Solicitation_LakeCushmanTempBridgeInstallation.doc
DOC document 593 KB Posted
- Attached to
- Lake Cushman Temporary Access Bridge Installation Federal contract opportunity
- Solicitation number
- AG-05G2-S-08-0056
About this file
Solicitation Number AG-05G2-S-08-0056
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_No_001.doc | DOC document | |
| SupplementalSpecs-LakeCushmanTempBridgeInstallation.doc | DOC document | |
| DrawingsLakeCushmanTempBridge.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT/ORDER AL ITEMS
| 1. REQUISITION NUMBER |
| PAGE 1 OF 63 |
| OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 |
| 2. CONTRACT NO. |
| 3. AWARD/EFFECTIVE |
| 4. ORDER NUMBER |
| 5. SOLICITATION NUMBER |
| 6. SOLICIATION ISSUE |
| DATE |
| AG-05G2-S-08-0056 |
| DATE |
Aug. 25, 2008
| a. NAME |
| b. TELEPHONE NUMBER(No collect |
| 8. OFFER DUE DATE/ |
| 7. FOR SOLICITATION |
| Miley Sutherland |
Kathryn Van Hecke calls) 360-956-2471 503-808-2829
LOCAL TIME
Sept. 12, 2008
INFORMATION CALL:
3:30 p.m.
| 9. ISSUED BY CODE |
| 10. THIS ACQUISITON IS |
| 11. DELIVERY FOR |
| 12. DISCOUNT TERMS |
FOB DESTINATION
| Western Washington Acquisition Group |
| FORMCHECKBOX |
UNRESTRICTED
| UNLESS BLOCK IS |
| Olympic National Forest |
| FORMCHECKBOX |
SET ASIDE: 100 % FOR
MARKED
1835 Black Lake Blvd., Suite A
Olympia, WA 98512
FORMCHECKBOX
SMALL BUSINESS
FORMCHECKBOX
SEE SCHEDULE
FORMCHECKBOX
HUBZONE SMALL
| BUSINESS |
| FORMCHECKBOX |
13a. THIS CONTRACT IS A RATED
ORDER UNDER DPAS (15 CFR 700)
FORMCHECKBOX
8(A) 13b. RATING
| NAICS: 237310 |
| SIZE STANDARD: $31.0 |
| 14. METHOD OF SOLICITATION |
FORMCHECKBOX
RFQ FORMCHECKBOX
IFB FORMCHECKBOX
RFP
15. DELIVER TO CODE
16. ADMINISTERED BY CODE
Western Washington Acquisition Group
Olympic National Forest
17a. CONTRACTOR/ CODE FACILITY
OFFEROR CODE
18a. PAYMENT WILL BE MADE BY CODE
National Finance Center
TELEPHONE N0.
FORMCHECKBOX
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
| OFFER |
| IS CHECKED |
FORMCHECKBOX
SEE ADDENDUM
| 19. |
| 20. |
| 21. |
| 22. |
| 23. |
| 24. |
| ITEM N0. |
| SCHEDULE OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| Lake Cushman Temporary Bridge |
Installation 100 percent Set-Aside for Small
Businesses (Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
FORMCHECKBOX
| 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA |
| FORMCHECKBOX |
| ARE |
| FORMCHECKBOX |
ARE NOT ATTACHED
FORMCHECKBOX
| 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.2124. FAR 52.212-5 IS ATTACHED. ADDENDA |
| FORMCHECKBOX |
| ARE |
| FORMCHECKBOX |
ARE NOT ATTACHED
| 28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN |
| FORMCHECKBOX |
29. AWARD OF CONTRACT: REF. OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
| DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY |
| DATED .. YOUR OFFER ON SOLICITATION |
| ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN. |
| (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE |
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
| 30a. SIGNATURE OF OFFEROR/CONTRACTOR |
| 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) |
| 30b. NAME AND TITLE OF SIGNER (Type or print) |
| 30c. DATE SIGNED |
| 31b. NAME OF CONTRACTING OFFICER (Type or print) |
| 31c. DATE SIGNED |
AUTHORIZED FOR LOCAL REPRODUCTION
STANDARD FORM 1449 (REV.4/2002)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA ‑ FAR (48 CFR) 53.212
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
Price Estimate is between $25,000 and
$100,000.
