numbers, and contacts.

6. Index tabs dividing information by specification section, major equipment, or systems. All tab titles shall be clearly printed under reinforced plastic tabs. Label all equipment to match the identification in the construction documents.

7. Copies of warranties.

8. Copies of all final approved shop drawings and submittals.

9. Copies of all factory inspection and/or equipment start-up reports.

C. Operation and maintenance data shall consist of written instructions for the care, maintenance, and operation of the equipment and systems. Instruction books, cards, manuals furnished with the equipment shall be included.

3.5 INSTRUCTING THE OWNER'S REPRESENTATIVE

A. Adequately instruct the Owner's designated representatives in the maintenance, care, and operation of the complete systems installed under this contract.

B. Provide verbal and written instructions to the Owner's representatives by FACTORY PERSONNEL in the care, maintenance, and operation of the equipment and systems.

C. The Owner has the option to video tape all instructions. Coordinate schedule of instructions to facilitate this recording.

D. The instructions shall include:

1. Maintenance of equipment.

2. Start-up procedures for all major equipment.

3. Description of emergency system operation.

E. Notify the Engineer of the time and place for the verbal instructions to the Owner's representative so his representative can be present if desired.

F. Minimum hours of instruction time for each item and/or system shall be as indicated in each individual specification section.

G. Operating Instructions:

1. Contractor is responsible for all instructions to the Owner’s representatives for the electrical and specialized systems.

3.6 RECORD DOCUMENTS

A. Maintain at the job site a separate and complete set of drawings and specifications with all changes made to the systems clearly and permanently marked in complete detail.

B. Mark drawings and specifications to indicate approved substitutions; Change Orders, and actual equipment and materials used. All Change Orders, RFI responses, Clarifications and other supplemental instructions shall be marked on the documents. Record documents that merely reference the existence of the above items are not acceptable.

C. Record changes daily and keep the marked drawings available for the Architect/Engineer's examination at any normal work time.

Replace Emergency Generator, USDA-ARS 26 05 00 - 11

Bailey Edward Project Number: 0413-07-08

D. Upon completing the job, and before final payment is made, give the marked-up drawings to the Architect/Engineer.

3.7 PAINTING

A. Paint all equipment that is marred or damaged prior to the Owner's acceptance. Paint and color shall match original equipment paint and shall be obtained from the equipment supplier if available. All equipment shall have a finished coat of paint applied unless specifically allowed to be provided with a prime coat only.

B. Equipment cabinets, casings, covers, metal jackets, etc., located in equipment rooms or concealed spaces, shall be furnished in standard finish, free from scratches, abrasions, chippings, etc.

C. Equipment in occupied spaces, or if standard to the unit, shall have a baked primer with baked enamel finish coat free from scratches, abrasions, chipping, etc. If color option is specified or is standard to the unit, verify with the Architect/Engineer his color preference before ordering.

D. After surfaces have been thoroughly cleaned and are free of oil, dirt or other foreign matter, paint all raceway and equipment with the following:

1. Bare Metal Surfaces - Apply one coat of metal primer suitable for the metal being painted. Finish with two coats of Alkyd base enamel paint.

2. Plastic Surfaces - Paint plastic surfaces with two coats of semi-gloss acrylic latex paint.

3.8 ADJUST AND CLEAN

A. Thoroughly clean all equipment and systems prior to the Owner's final acceptance of the project.

B. Clean all foreign paint, grease, oil, dirt, labels, stickers, etc. from all equipment.

C. Remove all rubbish, debris, etc., accumulated during construction from the premises.

3.9 SPECIAL REQUIREMENTS

A. Install all equipment to maximize access to parts needing service or maintenance.

Review the final location, placement, and orientation of equipment with the Owner’s representative prior to setting equipment.

B. Installation of equipment or devices without regard to coordination of access requirements and confirmation with the Owner’s representative will result in removal and reinstallation of the equipment at the Contractor’s expense.

3.10 SYSTEM COMMISSIONING

A. The electrical systems shall be complete and operating. System start-up, testing, balancing, and satisfactory system performance is the responsibility of the Contractor.

