Attach_1_SCHEDULE.pdf

PDF 18 KB Posted

Attached to
Houston Dam Removal Federal contract opportunity
Solicitation number
AG-4670-S-15-0105
Issued by
Department of Agriculture Forest Service

About this file

Atch 1 Schedule of Items

View the file

Other files for this federal contract opportunity

Other files attached to Houston Dam Removal, newest first.
File Type Posted
AMnedment_01__Attachment_4_Drawings_Complete_Revised_7_09_2015.pdf PDF
amendment_1.pdf PDF
Attach_2_HOUSTON_and_SANTEETLAH_SPECS.doc DOC document
Attach_6_DOL_NC68.txt TXT text file
Solicitation_SF_1442.doc DOC document
Attach_4_Houston_Drawings_Complete.pdf PDF
Attach_3_Site_Location.pdf PDF
Attach_7__Experience_Questionaire.doc DOC document
Road_Construction_RFQ.docx DOCX document
Attach_5_SUBMITTALS__Houston_Santeetlah.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6/19/2015

Contract MCAON-032

ITEM NO. DESCRIPTION

METHOD

OF

MEASURE

UNIT Quantity Unit Price TOTALS

15101 Mobilization LSQ LS 1 $_____________ $____________

15201

Construction survey and staking, Method 1, Precision class B As Built Topo Drawing (1 foot contours) Tolerance B

LSQ LS 1 $_____________ $____________

15702 Sedimentation, Pollution & Erosion Control (Temp.

Seeding and Mulching, Rock Check Dams, Silt Fence, Etc)

LSQ LS 1 $_____________ $____________

20801 Dewatering Structures (dams), sediment basins, pumps, sediment bags, bypass pipe excavation and placement and removal

LSQ LS 1 $_____________ $____________

20304 Removal of Existing Pond Drainage Structures, including access road culvert (complete removal and disposal)

LSQ LS 1 $_____________ $____________

20801 Earth Excavation includes haul and placement at borrow site (approx. 800 CY)

LSQ LS 1 $_____________ $____________

30109 Aggregate Surface Course, Grading ABC Compaction Method A.

AQ Ton 150 $_____________ $____________

30110 3" Railroad Ballasts for Access Road Entrance AQ Ton 300 $_____________ $____________

30111 Stream Bed Boulders (36" x 20" x 12") Machine Placed

AQ Ton 75 $_____________ $____________

62201 Stream Restoration - Equipment Rental for Stream Restoration - CAT 312 or equal (includes placement of log and boulder structures directed by USFS)

AQ HR 140.0 $_____________ $____________

62202 Equipment Rental - Excavator with Hoe Ram / Hydraulic Hammer CAT 320 or larger (5000 psi Min.

Burst Strength)

AQ HR 60.0 $_____________ $____________

62615a Betula lenta - Sweet/Black/Cherry Birch AQ EA 3 $_____________ $____________

62615b Carya ovata - Shagbark Hickory AQ EA 2 $_____________ $____________

62615c Platanus occidentalis - American Sycamore AQ EA 2 $_____________ $____________

62615d Aronia arbutifolia - Red Chokeberry AQ EA 9 $_____________ $____________

62615e Alnus serrulata - Tag Alder AQ EA 5 $_____________ $____________

62615f Diervilla sessifolia - Southern Bush Honeysuckle AQ EA 3 $_____________ $____________

62615g Viburnum prunifollium - Blackhaw AQ EA 6 $_____________ $____________

62615h Rhododendron calendulaceum - Flame Azalea AQ EA 3 $_____________ $____________

62615i Hypericum densiflorum - Bushy St. John's Wort AQ EA 6 $_____________ $____________

62615j Lindera benzoin - Spicebush AQ EA 6 $_____________ $____________

62615k Itea verticillata 'red sprite' - Red Sprite Common Winterbe AQ EA 2 $_____________ $____________

62615l Itea virginica - Virginia Sweetspire AQ EA 5 $_____________ $____________

62615m Clethra acuminata - Mountain Pepperbush AQ EA 6 $_____________ $____________

62615n Asclepias incarnata - Swamp Milkweed AQ EA 8 $_____________ $____________

62615o Lobella cardinalis - Cardinal Flower AQ EA 4 $_____________ $____________

62615p Eutrochium fistulosum - Joe-pye Weed AQ EA 6 $_____________ $____________

SCHEDULE OF ITEMS

(PUBLIC WORKS)

Dam Number Houston Dam Removal and Stream Restoration State ID Number MACON-032

6/19/2015

62615q Monarda didyma - Beebalm AQ EA 5 $_____________ $____________

62615r Xanthorhiza simplicissima - Yellowroot AQ EA 7 $_____________ $____________

62615s Carex stricta - Upright/Tussock Sedge AQ EA 9 $_____________ $____________

62615t Carex vulpinoides - Fox Sedge AQ EA 5 $_____________ $____________

62708 Furnishing and Placing Native Grass Sod AQ SF 43,560 $_____________ $____________

62909 Erosion Control COIR Matting 700 AQ SY 4,000 $_____________ $____________

63527 Tempoary Traffic Control LSQ LS 1 $_____________ $____________

64805 Placed streambed simulation rock Bed class 24, Method D

AQ Ton 200 $_____________ $____________

70001 Various Planting and Live Stakes LSQ LS 1 $_____________ $____________

70002 Log Vane Root Wads and Tree Stem (Material only) AQ EA 20 $_____________ $____________

TOTAL $__________

ITEM NO. DESCRIPTION

METHOD OF

MEASURE UNIT Quantity Unit Price TOTALS

15101 Mobilization LSQ LS 1 $_____________ $____________

15201

Construction survey and staking, Method 1, Precision class B Existing Topo and As Built Topo Complete Drawing (1 foot contours) Tolerance B

LSQ LS 1 $_____________ $____________

15702 Sedimentation, Pollution & Erosion Control (Temp.

Seeding and Mulching, Rock Check Dams, Silt Fence, Etc)

LSQ LS 1 $_____________ $____________

20801 Concrete Dam Removal Excavation includes haul and disposal off National Forest Lands properly

LSQ LS 1 $_____________ $____________

30111 Stream Bed Boulders (36" x 42" x 48") Machine Placed

AQ Ton 75 $_____________ $____________

62201 Stream Restoration - Equipment Rental for Stream Restoration - CAT 312 or equal (directed by USFS)

AQ HR 36.0 $_____________ $____________

62909 Erosion Control COIR Matting 700 AQ SY 400 $_____________ $____________

63527 Temporary Traffic Control LSQ LS 1 $_____________ $____________

SANTEETLAH BARRIER REMOVAL COMPLETE

TOTAL BASE (HOUSTON) + BID OPTION (SANTEETLAH):

As stated in FP-03, Subsection 109.05, payment for all contract work is provided, either directly or indirectly, under the pay items shown in the bid schedule. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items shown in the

BASE BID (Houston Dam Removal):

SANTEETLAH FISH BARRIER REMOVAL BID OPTION ITEM-

File details come from the government source that posted it. Updated .