Ninemile Pit Crushing Specifications AG-05G1-S-15-0050 Republic Ranger District Page 1 of 30
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
Republic Ranger District Page 2 of 30
109 Deletions
109.02 Measurement Terms and Definitions
153 - Contractor Quality Control
153.02 Contractor Quality Control Plan
153.04 Records
155 - Schedules for Construction Contracts
155 Delete
205 - Rock Blasting
205.03 Regulations
205.06 Preblast condition survey and vibration monitoring and control
205.07 Test Blasting
303 - Road Reconditioning
303.01 Work
303.10 Measurement
320 - Stockpiled Aggregates
320.01
320.02
651 - Development of Pits & Quarries
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
Republic Ranger District Page 3 of 30
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
Republic Ranger District Page 4 of 30
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
http://www.nist.gov/
Republic Ranger District Page 5 of 30
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Republic Ranger District Page 6 of 30
Figure 101-1—Illustration of road structure terms.
Republic Ranger District Page 7 of 30
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
Republic Ranger District Page 8 of 30
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
Republic Ranger District Page 9 of 30
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
Republic Ranger District Page 10 of 30
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
Republic Ranger District Page 11 of 30
106 - Acceptance of Work
106.01_nat_us_01_17_2013
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work.
However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
Republic Ranger District Page 12 of 30
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the Contracting Officer. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.
Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The Contracting Officer will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
Republic Ranger District Page 13 of 30
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The Contracting Officer will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
Republic Ranger District Page 14 of 30
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the Contracting Officer of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
Republic Ranger District Page 15 of 30
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the Contracting Officer and in a manner that complies with Federal, state, and local laws and regulations.
Republic Ranger District Page 16 of 30
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
Republic Ranger District Page 17 of 30
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
Republic Ranger District Page 18 of 30
153 - Contractor Quality Control
153.02_nat_us_02_17_2005
153.02 Contractor Quality Control Plan.
Add the following:
Submit written proposals for approval of alternate AASHTO or State approved test methods.
Alternate methods may be allowed based on documented equivalence to the specified method.
153.04_nat_us_10_24_2007
153.04 Records.
Delete all but the first sentence
Republic Ranger District Page 19 of 30
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
Republic Ranger District Page 20 of 30
205 - Rock Blasting
205.02_nat_us_05_13_2004
205.03 Regulations
(e) Forest Service Manual (FSM) 6745 Explosives and Blasting Materials.
205.06_nat_us_05_12_2004
205.06 Preblast condition survey and vibration monitoring and control.
Add the following:
Limit blasting induced vibrations in saturated soils or on steep slopes as designated or as directed by the Contracting Officer.
Notify the owners of nearby utilities at least 24 hours before blasting.
205.07_nat_us_05_12_2004
205.07 Test Blasting.
Add the following:
Test blast at all new sources, when rock type changes, and when blast layout changes due to slope or other changes.
Republic Ranger District Page 21 of 30
303 - Road Reconditioning
303.01_nat_us_03_02_2005
303.01 Work.
Delete and add the following:
This work consists of reconditioning ditches, shoulders, roadbeds, cattleguards, asphalt surfaces, and aggregate surfaces.
303.05_06_us_08_21_2008
Replace with the following:
303.05 Roadbed Reconditioning. Repair soft and unstable areas according to Subsection 204.07.
Remove all organic and deleterious material larger than 4 inches from the scarification depth specified. Dispose of waste according to Subsection 204.14. Scarify to the width and depth shown on the drawings, remove surface irregularities, and shape to provide a uniform surface.
Finish earth surfaces to within 0.2 feet and rock surfaces to within 0.10 feet of the required line, cross-section, and grade.
Dispose of rock larger than 4 inches brought to the surface during scarification in areas designated on the plans.
For portions of roads not requiring scarification, the roadbed may contain rocks larger than 4 inches provided they do not extend above the finished roadbed surface. Reduce in place or remove rock extending above the finished roadbed surface. Dispose of removed rock in areas designated on the plans.
303.11_nat_us_03_29_2005
303.10 Measurement
Modify the second paragraph as follows:
Measure ditch reconditioning and shoulder reconditioning by the mile, station, or foot horizontally along the centerline of the roadway for each side of the roadway.
Republic Ranger District Page 22 of 30
320 - Stockpiled Aggregates
320.00_nat_us_02_01_2012
Description
320.01 This work consists of furnishing and placing aggregate in a stockpile at an existing site or constructing a new site and placing the aggregate at the new site.
Material
320.02 Conform to the following Section:
Aggregate 703
Provide the gradation and quality requirements specified in the Section identified in the pay item.
Construction Requirements
320.03 Stockpile Site. Prepare existing sites as necessary to accommodate the quantity of aggregate to be stockpiled.
For new sites, clear and grub according to Section 201. Grade and shape the site to a uniform cross-section that drains. Compact the floor of the site with at least three passes using compaction equipment conforming to Subsection 204.11. Place, compact, and maintain a minimum 6 inches of crushed aggregate over the stockpile site and access roads. Prevent contamination of the stockpiles.
320.04 Stockpile. After a representative quantity of aggregate is produced, submit proposed target values for the appropriate sieve sizes along with a representative 350-pound sample.
Set target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading.
Request site approval before stockpiling aggregates. Make the stockpiles neat and regular in shape. Make the side slopes no flatter than 1:1.5.
Build the stockpiles in layers not exceeding 3 feet thick. Complete each layer before depositing aggregates in the next layer. Do not allow aggregates from the one layer to run down over lower
Republic Ranger District Page 23 of 30 layers of the stockpile. Do not drop aggregates from a bucket or spout in one location to form a cone-shaped pile.
Construct stockpile layers by spreading aggregates with trucks or other approved pneumatic-tired equipment. Do not push aggregates into piles.
When operating trucks on stockpiles, avoid tracking dirt or other deleterious material onto the stockpiled material.
Space stockpiles far enough apart or separate stockpiles by suitable walls or partitions to prevent the mixing of the different aggregate gradations.
320.05 Acceptance. Aggregate for stockpiling will be evaluated under Subsection 301.08 and Table 301-1. The point of sampling will be the belt or stockpile.
Preparation of stockpile sites and construction of stockpiles will be evaluated under Subsections
106.02 and 106.04.
Clearing will be evaluated under Section 201.
Measurement
320.06 Measure the 320 items listed in the bid schedule according to subsection 109.02.
Payment
320.07 The accepted quantities, measured as provided in subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 320 pay items listed in the bid schedule except the stockpiled aggregate.
Republic Ranger District Page 24 of 30
651 - Development of Pits & Quarries
651.00_nat_us_03_02_2005
Description
651.01 This work consists of clearing, grubbing, stripping topsoil, removing overburden, constructing access roads, conducting restoration activities, and performing other incidental work required for pit or quarry development.
Construction Requirements
651.02 General. Submit a plan of operations according to Section 105. Perform all work in accordance with Sections 105, 201, 203, 204, 625, and 635, landscape preservation requirements, and the approved pit and quarry development plan of operations. Perform the work in accordance with MSHA 30 CFR, part 56.
651.03 Acceptance. Developing pits and quarries will be evaluated under Subsections 106.02 and 106.04.
Measurement
651.04 Measure the Section 651 items listed in the bid schedule according to Subsection 109.02.
Payment
651.05 The accepted quantities will be paid at the contract price per unit of measurement for the Section 651 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05
Republic Ranger District Page 25 of 30
703 - Aggregate
703.05_nat_us_08_14_2009
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not furnish material that contains asbestos fibers.
Republic Ranger District Page 26 of 30
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradation Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Republic Ranger District Page 27 of 30
Delete Table 703-2 and replace with the following:
T ab le
-2 ar ge t V al ue
R an ge s f or S ub ba se a nd B as e
G ra da tio n Pe rc en t b y
M as s P as si ng
D es ig na te d
Si ev e (A
A
SH
T O
T an d T
1)
G ra di ng D es ig na tio n E
(B as e)
(6
(6
(4
4.
7.
(3
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al ue s..
D (B
(6
(6
(6
(4
4.
7.
(3
C (B
(6
(6
4.
–7 .0
(3
B (S ub ba se
(8
4.
.0 (4
A (S ub ba se
(7
(6
(4
4.
8.
(3
Si ev e Si ze
2½ in ch
1½
3/
1/
N o.
N o.
Republic Ranger District Page 28 of 30
Delete Table 703-3 and replace with the following:
ab le
-3 ar ge t V al ue R an ge s f or
S ur fa ce
G ra da tio n Pe rc en t b y
M as s P as si ng
D es ig na te d
Si ev e (A
A
SH
T O
T an d T
1) ra di ng D es ig na tio n U
(6
(7
(5
8.
.0 (4
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al ue s.
If th e pl as tic ity in de x
(P I) is gr ea te r t ha n 0, th e
TV
ra ng e fo r t he N o.
si ev e siz e is
-1
(4
(7
(5
8.
.0 (4
S 10
(6
(7
(5
8.
.0 (4
H
(6
(6
(5
9.
.0 (4
(6
(6
(5
.0
6.
(4
F 10
-1
-8
-6
(6
-5
-3
(6
-2
(5
.0
-1 6.
(4
Si ev e Si ze
N o.
N o.
Republic Ranger District Page 29 of 30
Add Table 703-16:
Table 703-16
Gradation Requirements for Screened Aggregate
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation L M N O P Q R
6 inch 100 100
4 inch 100 100
3 inch 100 100
2 inch 100
No. 4 15-45 15-45 15-45
Republic Ranger District Page 30 of 30
718 - Traffic Signing and Marking Material
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
| Table of Contents |
| Preface |
| 101 - Terms, Format, and Definitions |
| 101.01 Meaning of Terms |
| 101.03 Abbreviations. |
| 101.04 Definitions. |
| 102 - Bid, Award, and Execution of Contract |
| 102 Bid, Award, and Execution of Contract |
| 103 - Scope of Work |
| Deletions |
| 104 - Control of Work |
| Deletions |
| 104.06 Use of Roads by Contractor |
| 105 - Control of Material |
| 105.02 Material Sources. |
| 105.02(a) Government-provided sources. |
| 105.05 Use of Material Found in the Work. |
| 106 - Acceptance of Work |
| 106.01 Conformity with Contract Requirements. |
| 106.07 Delete |
| 107 - Legal Relations and Responsibility to the Public |
| 107.05 Responsibility for Damage Claims. |
| 107.06 Contractor’s Responsibility for Work. |
| 107.09 Legal Relationship of the Parties. |
| 107.10 Environmental Protection. |
| 108 - Prosecution and Progress |
| 108 Delete. |
| 109 - Measurement and Payment |
| 109 Deletions |
| 109.02 Measurement Terms and Definitions. |
| 153 - Contractor Quality Control |
| 153.02 Contractor Quality Control Plan. |
| 153.04 Records. |
| 155 - Schedules for Construction Contracts |
| 155 Delete. |
| 205 - Rock Blasting |
| 205.03 Regulations |
| 205.06 Preblast condition survey and vibration monitoring and control. |
| 205.07 Test Blasting. |
| 303 - Road Reconditioning |
| 303.01 Work. |
| 303.10 Measurement |
| 320 - Stockpiled Aggregates |
| 651 - Development of Pits & Quarries |
| 703 - Aggregate |
| 703.05 Subbase, Base, Surface Course, and Screened Aggregate. |
| 718 - Traffic Signing and Marking Material |
| 718.05 Aluminum Panels |