Attach_5_SUBMITTALS__Houston_Santeetlah.docx

DOCX document 16 KB Posted

Attached to
Houston Dam Removal Federal contract opportunity
Solicitation number
AG-4670-S-15-0105
Issued by
Department of Agriculture Forest Service

About this file

Atch 5 Submittals

View the file

Other files for this federal contract opportunity

Other files attached to Houston Dam Removal, newest first.
File Type Posted
AMnedment_01__Attachment_4_Drawings_Complete_Revised_7_09_2015.pdf PDF
amendment_1.pdf PDF
Attach_2_HOUSTON_and_SANTEETLAH_SPECS.doc DOC document
Attach_6_DOL_NC68.txt TXT text file
Solicitation_SF_1442.doc DOC document
Attach_4_Houston_Drawings_Complete.pdf PDF
Attach_1_SCHEDULE.pdf PDF
Attach_3_Site_Location.pdf PDF
Attach_7__Experience_Questionaire.doc DOC document
Road_Construction_RFQ.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTALS

The Contractor shall mail required submittals to Barry Jones, Assistant Forest Engineer, 160 Zillacoa Street, Asheville, NC 28801. Email is also an acceptable form of submission; Barry Jones - jbjones@fs.fed.us.

The Contractor shall maintain one approved set of submittals at the worksite and provide access to these submittals for the Contracting Officer and interested Government agencies.

List of Required Submittals For further details see the Technical Specifications.

Winthrop to Bear Creek Piping - Submittals

Submittal number
Location of submittal requirements in tech spec
Submittals required
Due date or delivery time:
No. of sets to be sent to:

USFS

Schedule of work
No more than 15 days after the award of the contract
1
1
Safety plan
Not less than 2 days prior to mobilization
1
1
Weather/Rain Monitoring plan
Not less than 2 days prior to mobilization
1
1
List of Hazardous Materials (LHM) and Material Safety Data Sheets (MSDS) and Updated LHM and MSDS
At least 15 days before delivering hazardous materials to the site
1
1
Traffic control plan
Not less than 15 days prior to mobilization
1
1
Water quality management plan
Not less than 2 days prior to mobilization
1
1
As-built drawings
At least 15 days prior to submitting request for final payment
1
1
Field survey notes and field books
At least 15 days prior to submitting request for final payment
1
1
Removal of water plan
Not less than 7 days prior to start of activity
1
1