S-10-0047_complete_solicitation.doc

DOC document 283 KB Posted

Attached to
Big Larch Water System Renovation Federal contract opportunity
Solicitation number
AG-03R6-S-10-0047
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

02 - Complete Solicitation Package (Retain for Your Records)

View the file

Other files for this federal contract opportunity

Other files attached to Big Larch Water System Renovation, newest first.
File Type Posted
Amendment1.pdf PDF
Big Larch 11x17.pdf PDF
s100047_attachments.docx DOCX document
S-10-0047_short_solicitation.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-03R6-S-10-0047

Big Larch Campground Water System Rehabilitation/Lolo NF

OFFEROR'S COPY

NOTE: Attached forms must be completed and submitted intact.

Issuing Office:

U.S. Department of Agriculture Forest Service Western Montana Acquisition Zone Building 24, Fort Missoula Missoula, Montana 59804

Offers Are Solicited For:

PROJECT

Big Larch Campground Water System Rehabilitation Project

Seeley Lake Ranger District

Lolo National Forest

Missoula County, Montana

Solicitation No. RFP AG-03R6-S-10-0047
HELP PREVENT FOREST FIRES

IMPORTANT - NOTICE TO OFFEROR

1. This is a complete copy. Information and instructions for submission of proposals as well as contract provisions and specifications are contained in this OFFEROR REFERENCE COPY. This copy should be retained by offerors.

2. Note: An offer guarantee (Bid Bond) IS REQUIRED. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.)

FS-6300-45 (11/79)

TABLE OF CONTENTS

Page(s)

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

1 - 2

SECTION B - SUPPLIES OR SERVICES AND PRICES

3 - 4

B- 1 - Schedule of Items

B- 2 - Payment for Bond Premiums

SECTION C - DESCRIPTION/SPECIFICATIONS

C- 1 - Scope of Contract

C- 2 - Project Location

C- 3 - Price Range

C- 4 - Site Visit

C- 5 - Start Work

C- 6 - Period of Performance

C- 7 - Standard Specifications

C- 8 - Drawings

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 - Clauses Incorporated by Reference

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 - Clauses Incorporated by Reference

F- 2 - Commencement, Prosecution, and Completion of Work

SECTION H - SPECIAL CONTRACT REQUIREMENTS

8 - 13

H- 1 - Clauses Incorporated by Reference

H- 2 - Fire Control

H- 3 - Loss, Damage, or Destruction

H- 4 - Incidental Payment Items

H- 5 - Conformity with Drawings and Specifications

H- 6 - Local Material Sources

H- 7 - Samples, Tests, Cited Specifications

H- 8 - Barricades, Warning Signs, and Other Devices

H- 9 - Weed Free Equipment

H-10 - Landscape Preservation

H-11 - Prework Conference

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

14 - 24

I- 1 - Clauses Incorporated by Reference

I- 2 - Central Contractor Registration

I- 3 - Post Award Small Business Program Representation

I- 4 - Buy American Act - Construction Materials

I- 5 - Bid Guarantee

I- 6 - Performance and Payment Bonds - Construction

I- 7 - Alternative Forms of Security

I- 8 - Reimbursement For Bond Premiums - Fixed Price Construction Contracts

I- 9 - Permits and Responsibilities

I-10 - Authorized Deviations in Clauses

I-11 - Order of Precedence - Construction

PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

J- 1 - Wage Determination

J- 2 - Specifications

J- 3 - Drawings

PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER

26 - 29

STATEMENTS OF OFFERORS AND RESPONDENTS

K- 1 - Annual Representations and Certifications

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

30 - 35

AND RESPONDENTS

L- 1 - Inquiries

L- 2 - Instructions for the Preparation of Technical and Business Proposals

L- 3 - Amendments to Proposals

L- 4 - Type of Contract

L- 5 - Davis-Bacon Act—Secondary Site of the Work

L- 6 - Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity

For Construction

L- 7 - Notice of Buy American Act Requirements - Construction Materials

L- 8 - Service of Protest

L- 9 - Site Visit (Construction) Alterante I

L-10 - Preparation of Proposals – Construction

L-11 - Authorized Deviations in Provisions

SECTION M - EVALUATION FACTORS FOR AWARD

M- 1 - Evaluation Criteria

M- 2 - Award Statement

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

RFP AG-03R6-S-10-0047

2. TYPE OF SOLICITATION

FORMCHECKBOX

SEALED BID (IFB)

FORMCHECKBOX

NEGOTIATED (RFP)

3. DATE ISSUED

5/21/2010

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

USDA, Forest Service

Western Montana Acquisition Zone Building 24, Fort Missoula

Missoula, MT 59804 USDA, Forest Service

Western Montana Acquisition Zone Building 24, Fort Missoula

Missoula, MT 59804

9. FOR INFORMATION

CALL:

a. NAME

Ron Penrose

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(406) 329-3979

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Big Larch Campground Water System Rehabilitation Project Seeley Lake Ranger District

Lolo National Forest

Missoula County, Montana

Price Range

The Government’s estimate is:

Between $100,000 and $250,000.

