Lake Eaton Boardwalk schedule of items REVISED 04-01-2010.pdf
PDF 17 KB Posted
- Attached to
- Repair/Replace Boardwalks and Deck Sections
- Solicitation number
- AG-4419-S-10-0474
About this file
Revised Schedule of Items
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REVISED LK EATON BOARD WALKS.pdf | ||
| Modification 01_Lake Eaton Board Walks.pdf | ||
| RFP_Lake Eaton Boardwalks.docx | DOCX document | |
| LAKE EATON BOARDWALKS SHEETS 1-3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
Ocala National Forest Lake Eaton Sinkhole Boardwalk and Deck Rehabilitation
METHOD OF UNIT
ITEM NO. DESCRIPTION MEASURE UNIT QUANTITY PRICE TOTAL
BASE BID:
1. Lake Eaton Sinkhole
a. Remove and dipose of the existing wood decking and steps. Install 2”x6” rough sawn pressure treated lumber for the new decking and 2”X12” treads for steps.
(See drawings for details)
S.F. A.Q. 2415 $_________ $__________
b. Remove and dispose of the existing railing. Install new railing as shown on the drawings. Replace existing 4”x4” or 6”X6” post as needed.
L.F. A.Q. 825 $_________ $__________
c. Remove and replace the existing 2’ wide X 15’ long bench.
L.S. EA 1 $_________ $__________
d. Remove and replace the existing 2’ wide X 11’ long bench.
2. Lake Eaton Loop Trail A existing wood decking. Install 2”x6” rough sawn pressure trated lumber for the new decking and 2”X12” treads for steps
S.F. A.Q. 1177 $_________ $__________ shown on the drawings. Replace existing 4”x4” or 6”X6” post as needed.
L.F. A.Q. 371 $_________ $__________
3. Lake Eaton Loop Trail B
2”x6” rough sawn pressure treated lumber for the new decking.
S.F. A.Q. 1302 $_________ $__________ shown on the drawings. Replace existing 4”x4” or 6”X6” post as needed.
L.F. A.Q. 320 $_________ $__________
2’ wide X 11’ long bench.
d. Remove and replace the existing 2’ wide X 8’ long bench.
4. Lake Eaton Loop Trail C
2”x6” rough sawn pressure treated lumber for the new decking.
S.F. A.Q. 1280 $_________ $__________ shown on the drawings. Replace existing 4”x4” or 6”X6” post as needed.
L.F. A.Q. 375 $_________ $__________
2’ wide X 10’ long bench.
5. Install new 2”x6” P.T. rough sawn beam as needed. Work shall include all materials and labor for removal of existing material and installation of new material.
L.F. A.Q. 130 $_________ $__________
6. Install new 2”x8” P.T. rough sawn beam as needed. Work shall include all materials and labor for removal of existing material and installation of new material.
L.F. A.Q. 130 $_________ $__________
7. Install new 2”x12” P.T. rough sawn beam as needed. Work shall include all materials and labor for removal of existing material and installation of new material.
L.F. A.Q. 130 $_________ $__________
8. Install new 2”x12” P.T. rough sawn Step stringer as needed. Work shall include all materials and labor for removal of existing material and installation of new material.
L.F. A.Q. 130 $_________ $__________
9. Install new 6”x6” rough sawn posts as needed. Work shall include all materials and labor.
L.F. A.Q. 130 $_________ $__________
10. Install new 4”x4” rough sawn posts as needed. Work shall include all materials and labor.
L.F. A.Q. 130 $_________ $__________
TOTAL $__________
L.S. = Lump Sum L.F. = Linear Feet EA = Each S.F. = Square Feet A.Q. = Actual Quantities