Use the attached Schedule of Items.
32a. QUANTITY IN COLUMN 21 HAS BEEN
FORMCHECKBOX
RECEIVED
FORMCHECKBOX
INSPECTED
FORMCHECKBOX
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ________________________________________
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
| 33. SHIP NUMBER |
| 34. VOUCHER NUMBER |
| 35. AMOUNT VERIFIED |
CORRECTFOR
| 36. PAYMENT |
| 37. CHECK NUMBER |
|PARTIAL | |FINAL
FORMCHECKBOX
COMPLETE FORMCHECKBOX
PARTIAL FORMCHECKBOX
FINAL
| 38. S/R ACCOUNT NUMBER |
| 39. S/R VOUCHER NUMBER |
| 40. PAID BY |
| 41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER |
| FOR PAYMENT |
| 42a. RECEIVED BY (Print) |
| 41 b. SIGNATURE AND TITLE OF CERTIFYING OFFICER |
| 41 c. DATE |
42b. RECEIVED AT (Location)
| 42c. DATE RECD (YY/MM/DD) |
| 42d. TOTAL CONTAINERS |
STANDARD FORM 1449 (REV.4/2002) BACK
Continuation of SF1449 Block 27: The full text of a clause or provision may be accessed electronically at www.arnet.gov/far/
SECTION B - SCHEDULE OF ITEMS
B.1 Schedule of Items:
ITEM
NUMBER
| DESCRIPTION |
| METHOD OF MEASURE |
| PAY |
UNIT
ESTIMATED
QUANTITY
UNIT
PRICE
AMOUNT
| Option 1 |
| Performance Completion Date: |
Oct. 30, 2008.
57104
| Government-furnished prefabricated bridge superstructure – transport and install |
| AQ |
| Lump Sum |
| 1 |
| $________ |
| $________ |
| Option 2 |
| Performance Completion Date: |
Oct. 30, 2009.
57104
| Government-furnished prefabricated bridge superstructure – transport and install |
| AQ |
| Lump Sum |
| 1 |
| $________ |
| $________ |
AQ - Actual Quantity
SECTION C – DESCRIPTION / SPECIFICATIONS / WORK STATEMENT
C.1
SCOPE OF CONTRACT
This contract consists of the installation of a Government Furnished pre-fabricated steel bridge 50 feet in length, a Government Furnished prefabricated steel ramp structure approximately 18 feet in length that is supported by a hinge or connection off the 50 foot bridge, and an aggregate approach ramp . The bridge and ramp will be delivered to a site near Lake Cushman approximately 17 miles west of Hoodsport, Washington. The timeframe for delivery of the bridge and ramp will be no later than October 10, 2008, with delivery by the fabricator coordinated as part of the installation contract. Install the temporary access bridge and both approach ramps no later than 21 days after delivery of the Government Furnished property. Furnish equipment that meets the weight restrictions and configurations shown on the plans. There is no vehicle access to the far side of the project at this time; vehicle access will be established by this contract.
C.2
PROJECT LOCATION
The existing Lake Cushman Bridge is located on Forest Service Road 2451 at milepost 0.1 of the Olympic National Forest, Hood Canal Ranger District in Mason County, Section 10, Township 23 North, Range 5 West, W.M., and west of Hoodsport, Washington. From Olympia, travel north on Hwy 101 to Hoodsport, then northeast on WA-119 North Lake Cushman Road to the intersection with Forest Road 24. Turn left at the ‘T’ intersection onto Forest Road 24 and travel east until the intersection with Forest Road 2451. The bridge is located at milepost 0.1 on Forest Road 2451.
(a) Existing Conditions:
The indications of physical conditions on the plans and in the specifications are the result of site investigations by surveys. Conditions may have changed due to filling and emptying of the Lake Cushman Reservoir.
