SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

11. The contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

AG-05M6-S-15-0052 X 7/14/2015

750868 05M6

USDA Forest Service Mt. Baker-Snoqualmie National Forest ATTN: Brian A. Johnson, Contracting Officer 2930 Wetmore Ave., Suite 3A Everett, WA 98201-4067

Same as Block 7

Brian A. Johnson (425) 783-6056, bajohnson03@fs.fed.us

SULPHUR CREEK CAMPGROUND RESTORATION

Mt. Baker-Snoqualmie National Forest

Darrington Ranger District Washington State

(Snohomish County)

15 60 X X

X Fourteen (14)

X

1 1530 August 10, 2015

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 1 of 151

1 151 bajohnson03 Highlight bajohnson03 Highlight

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 4-85) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

20b. SIGNATURE 20c. OFFER DATE

DUNS No.: _____________ E-mail: __________________

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 2 of 151

PART I—BID SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SULPHUR CREEK CAMPGROUND RESTORATION

Mt. Baker-Snoqualmie National Forest

Darrington Ranger District Washington State, Snohomish County

B.1 SCHEDULE OF ITEMS (Page 1 of 2)

SULPHUR CREEK CAMGROUND RESTORATION

ITEM # DESCRIPTION PAY

UNIT

EST.

QTY

UNIT

PRICE

TOTAL

COST

15101 Mobilization LS 1 $ $

15201 Construction Survey and Staking, Method 1, Tolerance C LS 1 $ $

20102 Clearing and Grubbing (0.067 Acres) New Parking Areas LS 1 $ $

*20301 Removal, Toilets, Disposal Method D EA 2 $ $

20491 Roadway Excavation and Embankment, Borrow Material for Subgrade, Compaction Method B - Green Mtn. Pit

CY 100 $ $

25101 Placed Barrier Rock EA 33 $ $

30322 Road Reconditioning LS 1 $ $

32451A Aggregate Base, 5/8" Minus, WSDOT Mix, Compaction Method B TN 500 $ $

32451B Aggregate Base, 1 1/4" Minus, WSDOT Mix, Compaction Method B TN 300 $ $

62201A Equipment Rental, Excavator HR 8 $ $ 62201B Equipment Rental, Dump Truck HR 4 $ $ 62201C Equipment Rental, Grader HR 8 $ $

62501 Turf Establishment, Seed Mix A, Wood Straw 3000 Lb/Acre AC 0.25 $ $

91201 Trail Construction - Approx. 100', 5/8” Minus Surfacing Aggregate Included LS 1 $ $

136010-1 Pre-Engineered Building, Double Vault Toilet LS 1 $ $

Total: $

* = Contract Quantity AC = Acre CY = Cubic Yard EA = Each LF = Linear Feet LS = Lump Sum SY = Square Yard TN = Ton

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 3 of 151

B.1 SCHEDULE OF ITEMS (Continued, Page 2 of 2)

Total Bid – Sulphur Creek Campground Restoration: $______________________

Name and Address of Offeror: ________________________________

Authorized Signature: ______________________________________

Title: ________________________________

Date: ______________

B.2 SCHEDULE OF ITEMS NOTES

a. If he Offeror does not intend to charge for an item, a price of "0" or "NO COST" should be shown.

b. The offeror must price all items to be considered for award and only prices to the nearest cent will be accepted.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 4 of 151

SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT

C.1 SCOPE OF WORK

This project consists of roadway and camp spur re-surfacing, roadway reconditioning, vault toilet removal and new installation, trail construction, and construction of new parking areas. The Contractor shall furnish all labor, materials, equipment, tools, transportation and supplies, and perform all work required to reconstruct, decommission, or store the road according to the drawings and specifications of the contract. The Contractor shall assume all risk, loss, damage, or expense arising out of prosecution of the work, except as otherwise provided in the contract. The scope includes everything necessary to complete the project in accordance with the drawings, specifications and provisions of the contract. All appurtenances, fasteners, hardware, connections, etc. to make a complete final product are considered incidental to the work.

C.2 PROJECT LOCATION

The project work area is located on the Darrington Ranger District along Forest Service Road ( FSR) 26 at approximately MP 22.5. (T31N–R12E–Section14) From Everett, WA take I-5 N for 14.4 miles to WA-530 exit 208. Turn right onto State Route 530 NE/WA – 530 and continue past Arlington, WA for 27.6 miles to Darrington,WA and the intersection with the Emens Ave. Turn left onto Emens Ave. and continue on Hwy. 530 for approximately 7.44 miles to the intersection with FSR 26. Turn right onto FSR 26 and head Easterly for approximately 22.5 miles to the project site Sulphur Creek Campground.