This includes all calibration and adjustment of electrical controls, balancing of loads, troubleshooting and verification of software, and final adjustments that may be needed.

B. All operating conditions and control sequences shall be tested during the start-up period.

Testing all interlocks, safety shut-downs, controls, and alarms.

Replace Emergency Generator, USDA-ARS 26 05 00 - 12

Bailey Edward Project Number: 0413-07-08

1. The Contractor, subcontractors, and equipment suppliers shall have skilled technicians to ensure that all systems perform properly.

3.11 FIELD QUALITY CONTROL

A. General:

1. Conduct all tests required during and after construction.

2. Supply necessary instruments, meters, etc., for the tests. Supply competent technicians with training in the proper testing techniques.

3. All cables and wires shall be tested for shorts and grounds following installation and connection to devices. Replace shorted or grounded wires and cables.

4. Any wiring device, electrical apparatus or lighting fixture, if grounded or shorted on any integral "live" part, shall have all defective parts or materials replaced.

5. Test cable insulation of service and panel feeder conductors for proper insulation values. Tests shall include the cable, all splices, and all terminations. Each conductor shall be tested and shall test free of short circuits and grounds and have an insulation value not less than the National Electrical Code Standards.

Take readings between conductors, and between conductors and ground.

6. If the results obtained in the tests are not satisfactory make adjustments, replacements, and changes as needed. Then repeat the tests, and make additional tests, as the Architect/Engineer or authority having jurisdiction deems necessary.

B. Other Equipment:

1. Give other equipment furnished and installed by the Contractor all standard tests normally made to assure that the equipment is electrically sound, all connections properly made, phase rotation correct, fuses and thermal elements suitable for protection against overloads, voltage complies with equipment nameplate rating, and full load amperes are within equipment rating.

C. If any test results are not satisfactory, make adjustments, replacements and changes as needed and repeat the tests and make additional tests as the Architect/Engineer or authority having jurisdiction deem necessary.

END OF SECTION

Replace Emergency Generator, USDA-ARS 26 05 05 - 1

SECTION 26 05 05

ELECTRICAL DEMOLITION FOR REMODELING

1.1 SECTION INCLUDES

A. Electrical demolition

PART 2 - PRODUCTS

2.1 MATERIALS AND EQUIPMENT

A. Materials and equipment for patching and extending work shall be as specified in individual Sections.

PART 3 - EXECUTION

3.1 EXAMINATION

A. THE DRAWINGS ARE INTENDED TO INDICATE THE SCOPE OF WORK REQUIRED

AND DO NOT INDICATE EVERY BOX, CONDUIT, OR WIRE THAT MUST BE

REMOVED.

B. It is strongly recommended that the bidding contractor visit the site prior to submitting their bid.

C. Verify that abandoned wiring and equipment serve only abandoned equipment or facilities. Extend conduit and wire to facilities and equipment that will remain in operation following demolition. Extension of conduit and wire to equipment shall be compatible with the surrounding area.

D. Coordinate scope of work with the Owner at the project site. Schedule removal of equipment and electrical service to avoid conflicts.

3.2 PREPARATION

A. Coordinate utility service outages with Utility Company.

B. Provide temporary wiring and connections to maintain existing systems in service during construction. When work must be performed on energized equipment or circuits, use personnel experienced in such operations. Assume all equipment and systems must remain operational unless specifically noted otherwise on drawings.

3.3 DEMOLITION AND EXTENSION OF EXISTING ELECTRICAL WORK

A. Demolish and extend existing electrical work under provisions of this Section.

B. Remove, relocate, and extend existing installations to accommodate new construction.

C. Remove abandoned wiring and raceway to source of supply.

Replace Emergency Generator, USDA-ARS 26 05 05 - 2

Bailey Edward Project Number: 0413-07-08

D. Remove exposed abandoned raceway, including abandoned raceway above accessible ceiling finishes. Cut raceway flush with walls and floors, and patch surfaces. Remove all associated clamps, hangers, supports, etc. associated with raceway removal.