(b) Weather Conditions:
Weather conditions suitable for ground excavation are normally expected in May through October. Rain, sometimes heavy, is normal throughout the winter, with periods of light to moderate snowfall. Night freezing is common throughout the winter and several periods of weeklong freezes are likely.
(c) Operating Season: Inclusive dates during which operations ARE permissible.
| Road Number |
| Construction Season |
| Instream Work |
| Hand Tools |
| Power Tools, Machinery, & Heavy Machinery |
| Time of Day: Operations can begin 2 hours after legal sunrise and must end 2 hours before legal sunset. |
| 2451 M.P. 0.1 |
| 7/16-10/31 |
| N/A |
| 7/16-10/31 |
| 7/16-10/31 |
| 4/1 to 9/15 |
NOTES:
Power Tools/2 Chainsaws - any power tools with noise output no more than two chainsaws.
Machinery/Car Traffic - any machinery with noise output no more than normal vehicular traffic at site (e.g. small excavator/backhoe).
Helicopter/Heavy Machinery - any machinery with noise output greater than normal vehicular traffic at site.
(d) Pre-bid Conference: NONE
C.3 AVAILABILITY OF SPECIFICATIONS OR PRODUCT DESCRIPTIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS AND STANDARDS (FAR 52.210-3) (APR 1984)
Specifications not on the list but referenced by other Standard Specifications, shall also be applicable to this document.
Specifications or product descriptions cited herein, but not attached to this solicitation nor listed in the General Services Administration Index of Federal Specifications and Standards (GSAIFSS), may be obtained from:
Specification
Address Standard Specifications
Superintendent of Documents
For Construction of
U.S. Government Printing Office
Roads and Bridges Washington, D.C. 20402
FP-03
(866) 512-1800
U.S. Customary http://bookstore.gpo.gov/ Units www.wfl.fha.dot.gov/disgn/specs/gpo3.htm.
ASTM Standards
American Society for Testing and Materials
P.O. Box C700
100 Bar Harbor Drive
West Conshohocken, PA 19428-2959
(610) 832-9585 http://www.astm.org
AASHTO Standards
American Association of State
Highway and Transportation Officials
444 North Capitol Street, NW
Suite 249
Washington, D.C., 20001
(206) 624- 5800 http://www.aashto.org
C.4
APPLICABLE SPECIFICATIONS, MATERIAL CERTIFICATIONS & OTHER SUBMITTALS
· Standard Specification for Construction of Roads and Bridges on Federal Highway Projects FP-03 U.S. Customary Units
· Forest Service Supplemental Specifications (FSSS) (attachment)
· Memorandum of Understanding No. NFS (attachment)
(a) Product Substitution:
Any modification of other items, designs, materials, products or equipment (including Government-Furnished Property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
(b) Submittals:
Compaction: 95% of the maximum density
Submit the following for this project. See FP-03 Sections 104, 106 and 571 for timely submittal and approval by the Contracting Officer.
| Brief Title |
| Basic Reference Section |
| Detailed Requirements Subsections |
| Number of Copies to Submit |
| Time for Government Approval After Total Submittal |
| Launching plan |
| 571 |
| 1 |
| 7 Days |
| Threaded rod certification |
| Plans |
| 571.08, |
557.04, plans
| 1 |
| 7 Days |
| Non-shrink grout certification |
| 571 |
| 725.22(c), |
Plans
| 1 |
| 7 Days |
| Elastomeric bearing pad certification |
| 564 |
| 717.10, supplemental specifications |
| 1 |
| 7 Days |
| Epoxy certification |
| 571 |
| WSDOT ASA Pre-Qualification information for source of gravel base and crushed surfacing |
| Plans |
| Plans |
| 1 |
| 7 Days |
| Equipment axle weights and configurations |
| C.8, Plans |
| 1 |
| 7 Days |
Do not begin work requiring submittals until submittals have been approved.
