IFB - Custer NF FY09 Toilet Install - Full Solicitation Package.pdf

PDF 360 KB Posted

Attached to
CUSTER NATIONAL FOREST - FY09 TOILET REPLACEMENTS
Solicitation number
AG-0355-S-09-0020
Issued by

About this file

Full Solicitation

View the file

Other files

File Type Posted
Reva_Base Layout1 —
MacNab_Base Layout1 —
Reva_Base Layout2 —
Sand Dunes Base Layout2 —
Sand Dunes Base Layout1 —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-0355-S-09-0020

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

19 June 2009

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

285382

6. PROJECT NO.

7. ISSUED BY CODE 03H6 8. ADDRESS OFFER TO

East Side Acquisition Zone Gallatin National Forest P.O. Box 130 Bozeman, MT 59771

East Side Acquisition Zone Attn: Gary Stephens Gallatin National Forest P.O. Box 130 Bozeman, MT 59771 Mark as: “SEALED BID – AG-0355-S-09-0020”

9. FOR INFORMATION

CALL:

A. NAME Gary Stephens – C.O.

David Shimek - Engineer

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 406-587-6774 (C.O.) 406-657-6205 x201 (Engineer)

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

1. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

FY09 TOILET REPLACEMENTS – CUSTER NATIONAL FOREST

1. SF1442, SF1442 Back

2. Part I The Schedule, Section B: Supplies or Services and Prices/Costs

3. Section C: Project Description, Specifications and Statement of Work

4. Section E: Inspection and Acceptance

5. Section F: Deliveries or Performance

6. Section G: Contract Administration Data

7. Section H: Special Contract Requirements

8. Part II Contract Clauses, Section I: Contract Clauses

9. Part III List of Documents, Exhibits, and Other Attachments, Section J: List of Documents, Exhibits, and Other Attachments

10. Part IV Representations and Instructions, Section K: Representations, Certifications, and Other Statements of Bidders

11. Section L: Instructions, Conditions, and Notice to Bidders

12. Section M: Evaluation Factors for Award SBA CERTIFIED HUBzone CONTRACTOR SET-ASIDE UNDER FAR 52.219-3

Price Range: The Government's estimate is between $100,000 and $250,000.

11. The Contractor shall begin performance within 10 calendar days and complete it within 365 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by 1400 (hour) local time 20 July 2009 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

TIN:___________________

DUNS:_________________ (see Section L-8)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

Sol. No. AG-0355-S-09-0020 Custer National Forest FY09 Toilet Replacements

SECTION B - SERVICES AND PRICES

PART 1 - THE SCHEDULE

FY09 EAST SIDE TOILET REPLACEMENT PROJECT

CUSTER NATIONAL FOREST

BEARTOOTH, SIOUX, AND ASHLAND RANGER DISTRICTS

MONTANA AND SOUTH DAKOTA

BASE BID – ITEMS 1-6

Item Number Description

Method of

Measure

Pay Unit

Estimated Quantity Unit Price Total

1 Mobilization LSQ LS ALL XXXXXX

PROJECT LOCATION 1

Reva Gap Cascadian Toilet 1, w/ gravel parking area and concrete path

LSQ LS ALL XXXXXX

Reva Gap Cascadian Toilet 2, w/ gravel parking area and concrete path

LSQ LS ALL XXXXXX

4 Mac Nab Pond Toilet, w/ gravel parking wings and concrete path LSQ LS ALL XXXXXX

5 Mac Nab Pond 16'x25' Concrete Parking area LSQ LS ALL XXXXXX

PROJECT LOCATION 2

Poker Jim Lookout Toilet 1, w/ gravel parking area and concrete path

LSQ LS ALL XXXXXX

TOTAL

BASE BID

ITEMS 1 - 6

ADDITIVE/DEDUCTIVE ITEM #1 PROJECT LOCATION 3 (PRIORITY 1)

7 Sand Dunes Toilet 1, w/ gravel parking area and concrete path LSQ LS ALL XXXXXX

ADDITIVE/DEDUCTIVE ITEM #2 PROJECT LOCATION 3 (PRIORITY 2)

8 Sand Dunes Toilet 2, w/ gravel parking area and concrete path LSQ LS ALL XXXXXX

GRAND TOTAL

ITEMS 1 - 8

DESIGNATED METHOD OF MEASUREMENT

LSQ Lump Sum Quantities

SPECIAL NOTES:

1) The bidder must bid on all items. Round to the nearest cent.