C.3 CONTRACT TIME

Sixty (60) calendar days from Notice to Proceed (Includes toilet building submittal and review).

C.4 SPECIFICATIONS

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-

03) and Forest Service Supplemental Specifications noted herein.

These Standard Specifications can be viewed and printed from the following website:

http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm

C.5 MATERIAL CERTIFICATIONS, INVOICES, AND TESTING REPORTS

Materials associated with the following Pay Items will require certifications and/or testing reports submitted to the Contracting Officer Representative.

Pay Item Material Requirement

32451A&B Aggregate Base Material Certification 62529 Seeding Mix A Material Certification

62529 Mulch Material Certification 136010-1 Double Vault Toilet Submittal

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 5 of 151 http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm

C.6 GOVERNMENT FURNISHED PROPERTY

The Government will provide the following item of Government property to the Contractor for use in the performance of this contract. This property shall be used, maintained and installed by the Contractor.

• FSR 2680 MP 2.4 Green Mountain Pit – Borrow Material

C.7 CONSTRUCTION WORK DAYS AND HOURS

Contract Time is sixty (60) calendar days for all project work. No work is allowed on weekends or Federal Holidays without written request by the Contractor to the CO for review and approval.

C.8 WILDLIFE RESTRICTIONS (INCLUDING FISHERIES)

For fish and wildlife considerations, the following restrictions are applicable to this contract:

No mechanical equipment generating noise above ambient levels shall occur prior to 2 hours after official sunrise and shall stop 2 hours before official sunset between April 1 to September 15 annually. This requirement is to minimize potential adverse effects to breeding marbled murrelets within forest tree canopies with suitable nesting branch structure.

C.9 DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECT

Between $100,000 and $250,000

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 6 of 151

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 7 of 151

SECTION E – INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Title Date 52.246-12 Inspection of Construction AUG 1996

E.2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at the project site.

E.3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT

The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.

E.4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 8 of 151 http://www.arnet.gov/far/

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

Clause Number Title Date

52.242-14 Suspension of Work APR 1984

F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within fifteen

(15) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than sixty (60) calendar days. The time stated for completion shall include final cleanup of the premises.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 9 of 151

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within ten (10) work days after the date of contract award. The conference will be held at: Darrington Ranger Station, 1405 Emens Street, Darrington, WA 98284.

G.2 CONTRACTOR INVOICE CERTIFICATION

When submitting partial payments the contractor shall submit the following certification with each invoice submission. This certification shall be attached in the Invoice Processing Platform (IPP) at www.ipp.gov:

CONTRACTOR CERTIFICATION

(FAR 52.232-5 Payments under Fixed-Price Construction Contracts)

I hereby certify, to the best of my knowledge and belief, that—

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.

(Signature / Printed Name)*

(Title)

(Date)

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 10 of 151 http://www.ipp.gov/

G.3 CONTRACT RELEASE

When submitting the final invoice via IPP, the contractor shall provide a signed and dated Contract Release that includes the following information:

"In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein. Reservations, if any:______________."

G.4 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE

The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly.

(This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).

On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits.

Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G.5 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE

PROCESSING PLATFORM (IPP)

(a) Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract.

The IPP website address is: https://www.ipp.gov

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 11 of 151 https://www.ipp.gov/ mailto:IPPCustomerSupport@fms.treas.gov

(b) In addition, when submitting the invoice, the Contractor shall submit payrolls, subcontractor payment information and a spreadsheet detailing the payment breakdown in accordance with the Pay Items in the Schedule of Items, Section B.1 (either electronically in IPP, hard copy, or via fax) to the Contracting Officer (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).

G.6 CONTRACTOR’S DESIGNATED REPRESENTATIVE

It is required that the Contractor have a designated representative available on the project during the entire project and that the representative be able to speak and understand English.

When designating a representative, the Contractor shall furnish a copy of the designation in writing to the Contracting Officer. Such designation shall clearly indicate the name and limitations (if any) of authority of the representative. If the Contractor intends to designate a representative prior to the pre-work meeting, the representative is strongly encouraged to attend that meeting.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 12 of 151

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS ( FAR 52.236-9) (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

H.2 USE OF PREMISES

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless provided otherwise, the Contractor shall: (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State, and local regulations.