11. The Contractor shall begin performance within 10 calendar days and complete it within 60 calendar days after receiving

FORMCHECKBOX

award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F, Clause 52.211-10)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12b.)

FORMCHECKBOX

YES

FORMCHECKBOX

NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a.

Sealed offers in original and * copies to perform the work required are due at the place specified in Item 8 by 4:00 pm local time 6/22/2010 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

b.

An offer guarantee

FORMCHECKBOX

is, FORMCHECKBOX is not required. (If “is required” see AGAR Clause 452.228-70) c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212

1442-101

STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

Duns No. ________________________________________ Taxpayer Identification No. _________________________

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE

FACILITY CODE

17.

The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

FORMCHECKBOX

10 U.S.C. 2304(c)( )

FORMCHECKBOX

41 U.S.C. 253(c)( )

26. ADMINISTERED BY

CODE

27. PAYMENT WILL BE MADE BY

USDA – Forest Service

Western Montana Acquisition Zone Building 24, Fort Missoula

Missoula, MT 59804

Submit invoice to COR for the work performed. Invoice will be reviewed and approved or rejected by the COR within 7 days of receipt of the invoice. Rejected invoices must be corrected and resubmitted. COR will forward the approved invoice to the CO who will submit to:

USDA, OCFO, COD, APB

PO Box 60075

New Orleans, LA 70160

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

FORMCHECKBOX

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

FORMCHECKBOX

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

RONALD B. PENROSE

30b. SIGNATURE

30c. DATE

31b. UNITED STATES OF AMERICA

BY

31c. DATE

Computer Generated

STANDARD FORM 1442 BACK (REV. 4-85)

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Big Larch Campground Water System Rehabilitation Project

Seeley Lake Ranger District

Lolo National Forest

Missoula County, Montana

B- 1 Schedule of Items

Pay

Item

Item Description
MM*
Estimated

Quantity Pay

Unit Unit

Price Amount

1.0
Mobilization
1.1
Mobilization
LSQ
1 LS
LS
XXXXXXX
$_________
2.0
Water Main “A”
2.1
Modifications to Meter Vault
LSQ
1 LS
LS
XXXXXXX
$_________
2.2
2” Diameter HDPE Pipe & Valves
DQ
866 LF
LS
XXXXXXX
$_________
2.3
1” Diameter HDPE Pipe & Valves
DQ
487 LF
LS
XXXXXXX
$_________
2.4
Remove Stop and Drain Valves
DQ
5 EA
LS
XXXXXXX
$_________
2.5
Connection to Existing Hydrants
DQ
3 EA
LS
XXXXXXX
$_________
2.6
Relocate Existing Concrete Slab & Hydrant
DQ
1 EA
LS
XXXXXXX
$_________
2.7
Steel Casing Pipe (1 Crossing)
DQ
40 LF
LS
XXXXXXX
$_________
2.8
Remove Miscellaneous Valve and Boxes Along the North Road
DQ
2 EA
LS
XXXXXXX
$_________
3.0
Water Main Loop “B”
3.1
2” Diameter HDPE Pipe & Valves
DQ
1774 LF
LS
XXXXXXX
$_________
3.2
1” Diameter HDPE Pipe
DQ
1879 LF
LS
XXXXXXX
$_________
3.3
Connection to Existing Hydrants
DQ
10 EA
LS
XXXXXXX
$_________
3.4
Connect to Existing Tee Hydrants
DQ
2 EA
LS
XXXXXXX
$_________
3.5
Blow-Off Assembly
DQ
2 EA
LS
XXXXXXX
$_________
3.6
Steel Casing Pipe (5 Crossings)
DQ
100 LF
LS
XXXXXXX
$_________
TOTAL AMOUNT OFFERED (All Items)
$____________________

* Designated Method of Measurement:

DQ – Designed Quantities; AQ - Actual Quantities, LSQ - Lump Sum Quantities; SQ – Staked Quantities; CQ – Contract Quantities B- 2 Payment for Bond Premiums Note: Payment for bond premiums in accordance with FAR Clause 52.232-5, Payment Under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS

C- 1 Scope of Contract

(a) Description of Work. Work includes, but is not limited to, excavation or trenching and backfilling for pipelines and appurtenances. It includes all clearing, grubbing, site preparation, removal and disposal of debris from the excavation; handling and storing materials for fill and backfill; all bracing, shoring and trench protection; construction dewatering; all backfill; subgrade preparation; final grading; site dressing; and cleanup.

C- 2 Project Location

To reach the project, from Missoula, Montana, go east on Interstate 90 approximately 3 miles to Highway 200 north. Follow Highway 200 north approximately 25 miles to Highway 83. Follow 83 north approximately 20 miles to Seeley Lake, Montana. Campgrounds are located on the east side of Seeley Lake.

C- 3 Price Range. $100,000 to $250,000 C- 4 Site Visit A site visit to the project area will meet at the Big Larch Campground at 10:00 a.m. on June 3, 2010. Contact Bill Kelley at the Lolo National Forest Supervisor’s Office, 406-329-3759, if you wish to attend. (See Section L, FAR Clause 52.236-27).

C- 5 Start Work

It is estimated that work will begin on September 7, 2010. Contract time will run continuously.

C- 6 Period of Performance

(See Section F, FAR Clause 52.211-10)

C- 7 Standard Specifications

See Section J for the list of Standard Specifications that are incorporated into this solicitation and any resultant contract.

C- 8 Drawings

See Section J for the listing of Drawings that are incorporated into this solicitation and any resultant contract.

PART I - THE SCHEDULE

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - https://www.acquisition.gov/far and the Agriculture Acquisition Regulations – www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection--Dismantling, Demolition, or Removal of Improvements (AUG 1996)

PART I - THE SCHEDULE

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - https://www.acquisition.gov/far and the Agriculture Acquisition Regulations – www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984) F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days. The time stated for completion shall include final cleanup of the premises.

PART I - THE SCHEDULE

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - https://www.acquisition.gov/far and the Agriculture Acquisition Regulations – www.usda.gov/procurement/policy/agar.html

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.236-72 Use of Premises (NOV 1996) H- 2 Fire Control

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. N/A

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Obtain a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H- 3 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

All claims arising under this clause will be submitted to the Contracting Officer.

H- 4 Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H- 5 Conformity With Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H- 6 Local Material Sources

(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.

The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.

When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.

Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.

(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.

H- 7 Samples, Tests, Cited Specifications Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H- 8 Barricades, Warning Signs, and Other The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

H- 9 Weed-Free Equipment In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.

Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.

H-10 Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H-11 Prework Conference

Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - https://www.acquisition.gov/far and the Agriculture Acquisition Regulations – www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1 Definitions (JULY 2004)

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (APR 1984)

52.203-7 Anti-Kickback Procedures (JUL 1995)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEPT 2007)

52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEPT 2006) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.219-3 Notice of Total HUBZone Set-Aside (JAN 1999) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.222-3 Convict Labor (JUNE 2003)

52.222-6 Davis-Bacon Act (JULY 2005)

52.222-7 Withholding of Funds (FEB 1988)

52.222-8 Payrolls and Basic Records (FEB 1988)

52.222-9 Apprentices and Trainees (JULY 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (JULY 2005) 52.222-12 Contract Termination - Debarment (FEB 1988)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (FEB 1988)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEPT 2006)

52.222-36 Affirmative Action for Workers with Disabilities (JUNE 1998)

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEPT 2006)

52.222-50 Combating Trafficking in Persons (FEB 2009)

52.223-6 Drug-Free Workplace (MAY 2001)

52.224-1 Privacy Act Notification (APR 1984)

52.225-13 Restrictions on Certain Foreign Purchases (JUNE 2008)

52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (SEP 2009) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.229-3 Federal, State, and Local Taxes (APR 2003)

52.232-5 Payments Under Fixed-Price Construction Contracts (SEPT 2002)

52.232-9 Limitation on Withholding of Payments (APR 1984)

52.232-23 Assignment of Claims (JAN 1986)

52.232-27 Prompt Payment for Construction Contracts (OCT 2008)

52.232-33 Payment by Electronic Funds Transfer--Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JULY 2002) Alternate I (DEC 1991)

52.233-3 Protest After Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

52.236-26 Preconstruction Conference (FEB 1995)

52.242-13 Bankruptcy (JULY 1995)

52.243-4 Changes (JUNE 2007)

52.244-6 Subcontracts for Commercial Items (APR 2010)

52.246-21 Warranty of Construction (MAR 1994) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004) Alternate I (SEPT 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) Alternate I (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.224-70 Confidentiality of Information (FEB 1988)

452.236-73 Archeological or Historic Sites (FEB 1988) 452-236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988)

I- 2 FAR 52.204-7 Central Contractor Registration (APR 2008)

(a) Definitions. As used in this clause-

"Central Contractor Registration (CCR) database" means the primary Government repository for Contractor information required for the conduct of business with the Government.

"Data Universal Numbering System (DUNS) number" means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

"Data Universal Numbering System +4 (DUNS+4) number" means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

"Registered in the CCR database" means that-

(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b)

(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "DUNS" or "DUNS +4" followed by the DUNS or DUNS +4 number that identifies the offeror's name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number-

(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company Physical Street Address, City, State, and Zip Code.

(iv) Company Mailing Address, City, State and Zip Code (if separate from physical).

(v) Company Telephone Number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(g) (1)

(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12 of the FAR; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor's CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.

(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.

I- 3 FAR 52.219-28 Post-Award Small Business Program Rerepresentation (APR 2009)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/services/contractingopportunities/sizestandardstopics/.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it FORMCHECKBOX is, FORMCHECKBOX is not a small business concern under NAICS Code ______________ assigned to contract number ______________.

[Contractor to sign and date and insert authorized signer’s name and title].

I- 4 FAR 52.225-9 Buy American Act--Construction Materials (FEB 2009)

(a) Definitions. As used in this clause-- “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is--

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, ad defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.

"Component" means any article, material, or supply incorporated directly into construction materials.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

"Cost of components" means--

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

"Domestic construction material" means--

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to the construction material or components listed by the Government as follows: None.

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that--

(i) The cost of domestic construction material would be unreasonable.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .