Revised Page 6.pdf
PDF 47 KB Posted
- Attached to
- Catawba Falls Parking Lot Construction Federal contract opportunity
- Solicitation number
- AG-4568-S-11-0060
- Issued by
- Department of Agriculture Forest Service
About this file
Revised Page 6
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised Page 15.pdf | ||
| PreBid Mtg Signin.pdf | ||
| AMD 003_SF30.pdf | ||
| PHASE I BID SCHEDULE REVISED 8_23_2011.docx | DOCX document | |
| AMD 002_SF 30.pdf | ||
| AMD001 SF30.pdf | ||
| ATT5 Experience Questionnaire.docx | DOCX document | |
| RFP SF1442.pdf | ||
| ATT 2 DB WAGES.docx | DOCX document | |
| ATT4_Drawings.pdf | ||
| RFP_body.docx | DOCX document | |
| ATT 1 BID SCHEDULE.docx | DOCX document | |
| ATT3 SPECS.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-4568-S-11-0060
AMENDMENT 003 NFNC, Grandfather Ranger District Catawba Falls Parking Lot Construction
STATEMENT OF WORK
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
This procurement is for one solicitation resulting in the award of a single Firm Fixed Price construction contract for the National Forests of North Carolina (NFsNC), for Catawba Falls Parking Lot, on the Grandfather Ranger District, Pisgah National Forest, in McDowell County, Nebo, NC.
Offerors are required to submit price and technical proposals as specified in Section L of this solicitation. Proposals will be evaluated in accordance with Section M of this solicitation.
1. DESCRIPTION AND LOCATION
Description: The purpose and intent of this contract is for construction in the National Forests of North Carolina, Grandfather Ranger District, per Section J, Attachment 3, Specifications, and Attachment 4, Drawings.
Location: State of North Carolina - National Forests of North Carolina, Grandfather Ranger District, McDowell County, Nebo, NC.
Technical Specifications: Technical specifications are found in Attachment 3
Contractor shall notify the Contracting Officer’s Representative (COR) when leaving the project area for three or more days and within 24 hours after returning to the project area. Each week, unless otherwise approved, the Contractor shall report his location and progress of work in writing to theCOTRto permit timely inspection and acceptance of completed work by the Government.
NOTE: " If contractor grinds / chips clearing and grubbing brush into mulch, mulch shall be placed at locations designated by the COTR within the project area"