H.3 ARCHAEOLOGICAL OR HISTORIC SITES (USDA 452.236-73) (FEB 1988)

If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

H.4 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (USDA

452.236-74) FEB 1988)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 13 of 151

(b) Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or near rivers, streams, and impoundments; or into natural or manmade channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H.5 RIGHTS IN AND USE OF MATERIALS

(a) The Contractors, with the written approval of the Contracting Officer, may use on the project suitable stone, gravel, and sand or other material found in the excavation. Payment will be made both for the excavation of such materials at the corresponding contract unit price and for the pay items for which the excavated material is used. The Contractor shall replace without additional compensation sufficient suitable materials to complete the portion of work which was originally contemplated to be constructed with such material.

(b) Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to reimburse the Contractor for the cost of their production.

H.6 STORAGE AND STOCKPILING OF MATERIALS

Material shall be stored to assure the preservation of quantity and fitness for the work.

Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by Forest Service shall be restored at Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered land.

H.7 EMERGENCY RESPONSE (USDA 452.236-77) (NOV 1996)

(a) Contractor's Responsibility for Fighting Fire. (1) The Contractor, under the provision of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish, all fires on the work site other than those fires in use as a part of the work. (2) The contractor may be held liable for all damages and for all costs incurred by the Government for labor subsistence, equipment, supplies, and transportation deemed necessary to suppress a fire set or caused by the Contractor or the Contractor's agent or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergency. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to restrict to

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 14 of 151 fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.

H.8 LANDSCAPE PRESERVATION

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products onsite, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states.

Servicing of all equipment shall be done only in the area approved by the Contracting Officer.

If the total oil or oil products storage exceeds 6,000 litters or if any single container exceeds a capacity of shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

The Contractor will be required to make reasonable attempts to preserve the scenic and natural environment along this construction project.

(c) Trash and Refuse - Contractor shall remove all of his own trash and refuse from the contract area. Material to be removed includes, but is not limited to; used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper, garbage, etc. This material must be removed to a State, County, or Municipality-designated solid waste disposal area.

H.9 CONTROL OF NOXIOUS WEEDS--CLEANING OF EQUIPMENT

To prevent the introduction and control the spread of seeds of noxious weeds onto and around National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. When the Contractor is working in an area that has been identified as a noxious weed infestation area, the Contractor shall ensure equipment is cleaned of weed seeds prior to moving to another work area on the Forest. The Contractor shall employ whatever cleaning methods necessary to ensure compliance with the terms of this provision, and shall notify the Forest Service for an inspection prior to moving each piece of equipment onto National Forestland, unless otherwise agreed in writing. Notification will include identifying the location of the equipment's most recent operations.

The Contractor shall certify, in writing, compliance with the terms of this clause prior to each start-up of operations. For the purposes of this clause, "equipment" includes all motorized equipment operated off system roads, transport vehicles, and all motorized

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 15 of 151 equipment used in road maintenance. Not included are log trucks, chip vans, pickup trucks, cars, or other vehicles used to daily transport personnel.

H.10 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Forest Personnel.

Weather Conditions: Expect mild or temperate weather conditions. Occasional rain showers would not be unexpected during the summer season.

Elevation of this project: 1600 feet

Transportation facilities: Road access is good – Overload permits required on bridges.

Allow 21 days for permits. FSR 26, Suiattle, is double lane paved from MP 0 to MP 10 and a single lane gravel road from MP 10 to MP 22.8. There are Two Concrete Ford dips and Three bridges to negotiate on FSR 26. On FSR 2680, Green Mtn (where borrow pit is located) a single lane gravel road exists. Condition of this road is standard but narrow in some locations.

Other Physical Data: Seasonal Conditions exist. Expect dry to wet soils.

H.11 FIRE PROTECTION REQUIREMENTS

The following fire requirements are attached in Section J and are applicable:

Fire Protection and Suppression, R6-FS-6300-52 (5/97)

Additional Fire Precautionary Measures - Tank Truck, R6-FS-6300-53 (5/89)

Additional Fire Precautionary Measures - Communications, R6-FS-6300-54 (5/89)

H.12 WDFW-USFS INTERIM MOU PROVISIONS (JAN 2012)

A copy of this Contract Requirement must be on-site at all times when work is being conducted under this contract.