E. Disconnect and remove abandoned panelboards and distribution equipment.

F. Disconnect and remove electrical devices and equipment serving utilization equipment that has been removed.

G. Repair adjacent construction and finishes damaged during demolition and extension work. Patch openings to match existing surrounding finishes.

H. Maintain access to existing electrical installations that remain active. Modify installation or provide access panel as appropriate.

I. Extend existing installations using materials and methods compatible with existing electrical installations, or as specified.

J. Regulatory Requirements: Comply with governing EPA notification regulations before beginning demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

K. Floor slab is post-tensioned. All penetrations shall be x-rayed prior to cutting and/or drilling to avoid any tension cables or utilities encased in floor construction.

L. Floor slabs may contain conduit systems. This Contractor is responsible for taking any measures required to ensure no conduits or other services are damaged. This includes x-ray or similar non-destructive means.

M. This Contractor is responsible for all costs incurred in repair, relocations, or replacement of any cables, conduits, or other services if damaged without proper investigation.

3.4 CLEANING AND REPAIR

A. Clean and repair existing materials and equipment that remain or are to be reused.

B. Panelboards: Clean exposed surfaces and check tightness of electrical connections.

Replace damaged circuit breakers and provide closure plates for vacant positions.

Provide typed circuit directory showing revised circuiting arrangement.

C. ELECTRICAL ITEMS REMOVED AND NOT RELOCATED REMAIN THE PROPERTY

OF THE OWNER. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE

DISPOSAL OF MATERIAL THE OWNER DOES NOT WANT.

3.5 INSTALLATION

A. Install relocated materials and equipment under the provisions of these Specifications.

Replace Emergency Generator, USDA-ARS 26 05 13 - 1

SECTION 26 05 13

WIRE AND CABLE

1.1 SECTION INCLUDES

A. Building wire B. Cable C. Wiring connections and terminations

1.2 REFERENCES

A. ASTM B800-05 – Standard Specification for 8000 Series Aluminum Alloy Wire Electrical Purposes-Annealed and Intermediate Tmepers

B. ASTM B801-07 – Standard Specification for Concentric-Lay-Stranded Conductors of 8000 Series Aluminum Alloy for Subsequent Covering or Insulation

C. NEMA WC 3 - Rubber-Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy

D. NEMA WC 5 - Thermoplastic-Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy

E. UL 44 – Thermoset-Insulated Wires and Cables

F. UL 854 – Service-Entrance Cables

PART 2 - PRODUCTS

2.1 BUILDING WIRE

A. Thermoplastic-insulated Building Wire: NEMA WC 5.

B. Rubber-insulated Building Wire: NEMA WC 3.

C. Feeders and Branch Circuits Larger Than 6 AWG: Copper, stranded conductor, 600 volt insulation, THHN/THWN.

D. Feeders and Branch Circuits Larger than 6 AWG in Underground Conduit: Copper, stranded conductor, 600 volt insulation, THWN.

E. Feeders and Branch Circuits 6 AWG and Smaller: Copper conductor, 600 volt insulation, THHN/THWN. 6 and 8 AWG, stranded conductor; smaller than 8 AWG, solid or stranded conductor, unless otherwise noted on the drawings.

F. Control Circuits: Copper, stranded conductor 600 volt insulation, THHN/THWN.

2.2 REMOTE CONTROL AND SIGNAL CABLE

A. Control Cable for Class 1 Remote Control and Signal Circuits: Copper conductor, 600 volt insulation, rated 60°C, individual conductors twisted together, shielded, and covered with a PVC jacket.

Replace Emergency Generator, USDA-ARS 26 05 13 - 2

Bailey Edward Project Number: 0413-07-08

B. Control Cable for Class 2 or Class 3 Remote Control and Signal Circuits: Copper conductor, 300 volt insulation, rated 60ºC, individual conductors twisted together, shielded, and covered with a PVC jacket; UL listed.