2) In the event of an error in extending the bid prices, unit prices will govern unless otherwise determined by the Contracting Officer in accordance with applicable regulations.

3) Offers for quantities less than those listed in the numbered items may be rejected.

4) Payment for bond premiums in accordance with Clause 52.232-5. Payments under

Fixed-Price Construction Contracts shall not be in addition to the contract price but can be included under Mobilization.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 - Description of Work.

The work shall consist of furnishing and installing new concrete vault toilets; demolishing existing wood toilets and vaults; disposing of demolition debris and vaults off of National Forest System Lands;

excavation; site grading; aggregate placement; placing forms and pouring concrete; vault pumping; and seeding.

There are Historical considerations at Reva Gap Campground that require a specific toilet model. The toilet at Reva Gap shall be a Cascadian style by CXT concrete products or approved equal. All other toilets may be either Gunnison Style by CXT Concrete Products or Aspen Style by Missoula Concrete, or approved equal.

The intent of the contract is to provide for a complete project as described in the contract. Unless otherwise provided, contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies, and perform all work required to complete the project.

C-2 - Submittals. The contractor shall submit a Progress Schedule Prior to starting work.

C-3 - Project Locations.

• Project Location 1 – The project is located on the Sioux Ranger District at Reva Gap Campground and Mac Nab Pond Picnic Area. Reva Gap Campground is located approximately 20 miles East of Buffalo South Dakota. Mac Nab Pond Picnic Area is located approximately 7 miles East of Ekalaka, MT.

• Project Location 2 – The project is located on the Ashland Ranger District at Poker Jim Butte

Lookout. Poker Jim Butte Lookout is located approximately 30 miles South of Ashland, Montana.

• Project Location 3 – The project is located at Sand Dunes Picnic Area on the Beartooth Ranger

District. The project is located approximately 8 miles Southwest of Roscoe, Montana.

C-4 - Security. The Contractor shall be responsible for protecting all equipment and supplies for use on the project and stored on the site. The Contractor shall be responsible for all costs required to provide such protection.

C-5 - Disturbances. The Contractor may work from 0700 – 1800 Monday through Friday excluding weekends and holidays.

C-6 - Staging Area. The Contractor may stage equipment on-site. The Contractor shall operate all equipment and store, transport, and handle materials in a manner that will not damage the existing facilities, roads, parking lots, and landscaping.

C-7 - Wastewater Facilities. No facilities are available.

C-8 - Electrical. None available.

C-9 - Price Range. Between $100,000 and $250,000

C-10 - Pre-Bid Tour. There will not be a pre-bid tour of the project. Contact David Shimek at the Supervisor’s Office, Custer National Forest Billings, Montana for additional information (406) 657- 6205 ext. 201.

Contractors are urged to visit the site and review the existing conditions prior to bidding. Contact Tawni Parks at the Sioux Ranger District to arrange a visit, phone number (605) 797-4432. Contact Nate Gassmann at the Ashland Ranger District to arrange a visit, phone number (406) 784-2344. Contact Jeff Gildehaus at the Beartooth Ranger District to arrange a visit, phone number (406) 446-4584.

C-11 - Pre-Bid Conference. A pre-bid conference will not be held.

C -12 - Start Work. Toilets shall be installed no later than July 1, 2010.

C-13 - Period of Performance. The Contract shall be completed no later than July 1, 2010, however, the contractor must complete the project at all sites within 30 calendar days, once excavation has begun.

C-14 - Asbestos Containing Materials – The Contractor shall not use during construction or incorporate into the final construction product any material or product that contains more than 1% asbestos by dry volume as determined by the Polar Light Microscopy Method (less than 1% shall be considered under these specifications as “Asbestos Free”).

C-15 - Potable Water – The Contractor should supply all drinking water.

AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C-16 – Special Project Specifications

SECTION 00100

MEASUREMENT AND PAYMENT

PART I - GENERAL

1.1 Measurement and Payment - Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.

When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any pay item, suffixes will be added to the item number to differentiate between items to be bid.

1.2 Determination of Quantities - The following methods of measurement are used to determine contract quantities for payment.

For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified.

1.3 Units of Measurement - Payment will be by units defined and determined according to U.S.

Standard measure as follows:

A. Lump Sum – Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item. The quantity is designated as “All.” Estimated quantities of lump sum work shown in the contract are approximate.