Include the following information with each submittal:
· Date and Revision Dates.
· Project Name and Contract Number.
· Names of Contractor, Subcontractor, Supplier, and Manufacturers.
· Field Dimensions and Relation to Adjacent Structures.
· Contractor's stamp, initialed or signed, certifying review of submittal, verification of field measurement and compliance with contract documents.
Submittals will be reviewed and either approved or rejected within 7 calendar days of their receipt by the Contracting Officer or COR.
C.5
LANDSCAPE PRESERVATION
(1) Erosion Control Measures:
Minimize sediment laden water from entering the reservoir or river. .
(2) Landscape Preservation:
Confine operations to within the roadway along the causeway, existing bridge, and the roadway past the bridge. Prevent the depositing of rocks, excavated materials, or other debris outside these limits. Retrieve material which falls outside of these limits and dispose of those materials or incorporate them into work as directed by the Contracting Officer. Repair damage to vegetation or structures outside the clearing limits as directed by the Contracting Officer.
Schedule and conduct operations to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
Do not discharge pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Do not allow wash water or waste from grouting or aggregate operations to enter live steams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the waterway into which it is discharged.
Do not maintain storage facilities for oil or oil products on project Area.
C.6
CLEANING OF EQUIPMENT
Conduct operations so that all equipment is operated on the roadway (causeway, existing bridge, and paved roadway past the existing bridge.) Equipment may also be staged and used at the parking area at the end of the causeway and may be turned around at the widened area past the bridge once vehicle access is established. Prior to delivery at the project, clean equipment as necessary to ensure equipment is free of all attached mud, dirt, and plant parts. If noxious weeds are present at a project site, cleaning may also be required before moving between locations within the same project. These measures will assist to prevent the introduction/spread of the seeds of noxious weeds onto National Forest land. Notify the Forest Service prior to moving each piece of equipment onto the project. Upon request from the Forest Service, arrangement will be made for Forest Service to inspect each piece of equipment prior to it being placed into service. Certify, in writing, compliance with the above requirements.
C.7
CONTRACT TIME AND PLAN FOR WEATHER-CAUSED SUSPENSIONS OF WORK
Option 1: Do not exceed 60 calendar days from the contract award with completion of contract not to exceed 21 days from delivery of the GFP bridge superstructure and approach ramp. The supply contract requires delivery of the Government-furnished superstructure no later than October 10, 2008.
Option 2: Completion of contract no later than October 30, 2009.
No weather related delays will be considered for normal seasonal weather. Weather related delays for unseasonable snow (exceeding 6 inches) or high winds (exceeding 35 mph) will be considered as operating under these conditions may adversely affect safe operations.
C.8
USE OF PREMISES
No developed recreation sites are available for temporary occupancy during the project.
A storage site will be permitted at a designated site within the project area. The Forest Service assumes no liability for materials stored within the storage site. The Contractor will be allowed to erect a temporary fence to secure materials and equipment, however, remove the fence and restore the site prior to final acceptance of the contract.
No electrical power is available at the site.
Potable water and sanitary facilities ARE NOT available for use during construction.
Load Limits – Do not exceed posted limits or load limits shown on the plans, especially for the existing concrete bridge. Submit axle weights and configurations for all proposed equipment to be used on the existing bridge for consideration. Allow 7 days for review of submittals.
C.9 STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-72)(FEB 1988)
Furnish the necessary personnel, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C.10 ATTACHMENTS TO STATEMENTS OF WORK/SPECIFICATIONS (AGAR 452.211-73)(FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
FAR 52.212-4 Contract Terms and Conditions—Commercial Items (FEB 2007)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601-613). Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, contract line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—Central Contractor Registration, or 52.232-34, Payment by Electronic Funds Transfer—Other Than Central Contractor Registration), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall immediately notify the Contracting Officer and request instructions for disposition of the overpayment.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. 423 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The Schedule (excluding the specifications)
(2) Representations and Other Instructions
(3) Contract Clauses
(4) Other Documents, Exhibits, and Attachments
(5) The Specifications
(6) Plans
(t) Central Contractor Registration (CCR).