C. Plenum Cable for Class 2 or Class 3 Remote Control and Signal Circuits: Copper conductor, 300 volt insulation, rated 60°C, individual conductors twisted together, shielded, and covered with a nonmetallic jacket; UL listed for use in air handling ducts, hollow spaces used as ducts, and plenums.

PART 3 - EXECUTION

3.1 GENERAL WIRING METHODS

A. The ampacity of multiple conductors in one conduit shall be derated per National Electrical Code, Article 310. In no case shall more than 4 conductors be installed in one conduit to such loads as panelboards.

B. Where installing parallel feeders, place an equal number of conductors for each phase of a circuit in same raceway or cable.

C. Splice only in junction or outlet boxes.

D. Neatly train and lace wiring inside boxes, equipment, and panelboards.

E. Make conductor lengths for parallel circuits equal.

F. All conductors shall be continuous in conduit from last outlet to their termination.

3.2 WIRING INSTALLATION IN RACEWAYS

A. Pull all conductors into a raceway at the same time. Use UL listed wire pulling lubricant for pulling 4 AWG and larger wires.

B. Install wire in raceway after interior of building has been physically protected from the weather and all mechanical work likely to injure conductors has been completed.

C. Pulling shall be continuous without unnecessary stops and starts with wire or cable only partially thru raceway.

D. Where reels of cable or wire are used, they shall be set up on jacks close to the point where the wire or cable enters the conduit or duct so that the cable or wire may be unreeled and run into the conduit or duct with a minimum of change in the direction of the bend.

E. Cables or wires shall not be laid out on the ground before pulling.

F. Cables or wires shall not be dragged over earth or paving.

G. Care shall be taken so as not to subject the cable or wire to high mechanical stresses that would cause damage to the wire and cable.

H. Conductors shall not be pulled through conduits until plastering or masonry work is completed and conduits are free from moisture. Care shall be taken so that long pulls of wire or pulls around several bends are not made where the wire may be permanently stretched and the insulation damaged.

Replace Emergency Generator, USDA-ARS 26 05 13 - 3

Bailey Edward Project Number: 0413-07-08

I. Only nylon rope shall be permitted to pull cables into conduit and ducts.

J. At least six (6) inch loops or ends shall be left at each outlet for installation connection of fixtures or other devices.

K. All wires in boxes not connected to fixtures or other devices shall be rolled up, spliced if continuity of circuit is required, and insulated.

L. Completely and thoroughly swab raceway system before installing conductors.

3.3 CABLE INSTALLATION

A. Provide protection for exposed cables where subject to damage.

B. Use suitable cable fittings and connectors.

C. Run all open cable in a neat and symmetrical manner. Follow the routing as illustrated on the drawings as closely as possible. If routing is not illustrated then the Contractor shall choose his own routing, but in any case it shall be run in a manner previously stated.

D. Open cable shall be supported by the appropriate size bridle rings or other means if called for on the drawings. Wire and cable from different systems shall not be installed in the same bridle rings.

E. Open cable installed above suspended ceilings shall not rest on the suspended ceiling construction, nor utilize the ceiling support system for wire and cable support.

F. Where open cables are grouped, they shall be neatly bundled and held together with nylon tie wraps placed every 2.5 ft. on the bundle. Where tie bundle passes through a bridle ring it shall be fastened to the ring with a tie wrap.

G. Bridle ring supports shall be installed at five foot (5') intervals. All rings shall be installed where completely accessible and not blocked by piping, ductwork, inaccessible ceilings, etc.

H. Open cable shall only be installed where specifically shown on the drawings, or permitted in these specifications.

3.4 WIRING CONNECTIONS AND TERMINATIONS

A. Splice and tap only in accessible junction boxes.

B. Use solderless, tin-plated copper, compression terminals (lugs) applied with circumferential crimp for copper conductor terminations, 8 AWG and larger.

C. Use solderless, tin-plated, compression terminals (lugs) applied with indenter crimp for copper conductor terminations, 10 AWG and smaller.

D. Use solderless pressure connectors with insulating covers for copper wire splices and taps, 8 AWG and smaller. For 10 AWG and smaller, use insulated spring wire connectors with plastic caps.