The following provisions are applicable to this contract:

GENERAL PROVISIONS APPLICABLE TO ALL APPENDIX A PROJECTS

Timing

1. Freshwater hydraulic projects shall normally be implemented only during the work periods outlined in Appendix D. Other timing will be allowed on a site-specific basis if the Forest Service fish biologist and WDFW Area Habitat Biologist agree that implementing the activity outside of the normal period would be unlikely to cause negative impacts to fish. Any agreements to modify the

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 16 of 151 work periods in Appendix D for specific projects or specific sites shall be documented by WDFW.

2. Those portions of hydraulic project work that occur outside or above the bank full channel and have little or no potential to negatively affect fish or fish habitat are not subject to the work periods specified in Appendix D. Examples of such work include replacing bridge decking, constructing a bridge superstructure after footings are in place, and building up the fill of a culvert that is in place.

These projects are still bound the other provisions in Appendix A. The Forest Service shall notify the appropriate WDFW Regional Habitat Program Manager prior to implementing work on these hydraulic projects outside the work periods specified in Appendix D.

3. Hydraulic projects conducted in intermittent non-fish-bearing streams that are dry during the proposed work are not subject to the work periods specified in Appendix D unless USFS fish biologist determine the activities are likely to negatively affect fish life, in which case the work periods specified in Appendix D apply.

4. Hydraulic projects conducted in wetted non-fish-bearing streams that are greater than ¼ mile from fish-bearing water are not subject to the work periods specified in Appendix D unless USFS fish biologist determine the activities are likely to negatively affect fish life, in which case the work periods specified in Appendix D apply.

Fish Protection

5. Any pump used for diverting water from a fish-bearing waterbody shall be equipped with a fish guard to prevent passage of fish into the pump. The pump intake shall be screened with 3/32 inch or smaller mesh. Screen maintenance shall be adequate to prevent injury or entrapment to juvenile fish and shall remain in place whenever water is withdrawn from the water body through the pump intake.

6. Fish within construction sites that will be dewatered or isolated from the main water body will be captured and safely moved from the job site. Fish capture and transportation equipment shall be available on the job site during all in water activities.

7. If at any time, as a result of project activities, a fish kill occurs, fish are observed in distress, or water quality problems develop that may present a threat to fish life, the Forest Service shall immediately notify the appropriate WDFW Regional Habitat Program Manager. Outside of business hours, notification shall be made to the Washington State Emergency Management Division of the Department of Ecology at 1-800-258-5990.

Erosion and Wastewater Control

8. Alteration or disturbance of the bed, banks, and vegetation of waterbodies shall be minimized and limited to that necessary to construct the project.

9. Erosion prevention and control methods shall be used as necessary during and immediately after project implementation to minimize loss or displacement of soils and to prevent delivery of sediment into water body. These may include, but are not limited to, operational techniques, straw bales, silt fencing, erosion control blankets, temporary sediment ponds, and/or immediate mulching of exposed areas. Disturbed ground with the potential to deliver sediment into water bodies shall be re-vegetated or protected from surface erosion by seeding, mulching, other methods prior to the fall

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 17 of 151 rainy season.

10. After project completion, disturbed stream banks and lakeshores shall be re-vegetated with site-appropriate vegetation to maintain soil stability and provide shade and future sources of large wood.

11. Wastewater from project activities shall be routed to an area outside the bank full channel to allow removal of fine sediment and other contaminants prior to infiltrating back into water bodies.

Heavy Equipment

12. The use of heavy equipment within the bank-full channel in streams and below the ordinary high water line in lakes is discouraged. If such work is necessary, operation of heavy equipment in these areas shall be minimized.

13. Accumulations of soil or debris shall be removed from drive mechanisms (wheels, tires, tracks, etc.)

and undercarriage of all heavy equipment prior to its working within the bank-full channel in streams or below the ordinary high water line in lakes.

14. To prevent contamination, equipment used around water bodies shall be free of external petroleum based products. Equipment shall be checked daily for leaks and any necessary repairs shall be completed prior to commencing work activities. All machinery fueling and maintenance involving petroleum products shall occur at a sufficient distance from stream channels, water bodies, or wetlands to prevent delivery of potential contaminants. Spill containment equipment and material shall be on site.

Concrete and Treated Wood

15. Fresh concrete, concrete by-products or other chemical contaminants shall not be allowed to enter water bodies. Structures containing concrete shall be sufficiently cured to prevent leaching prior to contact with the water body.

16. Treated wood used for hydraulic projects shall meet or exceed the standards established in the most current edition of “Best Management Practices For the Use of Treated Wood in Aquatic Environments” developed by the Western Wood Preservers Institute. At the time of the signing of this MOU, the most current version is the July 1996 edition

PERMANENT CULVERT INSTALLATION AND REPLACEMENT

NOTE: Permanent culvert installation and replacement projects include installation of new culverts that are installed for more than one year and replacement of existing culverts with similar or larger structures.

