ATT 1 BID SCHEDULE.docx
DOCX document 27 KB Posted
- Attached to
- Catawba Falls Parking Lot Construction Federal contract opportunity
- Solicitation number
- AG-4568-S-11-0060
- Issued by
- Department of Agriculture Forest Service
About this file
ATT1 BID SCHEDULE
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised Page 15.pdf | ||
| PreBid Mtg Signin.pdf | ||
| AMD 003_SF30.pdf | ||
| PHASE I BID SCHEDULE REVISED 8_23_2011.docx | DOCX document | |
| Revised Page 6.pdf | ||
| AMD 002_SF 30.pdf | ||
| AMD001 SF30.pdf | ||
| ATT5 Experience Questionnaire.docx | DOCX document | |
| RFP SF1442.pdf | ||
| ATT 2 DB WAGES.docx | DOCX document | |
| ATT4_Drawings.pdf | ||
| RFP_body.docx | DOCX document | |
| ATT3 SPECS.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GRANDFATHER RANGER DISTRICT
CATAWBA FALLS RECREATION AREA
TRAILHEAD PARKING LOT CONSTRUCTION
PHASE I
BID SCHEDULE
*Pay Item Description Quantity Unit Unit Price Amount
| 1. | MOBILIZATION & BONDING | 1 | LS | $ |
| (Not to exceed 7.5% of total bid) |
| 2. | CLEARING & GRUBBING | 1 | LS | $ |
| Including disposal |
3. SURVEY & LAYOUT 1 LS $
| 4. | ROADWAY/ PARKING LOT | 1 | LS | $ |
| Excavation & Disposal |
| 5. | SOIL REINFORCING FABRIC | 3,300 | SY | $ | $ |
| (overlapping is incidental to quantity shown) |
| 6. | 6” THK. ROADWAY BASE | 1,300 | TONS | $ | $ |
| NC DOT approved ABC stone |
7. ROCK DUST SURFACING 16 TONS $ $
| 8. | 24” DIA. DRAINAGE CULVERT | 80 | LF | $ | $ |
| 9. | TRAFFIC SIGNS | 11 | EA | $ | $ |
| 10. | 2-UNIT VAULT TOILET | 1 | LS | $ | |
| Includes solar fans |
11. 4” THK. CONCRETE SIDEWALK 426 SF $ $
| 12. | WOODEN WHEEL STOPS | 30 | EA | $ | $ |
| 13. | 6x6 P.T. DELINEATOR POSTS | 11 | EA | $ | $ |
| 14. | 3-PANEL BULLETIN BOARD | 1 | LS | $ |
| Complete incl. concrete foundation |
15. GARBAGE CONTAINERS 2 EA $ $
*Pay Item Description Quantity Unit Unit Price Amount
| 16. | EROSION & SEDIMENTATION | |
| Control |
A. SILT FENCE 1,550 LF $ $
B. 1RST. STAGE DRAINAGE 1 LS $
DITCH/POND Construction
C. 2ND. STAGE DRAINAGE 1 LS $
DITCH/POND/RAIN GARDEN
Construction
D. SEEDING & MULCHING 1 LS $
TOTAL PRICE $