E. Use copper, compression connectors applied with circumferential crimp for copper wire splices and taps, 6 AWG and larger. Tape uninsulated conductors and connectors with electrical tape to 150 percent of the insulation value of conductor.

Replace Emergency Generator, USDA-ARS 26 05 13 - 4

Bailey Edward Project Number: 0413-07-08

F. Thoroughly clean wires before installing lugs and connectors.

G. Make splices, taps and terminations to carry full ampacity of conductors without perceptible temperature rise.

H. Terminate spare conductors with electrical tape, unless otherwise indicated on the drawings.

I. Phase Sequence: All apparatus shall be connected to operate in the phase sequence A-B-C representing the time sequence in which the phase conductors so identified reach positive maximum voltage.

J. As a general rule, applicable to switches, circuit breakers, starters, panelboards, switchgear and the like, the connections to phase conductors are intended thus:

Facing the front and operating side of the equipment, the phase identification shall be:

Left to Right - A-B-C Top to Bottom - A-B-C

K. Connection revisions as required to achieve correct rotation of motors shall be made at the load terminals of the starters or disconnect switches.

3.5 FIELD QUALITY CONTROL

A. Field inspection and testing will be performed under provisions of Division 1.

B. Cable Testing: Test shall be made by means of an insulation testing device such as a “Megger” using not less than 500 volts D.C. test potential.

C. Inspect wire and cable for physical damage and proper connection.

D. Torque test conductor connections and terminations to manufacturer's recommended values.

E. Perform continuity test on all power and equipment branch circuit conductors. Verify proper phasing connections.

3.6 WIRE AND CABLE INSTALLATION SCHEDULE

A. Concealed Interior Locations: Building wire in raceways.

B. Exposed Interior Locations: Building wire in raceways.

C. Above Accessible Ceilings: Building wire in raceways.

D. Wet or Damp Interior Locations: Building wire in raceway.

E. Exterior Locations: Building wire in raceways.

F. Underground Locations: Building wire in raceways.

Replace Emergency Generator, USDA-ARS 26 05 31 - 1

SECTION 26 05 31

BOXES

1.1 SECTION INCLUDES

A. Pull and junction boxes B. Accessories

1.2 REFERENCES

A. ANSI/NEMA OS 1 - Sheet-Steel Outlet Boxes, Device Boxes, Covers and Box Supports

B. NEMA 250 - Enclosures for Electrical Equipment (1000 Volts Maximum)

C. Federal Specification A–A–50563 – Conduit Outlet Boxes, Bodies, and Entrance Caps, Electrical Cast Metal

PART 2 - PRODUCTS

2.1 PULL AND JUNCTION BOXES

A. Sheet Metal Boxes: ANSI/NEMA OS 1; galvanized steel.

B. Sheet Metal Boxes Larger than 12 Inches in Any Dimension: Hinged enclosure.

C. Cast Metal Boxes for Outdoor and Wet Location Installations: NEMA 250; Type 4 and Type 6, flat-flanged, surface-mounted junction box, UL listed as raintight. Galvanized cast iron box and cover with ground flange, neoprene gasket, and stainless steel cover screws.

D. Cast Metal Boxes for Underground Installations: NEMA 250; Type 4, inside flanged, recessed cover box for flush mounting, UL listed as raintight. Galvanized cast iron box and plain cover with neoprene gasket and stainless steel cover screws.

E. Flanged type boxes shall be used where installed flush in wall.

PART 3 - EXECUTION

3.1 BOX INSTALLATION SCHEDULE

A. Galvanized steel boxes may be used in:

1. Concealed interior locations above ceilings and in hollow studded partitions.

2. Exposed interior locations in mechanical rooms and in rooms without ceilings;

higher than 8’ above the highest platform level.

3. Direct contact with concrete except slab on grade.

4. Recessed in stud wall of kitchens and laundries.

Replace Emergency Generator, USDA-ARS 26 05 31 - 2

Bailey Edward Project Number: 0413-07-08

B. Cast boxes shall be used in:

1. Exterior locations.

2. Hazardous locations.

3. Exposed interior locations within 8’ of the highest platform level.

4. Direct contact with earth.

5. Direct contact with concrete in slab on grade.

6. Wet locations.

7. Kitchens and laundries when exposed on wall surface.

3.2 COORDINATION OF BOX LOCATIONS

A. Provide electrical boxes as shown on the drawings, and as required for splices, taps, wire pulling, equipment connections, and code compliance.

B. Electrical box locations shown on the Contract Drawings are approximate, unless dimensioned. Verify location of floor boxes and outlets in offices and work areas prior to rough-in.

C. Locate and install boxes to allow access. Avoid interferences with ductwork, piping, structure, equipment, etc. Where installation is inaccessible, provide access doors.

Coordinate locations and sizes of required access doors with the Architect and General Contractor.

D. Locate and install to maintain headroom and to present a neat appearance.

E. Coordinate locations with Heating Contractor to avoid baseboard radiation cabinets.

3.3 PULL AND JUNCTION BOX INSTALLATION

A. Locate pull boxes and junction boxes above accessible ceilings or in unfinished areas.

B. Support pull and junction boxes independent of conduit.

3.4 EXPOSED BOX INSTALLATION

A. Boxes shall be secured to the building structure with proper size screws, bolts, hanger rods, or structural steel elements.

B. On brick, block and concrete walls or ceilings, exposed boxes shall be supported with no less than two (2) Ackerman-Johnson, Paine, Phillips, or approved equal screw anchors or expansion shields and round head machine screws. Cast boxes shall not be drilled.

C. On steel structures, exposed boxes shall be supported to the steel member by drilling and tapping the member and fastening the boxes by means of round head machine screws.

D. Boxes may be supported on steel members by APPROVED beam clamps if conduit is supported by beam clamps.

Replace Emergency Generator, USDA-ARS 26 05 31 - 3

Bailey Edward Project Number: 0413-07-08

E. Boxes shall be fastened to wood structures by means of a minimum of two (2) wood screws adequately large and long to properly support. (Quantity depends on size of box.)

F. Wood, plastic, or fiber plugs shall not be used for fastenings.

G. Explosive devices shall not be used unless specifically allowed.

Replace Emergency Generator, USDA-ARS 26 05 33 - 1

SECTION 26 05 33

CONDUIT

1.1 SECTION INCLUDES

A. Rigid metallic conduit and fittings B. Intermediate metallic conduit and fittings C. Electrical metallic tubing and fittings D. Flexible metallic conduit and fittings E. Liquidtight flexible metallic conduit and fittings

1.2 REFERENCES

A. American National Standards Institute (ANSI):

1. ANSI C80.1 - Rigid Steel Conduit, Zinc-Coated

2. ANSI C80.3 - Electrical Metallic Tubing, Zinc-Coated and Fittings

3. ANSI C80.4 - Fittings for Rigid Metal Conduit and Electrical Metallic Tubing

4. ANSI C80.6 – Intermediate Metal Conduit, Zinc Coated

5. ANSI C80.5 – Aluminum Rigid Conduit

B. Federal Specifications (FS):

1. A–A–50553A – Fittings for Conduit, Metal, Rigid, (Thick-Wall and Thin-Wall (EMT) Type

2. A–A–55810 – Specification for Flexible Metal Conduit

C. NECA “Standards of Installation”

D. National Electrical Manufacturers Association (NEMA):

1. ANSI/NEMA FB 1 – Fittings, Cast Metal Boxes, and Conduit Bodies for Conduit, Electrical Metallic Tubing and Cable

2. RN 1 – Polyvinyl chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit

3. TC 2 – Electrical Polyvinyl Chloride (PVC) Conduit

4. TC 3 – PVC Fittings for use with Rigid PVC Conduit and Tubing

5. TC14 – Filament-Wound Reinforced Thermosetting Resin Conduit and Fittings

E. National Fire Protection Association (NFPA):

1.