Addendum_to_Amendment_2_-_RFIs.docx
DOCX document 16 KB Posted
- Attached to
- Goose & Soda Creek Drainage Reconstruction Federal contract opportunity
- Solicitation number
- AG-04GG-S-16-0001
About this file
Addendum to Amendment 2 RFI-005 to RFI-009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_3.pdf | ||
| Goose_Culvert_Main_3-8-16_10_7th_Mt__M_S.pdf | ||
| Goose_Culvert_Main_3-8-16_9_7th_Mt__M_S.pdf | ||
| Addendum_to_Amendment_3_-_RFIs_FINAL_(002).docx | DOCX document | |
| Goose_Soda_Amendment_2.pdf | ||
| Addendum_to_Amendment_1_-_RFIs_1.docx | DOCX document | |
| Goose_Soda_Amendment_1.pdf | ||
| Soda_ _Goose_Specifications.pdf | ||
| Goose_and_Soda_Solicitation_FINAL.pdf | ||
| Soda_and_Goose_Creek_Signed_Drawings.pdf | ||
| Goose_and_Soda_Solicitation_FINAL.pdf | ||
| Soda_and_Goose_Creek_Signed_Drawings.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum to Amendment 2
REQUESTS FOR INFORMATION GOOSE & SODA CREEK DRAINAGE RECONSTRUCTION PROJECT
RFI’s
RFI-005
How will temp signs, traffic control and traffic devices, flagging be paid? There are no bid items on the schedule.
Answer - This work will be paid with Pay Item 63501 - Temporary Traffic Control, which is located on Drawing Sheet #3 of 84 and on the bid schedule.
RFI-006
There on 2 items on the Soda Cr. Schedule for agg base, 3/4" -0. The qty is different on them, is one for permanent and one for the temp road?
Answer - See remarks column for Pay Items 30103A and 30103B on Drawing Sheet #2 of 84. Pay Item 30103B - Aggregate Base, Grading ODOT ¾”-0, Compaction Method B, is for the placement only (not furnishing of material) of the Pay Item 20416B - Waste, Shoulder & Base Rock onto the Road 4600-400 located on the site map. Furnishing of this material is covered in Pay Item 30103A.
RFI-007
Please clarify whether or not the govt will both supply and install the temp bridge or just supply it. If the govt installs it, is the contractor responsible for the foundation of it, the excavation for it? Will the govt remove it? Will the govt be responsible for all transporting of it?
Answer - The Government will supply and be responsible for transportation, installation and removal of the temporary bridge and it’s foundation. The Contractor is required to perform all other work associated with the construction and subsequent removal of the temporary bypass road. The temporary bridge will be in place prior to July 11, 2016.
RFI-008
How will the paving of the temp bypass road be paid?
Answer - Paving for the Bypass/Diversion Road will be paid under Pay Item 40311 – State of Oregon, Asphalt Concrete Pavement Class Level 2. See Drawing Sheet #2 of 84, Pay Item 40311 for estimated quantities for paving of Soda Bridge, Soda Diversion Road and Goose Culvert.
RFI-009
How will the embankment placement and removal for the temp bypass be paid?
Answer - For both the diversion roads at Soda Creek and Goose Creek the embankment placement will be paid under the Pay Item 20404 – Unclassified borrow, compaction method B, Finishing Method B and the removal of the embankment material will be paid under the Pay Item 20416A – Waste, Excavation. See Drawing sheet #1 of 84.