(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(2)(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.
(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423 or 269-961-5757.
Commencement, Prosecution, and Completion of Work (FAR 52.211-10)(APR 1984) The Contractor shall be required to (a) commence work under this contract within 3 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than: Option 1: OCTOBER 30, 2008 ; and Option 2: OCTOBER 30, 2009. The time stated for completion shall include final cleanup of the premises.
Maximum Workweek – Construction Schedule (AGAR 452.236-75) (NOV 1996) Within 7 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.
The maximum workweek that will be approved is Monday through Friday from 7:00 am to 7:00 pm. Work may be completed on weekends with prior approval of the Contracting Officer’s Representative (COR).
Buy American Act-Construction Materials (FAR 52.225-9)(JAN 2005)
(a) Definitions. As used in this clause—
"Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Domestic construction material" means—
(1) An unmanufactured construction material mined or produced in the United States; or
(2) A construction material manufactured in the United States, if the cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.
"Foreign construction material" means a construction material other than a domestic construction material.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to the construction material or components listed by the Government as follows: None.
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(a) Request for determination of inapplicability of the Buy American Act.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
| Construction material description |
| Unit of measure |
| Quantity |
| Price (dollars) * |
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).] Insurance—Work on a Government Installation (FAR 52.228-5)(JAN 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government’s interest shall not be effective—
(1) For such period as the laws of the State in which this contract is to be performed prescribe; or
(2) Until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors’ proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
Insurance Coverage (AGAR 452.228-71)(NOV 1996) Pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
Workers Compensation and Employer’s Liability. The Contractor is required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a Contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker’s compensation to be written by private carriers.
General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
Accident Prevention (52.236-13)(NOV 1991)
(a) The Contractor shall provide and maintain work environments and procedures which will—
(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;
(2) Avoid interruptions of Government operations and delays in project completion dates; and
(3) Control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall—
(1) Provide appropriate safety barricades, signs, and signal lights;
(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and
(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.
(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
(d) Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.
(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.
Specifications and Drawings for Construction (FAR 52.236-21)(FEB 1997)
(a) The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense. The Contracting Officer shall furnish from time to time such detailed drawings and other information as considered necessary, unless otherwise provided.
(b) Wherever in the specifications or upon the drawings the words “directed,” “required,” “ordered,” “designated,” “prescribed,” or words of like import are used, it shall be understood that the “direction,” “requirement,” “order,” “designation,” or “prescription,” of the Contracting Officer is intended and similarly the words “approved,” “acceptable,” “satisfactory,” or words of like import shall mean “approved by,” or “acceptable to,” or “satisfactory to” the Contracting Officer, unless otherwise expressly stated.
(c) Where “as shown,” “as indicated,” “as detailed,” or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word “provided” as used herein shall be understood to mean “provide complete in place,” that is “furnished and installed.”
(d) Shop drawings means drawings, submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to a construction contract, showing in detail (1) the proposed fabrication and assembly of structural elements, and (2) the installation (i.e., fit, and attachment details) of materials or equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.
(e) If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor’s approval may be returned for resubmission. The Contracting Officer will indicate an approval or disapproval of the shop drawings and if not approved as submitted shall indicate the Government’s reasons therefore. Any work done before such approval shall be at the Contractor’s risk. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract, except with respect to variations described and approved in accordance with (f) of this clause.
(f) If shop drawings show variations from the contract requirements, the Contractor shall describe such variations in writing, separate from the drawings, at the time of submission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, if the variation is minor or does not involve a change in price or in time of performance, a modification need not be issued.
(g) The Contractor shall submit to the Contracting Officer for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. Three sets (unless otherwise indicated) of all shop drawings, will be retained by the Contracting Officer and one set will be returned to the Contractor.
Alternative Forms of Security (AGAR 452.228-70)(NOV 1996)
If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.
52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Items (FEB 2008)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
(1) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).
(2) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Pub. L. 108-77, 108-78)
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:
[Contracting Officer check as appropriate.]
__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Sept 2006), with Alternate I (Oct 1995) (41 U.S.C. 253g and 10 U.S.C. 2402).
__ (2) 52.219-3, Notice of Total HUBZone Set-Aside (Jan 1999) (15 U.S.C. 657a).
__ (3) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (July 2005) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
__ (4) [Reserved]
_X_ (5)(i) 52.219-6, Notice of Total Small Business Set-Aside (June 2003) (15 U.S.C. 644).
__ (ii) Alternate I (Oct 1995) of 52.219-6.
__ (iii) Alternate II (Mar 2004) of 52.219-6.
__ (6)(i) 52.219-7, Notice of Partial Small Business Set-Aside (June 2003) (15 U.S.C. 644).
__ (ii) Alternate I (Oct 1995) of 52.219-7.
__ (iii) Alternate II (Mar 2004) of 52.219-7.
_X_ (7) 52.219-8, Utilization of Small Business Concerns (May 2004) (15 U.S.C. 637(d)(2) and (3)).
__ (8)(i) 52.219-9, Small Business Subcontracting Plan (Nov 2007) (15 U.S.C. 637(d)(4).
__ (ii) Alternate I (Oct 2001) of 52.219-9.
__ (iii) Alternate II (Oct 2001) of 52.219-9.
_X_ (9) 52.219-14, Limitations on Subcontracting (Dec 1996) (15 U.S.C. 637(a)(14)).
__ (10) 52.219-16, Liquidated Damages—Subcontracting Plan (Jan 1999) (15 U.S.C. 637(d)(4)(F)(i)).
__ (11)(i) 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns (Sept 2005) (10 U.S.C. 2323) (if the offeror elects to waive the adjustment, it shall so indicate in its offer).
__ (ii) Alternate I (June 2003) of 52.219-23.
__ (12) 52.219-25, Small Disadvantaged Business Participation Program—Disadvantaged Status and Reporting (Oct 1999) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
__ (13) 52.219-26, Small Disadvantaged Business Participation Program—Incentive Subcontracting (Oct 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).
__ (14) 52.219-27, Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside (May 2004) (15 U.S.C. 657 f).
__ (15) 52.219-28, Post Award Small Business Program Rerepresentation (June 2007) (15 U.S.C. 632(a)(2)).
_X_ (16) 52.222-3, Convict Labor (June 2003) (E.O. 11755).
__ (17) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Feb 2008) (E.O. 13126).
_X_ (18) 52.222-21, Prohibition of Segregated Facilities (Feb 1999).
_X_ (19) 52.222-26, Equal Opportunity (Mar 2007) (E.O. 11246).
_X_ (20) 52.222-35, Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Sept 2006) (38 U.S.C. 4212).
_X_ (21) 52.222-36, Affirmative Action for Workers with Disabilities (Jun 1998) (29 U.S.C. 793).
_X_ (22) 52.222-37, Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Sept 2006) (38 U.S.C. 4212).
_X_ (23) 52.222-39, Notification of Employee Rights Concerning Payment of Union Dues or Fees (Dec 2004) (E.O. 13201).
_X_ (24)(i) 52.222-50, Combating Trafficking in Persons (Aug 2007) (Applies to all contracts).
__ (ii) Alternate I (Aug 2007) of 52.222-50.
__ (25)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Aug 2000) (42 U.S.C. 6962(c)(3)(A)(ii)).
__ (ii) Alternate I (Aug 2000) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)).
__ (26) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b).
__ (27)(i) 52.223-16, IEEE 1680 Standard for the Environmental Assessment of Personal Computer Products (Dec 2007) (E.O. 13423).
__ (ii) Alternate I (Dec 2007) of 52.223-16.
__ (28) 52.225-1, Buy American Act—Supplies (June 2003) (41 U.S.C. 10a-10d).
__ (29)(i) 52.225-3, Buy American Act—Free Trade…
This is the start of the file's text. The full file is on GovTribe.