In addition to the General Provisions Applicable to All Projects, the following project-specific provisions apply when conducting permanent culvert installation or replacement projects.

1. Construction sites shall be dewatered or isolated from flowing waters to prevent generation of sediment and minimize turbidity.

2. Every effort shall be made to avoid stream crossings with heavy equipment. A single round-trip

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 18 of 151 equipment crossing of the stream channel shall be allowed, if necessary. Equipment operation within the stream channel inside of the approximate culvert footprint is permissible so long as the stream has been dewatered.

3. Silt Fence.

H.13 FOREST SERVICE NATIONAL CORE BEST MANAGEMENT PRACTICES

(BMP’S)

• Nonpoint Source Pollution Control for Water Quality Management on National Forest Lands (2010)

The BMPs are a part of this Contract for all the related items of work listed herein. The Contractor shall have a copy of the BMP’s available and on-site at all times. The BMP’s shall be available upon request to the Contracting Officer or his designated representative.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 19 of 151

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

(FAC Number/Effective Date: FAC 2005-83/07-02-2015)

I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity

(MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform

Employees of Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013) 52.204-13 System for Award Management Maintenance (JUL 2013) 52.204-16 Commercial and Government Entity Code Reporting (JUL 2015) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (AUG 2013) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (OCT 2014) 52.219-14 Limitations on Subcontracting (NOV 2011) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005)

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 20 of 151 http://www.usda.gov/procurement/policy/agar.html

52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2015) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUL 2014) 52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (JUL 2014) 52.222-40 Notification of Employee Rights under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2014) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction

Contracts (SEP 2013) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984)

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 21 of 151

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991), Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items ( MAR 2015) 52.245-1 Government Property (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2010) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012), Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

I.2 AGAR 452.209-71 ASSURANCE REGARDING FELONY CONVICTIONS OR

TAX DELINQUENT STATUS FOR CORPORATE APPLICANTS (FEB 2012)

ALTERNATE I (FEB 2012)

(a) This award is subject to the provisions contained in section As prescribed in 25.1102(d)(2), substitute the following paragraph (b) for paragraph (b) of the basic provision:

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11.

433 and 434 of the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, as amended and/or subsequently enacted, regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 22 of 151 https://acquisition.gov/far/current/html/Subpart%2025_11.html%23wp1078063 https://acquisition.gov/far/current/html/52_223_226.html%23wp1193406 liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.

(c) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434.

I.3 FAR 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE

MAINTENANCE (JUL 2015)

(a) Definition. As used in this clause– “Commercial and Government Entity (CAGE) code” means–

(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Contractor and Government Entity (CAGE) Branch to identify a commercial or government entity, or

(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Contractor and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as an NCAGE code.

(b) Contractors shall ensure that the CAGE code is maintained throughout the life of the contract.

For contractors registered in the System for Award Management (SAM), the DLA Contractor and Government Entity (CAGE) Branch shall only modify data received from SAM in the CAGE master file if the contractor initiates those changes via update of its SAM registration.

Contractors undergoing a novation or change-of-name agreement shall notify the contracting officer in accordance with subpart 42.12. The contractor shall communicate any change to the CAGE code to the contracting officer within 30 days after the change, so that a modification can be issued to update the CAGE code on the contract.

(c) Contractors located in the United States or its outlying areas that are not registered in SAM shall submit written change requests to the DLA Contractor and Government Entity (CAGE) Branch. Requests for changes shall be provided on a DD Form 2051, Request for Assignment of a Commercial and Government Entity (CAGE) Code, to the address shown on the back of the DD Form 2051. Change requests to the CAGE master file are accepted from the entity identified by the code.

RFP No. AG-05M6-S-15-0052 Project: Sulphur Creek Campground Restoration Page 23 of 151 https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_12.html%23wp1084217

(d) Contractors located outside the United States and its outlying areas that are not registered in SAM shall contact the appropriate National Codification Bureau or NSPA to request CAGE changes. Points of contact for National Codification Bureaus and NSPA, as well as additional information on obtaining NCAGE codes, are available at http://www.dlis.dla.mil/nato/ObtainCAGE.asp.

(e) Additional guidance for maintaining CAGE codes is available at http://www.dlis.dla.mil/cage_welcome.asp.

I.4 FAR 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REPRESENTA-

TION (JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern…