Addendum_to_Amendment_2_-_RFIs.docx

DOCX document 16 KB Posted

Attached to
Goose & Soda Creek Drainage Reconstruction Federal contract opportunity
Solicitation number
AG-04GG-S-16-0001
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Addendum to Amendment 2 RFI-005 to RFI-009

View the file

Other files for this federal contract opportunity

Other files attached to Goose & Soda Creek Drainage Reconstruction, newest first.
File Type Posted
Amendment_3.pdf PDF
Goose_Culvert_Main_3-8-16_10_7th_Mt__M_S.pdf PDF
Goose_Culvert_Main_3-8-16_9_7th_Mt__M_S.pdf PDF
Addendum_to_Amendment_3_-_RFIs_FINAL_(002).docx DOCX document
Goose_Soda_Amendment_2.pdf PDF
Addendum_to_Amendment_1_-_RFIs_1.docx DOCX document
Goose_Soda_Amendment_1.pdf PDF
Soda_ _Goose_Specifications.pdf PDF
Goose_and_Soda_Solicitation_FINAL.pdf PDF
Soda_and_Goose_Creek_Signed_Drawings.pdf PDF
Goose_and_Soda_Solicitation_FINAL.pdf PDF
Soda_and_Goose_Creek_Signed_Drawings.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum to Amendment 2

REQUESTS FOR INFORMATION GOOSE & SODA CREEK DRAINAGE RECONSTRUCTION PROJECT

RFI’s

RFI-005

How will temp signs, traffic control and traffic devices, flagging be paid? There are no bid items on the schedule.

Answer - This work will be paid with Pay Item 63501 - Temporary Traffic Control, which is located on Drawing Sheet #3 of 84 and on the bid schedule.

RFI-006

There on 2 items on the Soda Cr. Schedule for agg base, 3/4" -0. The qty is different on them, is one for permanent and one for the temp road?

Answer - See remarks column for Pay Items 30103A and 30103B on Drawing Sheet #2 of 84. Pay Item 30103B - Aggregate Base, Grading ODOT ¾”-0, Compaction Method B, is for the placement only (not furnishing of material) of the Pay Item 20416B - Waste, Shoulder & Base Rock onto the Road 4600-400 located on the site map. Furnishing of this material is covered in Pay Item 30103A.

RFI-007

Please clarify whether or not the govt will both supply and install the temp bridge or just supply it. If the govt installs it, is the contractor responsible for the foundation of it, the excavation for it? Will the govt remove it? Will the govt be responsible for all transporting of it?

Answer - The Government will supply and be responsible for transportation, installation and removal of the temporary bridge and it’s foundation. The Contractor is required to perform all other work associated with the construction and subsequent removal of the temporary bypass road. The temporary bridge will be in place prior to July 11, 2016.

RFI-008

How will the paving of the temp bypass road be paid?

Answer - Paving for the Bypass/Diversion Road will be paid under Pay Item 40311 – State of Oregon, Asphalt Concrete Pavement Class Level 2. See Drawing Sheet #2 of 84, Pay Item 40311 for estimated quantities for paving of Soda Bridge, Soda Diversion Road and Goose Culvert.

RFI-009

How will the embankment placement and removal for the temp bypass be paid?

Answer - For both the diversion roads at Soda Creek and Goose Creek the embankment placement will be paid under the Pay Item 20404 – Unclassified borrow, compaction method B, Finishing Method B and the removal of the embankment material will be paid under the Pay Item 20416A – Waste, Excavation. See Drawing sheet #1 of 84.