1.4 Methods of Measurement - One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:

A. Contract Quantities (CQ) AND Design Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

1. As a result of changes in the work authorized by the Contracting Officer.

2. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities, that cause a pay item to change by more than 15 percent.

3. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by more than 15%. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

E. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.

PART II - PRODUCTS (Not Applicable)

PART III - EXECUTION (Not Applicable)

END OF SECTION

SECTION 00110

QUALITY CONTROL AND QUANTITY MEASUREMENT

1.1 Scope - This work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.

1.2 Measurement and Payment - No separate payment will be made for the work included under this section. Payment for this work is considered incidental to other items of work.

PART II - PRODUCTS (Not Applicable)

PART III - EXECUTION

3.1 Records of Inspection and Tests

A. This Section not used.

3.2 Certifications and Measurements

A. Quantity Measurements - The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Designed Quantity (DQ). The Contractor shall compute the quantities for periodic progress payments; the Contracting Officer will compute the quantities for the final payment based on measurements taken by the Contractor. All Contractor measurements are subject to verification. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.

The following format or one containing the following information will be acceptable to the Government:

Project ______________________ Contract No._______________________

Pay Item No.

Date

Station

Quantity or Measurement

Measured by (Initials)

SECTION 00151

MOBILIZATION

PART I: GENERAL

Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site.

PART II: PRODUCTS (NOT USED)

PART III: EXECUTION (NOT USED)

PART IV: MEASUREMENT AND PAYMENT

METHOD OF MEASUREMENT:

Units: Progress payments will be made as follows:

1. When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.

2. When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.

3. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10% of the original Contract amount, will be paid.

4. The total sum of all payments shall not exceed the original Contract amount bid for mobilization, regardless of the fact that the Contractor may have shut down the work on the project or moved equipment away from the project and then back again.

Prices and payment will be full compensation for the work described in this section. Payment will be made as Shown on the Schedule of Items.

SECTION 02119

DEMOLITION

1.1 SCOPE

This item shall consist of removal and disposal of structures, concrete foundations, cmp vaults, fiberglass vaults, and all other associated items and obstructions as shown on the drawings or encountered at the site.

PART II – PRODUCTS (NOT USED)

3.1 REMOVAL AND DEMOLITION

A. Unless shown otherwise, the Contractor may use any suitable means to remove the structure as long as the safety of the public and preservation of existing vegetation is provided for by the Contractor.

B. Vault contents shall be pumped and disposed of by a licensed and qualified septic pumping business in a legal manner off of National Forest System Lands.

C. Remove vaults, pads, and footings completely. The existing vault foundation and floor shall be broken into sufficiently small pieces to enable handling and disposal.

D. Materials such as but not limited to: metal, wood, fiberglass, brick, plastic, concrete, and all other vault and structure materials shall be completely removed.

E. Explosives shall not be used.

3.2 DISPOSAL

A. Remove demolished materials from the project site and legally dispose of them in any city, county or state approved landfill that accepts construction debris that may contain lead-based paint. The Contractor shall be responsible to obtain permission to dump the waste in the landfill facilities and pay any fees required.

B. Demolished materials shall not be allowed to accumulate on site. The removal and transport of all demolished debris shall be accomplished in a manner that will prevent spillage on adjacent surfaces and areas.

C. Burning of materials shall not be allowed.

3.3 SALVAGE

Contractor may salvage or recycle any of the building components. All items are the property of the Contractor.

3.4 BACKFILLING

The toilet pits at shall be backfilled according to the following.

A. After the existing toilet structure and all components have been removed, the remaining depression shall be backfilled. Backfill shall not be placed when the depression is saturated or flooded with water. Backfill shall be placed when the hole is free of standing water.

B. Place the entire contents of one bag of Hydrated Lime within each toilet pit prior to backfill.

Common backfill from excavated material shall be placed within the remaining depression.

Mound the backfill 6” above natural ground to allow for settlement.

C. Any additional backfill that is needed beyond the excavation created for the new toilet installations will be obtained within ½ mile of the site.

3.5 SITE RESTORATION, AND CLEANUP

All holes and depressions, resulting from the removal of structures, shall be backfilled with approved excavated excess material as directed by the CO. Restore site and the surrounding ground to as near normal condition as practicable in accordance with these specifications. Fill will be available on site. The finish elevation shall be hand raked and shoveled ready to receive seeding and to obtain a smooth uniform texture to blend into natural terrain.

SECTION 02240

CRUSHED AGGREGATE SURFACE COURSE

1.1 This item shall consist of furnishing, hauling, and placing of one or more courses of aggregate bases or surface courses, on an approved sub grade or base.

1.2 Method of Measurement – - Measurement of aggregate will be by the method as indicated in the Schedule of Items.

1.3 Reference Specifications – The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AASHTO T11 Materials Finer Than 75-pm (No. 200) Sieve in Mineral Aggregates by Washing.

AASHTO T27 Sieve Analysis of Fine and Coarse Aggregates AASHTO T89 Determining the Liquid Limit of Soils AASHTO T90 Determining the Plastic Limit and Plasticity Index of Soils AASHTO T96 Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine AASHTO T99 The Moisture-Density Relations of Soils Using a 2.5-kg (5.5-lb) Rammer and a 305-mm (12-in) Drop AASHTO T176 Plastic Fines in Graded Aggregates and Soils by Use of the Sand

Equivalent Test AASHTO T210 Aggregate Durability Index

PART II - PRODUCTS

2.1 Crushed Aggregate. Furnish hard, durable particles or fragments of crushed stone or gravel conforming to the size and quality requirements for crushed aggregate material normally used locally in the construction and maintenance of highways by Federal, State, or County agencies.

Submit sample to the COR for approval prior to placement. Aggregate shall be certified to be free of Erionite.

Furnish crushed aggregate with a maximum size of 1 inch as determined by AASHTO T 27 and T

11. Furnish crushed aggregate uniformly graded from coarse to fine and free of organic matter, lumps or balls of clay, and other deleterious matter.

Materials shall be obtained from an approved commercial source. Crushed aggregate for crushed base or surface courses shall be crushed stone, or gravel meeting the requirements shown in Table 02240-1.

Table 02240-1--Crushed Aggregate Quality Requirements for Base or Surface Courses

Requirement Description

AASHTO

Test Method Base Surfacing

Percent Wear T96 40 Max. 40 Max.

Durability Index, Coarse & Fine T210 35 Min. 35 Min.

Liquid Limit T89 25 Max. 35 Max.

Plasticity Index T90 6 Max. 0 - 9 Dust Ratio: % Passing No. 200 T11 2/3 Max. 2/3 Max.

% Passing No. 30 T27 Sand Equivalent T176 35 Min.

A. Gradation - Aggregate shall be well graded from coarse to fine within the gradation band.

Aggregate shall have good binder for proper compaction.

B. Fractured Faces - When crushed gravel is used, at least 50 percent by weight of the particles retained on No. 4 sieve shall have at least one fractured face. Naturally fractured faces may be included in the 50 percent requirement, provided the roughness and angularity produce strength characteristics equivalent to mechanically fractured faces.

C. Aggregate Certification - The commercial source shall provide a statement from a certified testing facility stating that aggregate from this source meets the requirements of these specifications and the designated gradation. The Contracting Officer may at any time sample the delivered materials and make compliance tests.

D. Variance from Specified Requirements - Variances from the crushed aggregate quality and gradation requirements shall be approved in writing by the Contracting Officer prior to use of the material on the project.

3.1 Preparation of Subgrade - The subgrade shall conform to the road typical template. Rippable rock, and boulders shall be excavated to a minimum depth of 6 inches below sub grade unless otherwise shown on the drawings and replaced with suitable cushion material obtained from within the excavation area or from sources approved by the Contracting Officer. Rocks larger than 4 inches that do not protrude above the subgrade more than one third of the depth of the base or surface course, or 3 inches, whichever is less, may be left in place.

Suitable excavated material shall be utilized in the preparation of the sub grade. Unsuitable and excess suitable, excavated material shall be disposed of as directed by the Contracting Officer.

Embankments shall be placed in compacted layers not exceeding 8 inches (loose measure).

The entire sub grade shall be compacted. Each layer shall be compacted. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases. Make at least three complete passes.

3.2 Mixing and Placing - Water shall be added to the aggregate in an amount necessary to provide the moisture content for compacting to the specified density. The moisture content of the aggregate shall be uniform throughout. The aggregate shall be spread in a uniform layer, with no segregation of size, and to a loose depth that shall have the required thickness when compacted.

If the aggregate base or surface course exceeds 6 inches, it shall be placed in two or more layers of approximate equal thickness. Hauling equipment shall be dispersed over the surface of the previously constructed layer to minimize rutting or uneven compaction.

3.3 Compaction - Each layer of aggregate shall be compacted. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases. Make at least three complete passes. Water shall be added for optimum compaction.

3.4 Thickness Requirement - The thickness of the compacted aggregate shall be minimum 4” compacted depth or as Shown on the Drawings.

Section 02130 Grading

Part 1 - GENERAL

This section specifies grading requirements for project.

Part 2 - PRODUCTS

Fill material shall be free from frozen or organic material, and rocks larger than 2 inches.

Part 3 - EXECUTION

Confine work to the immediate vicinity of the toilet installation.

Slopes should be graded to no less than 5% slope away from building for 5 feet, and smoothly blend into existing contours. Grade to uniform levels or slopes, round surfaces at abrupt changes in levels. Slope ground away from building walls and walks to facilitate drainage.

Grade all areas to produce uniform slopes.

Hand rake all areas that are disturbed. Remove all roots, brush, weeds and stones larger than 2 inches from the finish graded surface.

Control grading within 5 feet of buildings and all other structures to prevent water from running into excavated areas. Area within 5 feet of building shall be graded at no less than 5% (~3” per 5 ft). Remove all water, which accumulates in excavated areas.

Remove excess material, not required for grading, from the site.

Part 4 - MEASUREMENT AND PAYMENT

Measurement shall be lump sum.

Payment shall be as Shown on the Schedule of Items.

End of Section

SECTION 02910

SEEDING

This item shall consist of furnishing and placing approved seed mixtures on disturbed earth.

1.2 METHOD OF MEASUREMENT

Measurement of seeding will be by the method as indicated in the Schedule of Items.

2.1 MATERIALS

A. Seed shall be certified weed-free from commercial source of the mix shown in table 02910-01.

B. Do not use wet, moldy, or otherwise damaged seed in the work.

Table 02910-1 – Seed Mixture Furnish and apply the following kinds and amounts pure live seed (PLS):

Common Name – Variety Scientific Name %-of Mixture western wheat – rosana or rodan

Agropyron smithii 40% thickspike wheat – critana Agropyron dasystachym 30% slender wheat – pryor Agropyron trachycaulum 17% green needle grass – lodorm Stipa viridula 13%

Total Pure Live Seed (PLS) lbs/acre* 17.5

*Note: Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

3.1 SEEDING

A. Apply seed to finished slopes before final acceptance.

B. Do not seed during windy weather or when the ground is excessively wet, frozen, snow covered, extremely dry, cloddy, hard pan, or is otherwise untillable.

C. Broadcast seed at the rate required by any suitable method.

D. Protect seeded areas from traffic or pedestrian use while on site.

SECTION 03300

CAST-IN-PLACE CONCRETE

1.1 This section specifies cast-in-place concrete.

RELATED SECTIONS

03100 - Concrete Forms and Accessories.

03200 - Concrete Reinforcement.

REFERENCES

ACI 301 - Structural Concrete for Buildings.

ACI 304 - Recommended Practice for Measuring, Mixing, Transporting and Placing Concrete.

ACI 308 - Standard Practice for Curing Concrete.

ACI 318 - Building Code Requirements for Reinforced Concrete.

ASTM C94 - Ready-Mixed Concrete.

ASTM C150 - Portland Cement.

ASTM C260 - Air Entraining Admixtures for Concrete.

QUALITY ASSURANCE

Perform work in accordance with ACI 301.

Acquire cement and aggregate from same source for all work.

Use only 1 brand of cement and admixtures unless otherwise approved in writing by the COR.

Provide the COR with delivery ticket in accordance with ASTM C94 for each load of concrete.

Part 2 - PRODUCTS

2.1 Cement.

Type I or Type II Portland Cement: ASTM C150. Use only 1 brand of cement.

For areas with poor aggregate quality: Type II Portland Cement, ASTM C150. Use only 1 brand of cement.

Type III Portland Cement: ASTM C150. For use at the Contractor's option under Cold Weather Concreting and Curing and Proportioning Concrete for Cold Weather.

Aggregate.

ASTM C33, "Specifications for Concrete Aggregate,” Size Number 57.

For areas with poor quality aggregate, aggregate shall conform to ASTM C33 and meet the following minimum standards:

TEST ASTM LIMIT

Fine Aggregate Sieve Analysis C 33 (as specified below) Clay lumps & Friables C 142 2% Max Light Weight Material C 123 2% Max Material finer than C 117 3% Max No. 200 Sand Equivalent C 241 80% Min Soundness (NaSO4) C 88 10% Max

Coarse Aggregate Sieve Analysis C 33 (as specified below) Clay Lumps & Friables C 142 0.5% Max Light Weight Material C 123 1.0% Max

Gradation follows:

Fine Aggregate Coarse Aggregate Sieve Passing Size % Passing Sieve Passing Size % Passing (Weight) (Weight) 3/8 100 1-1/2 100 No. 4 90-100 1 90-100 No. 16 45-75 3/4 50-80 No. 30 25-55 3/8 15-40 No. 100 0-8 No. 4 0-10

Admixtures for Concrete.

Air-entraining admixtures - ASTM C260.

Water-reducing retarding admixtures - ASTM C494, Type D. Water-reducing, retarding admixtures may be used when approved by the COR. The time limit between batching and placing concrete may be extended up to an additional 2 hours. Use a quantity of admixture within the range of the manufacturer's recommendation. The amount of water may be reduced;

other proportions shall remain the same.

Furnish the following information to the COR for approval:

Brand name of the admixture.

Amount of admixture, per cubic yard of concrete to be used.

Reason for requesting the use of the admixture.

Water.

Clear, clean, and suitable for domestic consumption.

2.2 CONCRETE MIX

Schedule - Concrete Types and Finishes.

Proportion concrete in accordance with ACI 318. The strength of concrete (f'c), air entrainment, slump, and finish meet the requirements below:

Non-Structural Concrete, Walks and Slabs.

Unit Requirement Compressive Strength (f'c) (28 day) 3,000 psi Air Entrained 4-6% Slump (±1 inch) 4” Finish Broom finish or as specified on drawings

Add air entraining agent to normal weight concrete mix for work exposed to exterior.

Proportioning Concrete for Cold Weather.

For concrete placed under "Cold Weather Concreting and Curing" condition, the Contractor may elect to alter the required proportions in one of the following ways:

Type III Portland Cement.

Type III Portland Cement may be substituted in equal quantities for Type I or II Portland Cement.

Additional Cement.

An additional sack per cubic yard of Type I or Type II Portland Cement may be added.

Temperature Limits for Cold Weather Concrete.

Provide concrete having a minimum temperature of 50 degrees F and a maximum temperature of 90 degrees F at the time of placing. The temperature of the mixing water shall not exceed 140 degrees F. If aggregates are heated, heat uniformly with steam or water coil. Aggregate temperature shall not exceed 95 degrees F. Aggregate water mix temperature shall not exceed 80 degrees F. Do not use materials containing frost or icy lumps.

Proportioning Grout Fill.

Fine concrete aggregate with 3 sacks of cement per cubic yard and a maximum slump of 6 inches.

3.1 Mixing

Plant Batched and Transit Mixed.

Batch at a central plant and mix enroute to the project in transit mix trucks in compliance with ASTM C94. (ASTM C94 Sections 3 and 17 shall not apply to this contract).

Place truck or transit mixed concrete within a maximum of 1-1/2 hours after introduction of cement into the batch. In hot weather or due to other contributing factors, a time less than 1-1/2 hours may be required by the COR.

Time interval between placement of batches not to exceed 30 minutes.

Plant Batched and Project Mixed.

Batch aggregates at a central plant and add water, cement, and admixture at the project.

Meet all requirements specified for transit mix.

Add cement, water, and admixture by accurate measurement, using measuring devices approved by the COR.

3.2 Project Batched and Mixed.

Batch and mix at project site.

Methods and apparatus used to batch the design mix will be reviewed for approval by the

COR.

Mixer rated capacity not to be less than a 1 bag batch. Batch quantities requiring fractional bags will not be allowed.

Mix concrete a minimum period of 1-1/2 minutes after all materials are in the drum.

Hand Mixed.

Hand mixing may be allowed only upon written approval of the COR. Batches not to exceed 1/2 cubic yard in volume.

3.3 Mix Adjustments

After the mix period but no later than 15 minutes from start of mixing, water may be added once for purposes of acquiring minimum slump, provided specified water-cement ratio is not exceeded. Adding water beyond these conditions constitutes retempering which will not be allowed. When water is added, an additional 20 revolutions at mixing speed is required.

Air-entraining admixtures will not be allowed to be added after the start of mixing for purposes of acquiring minimum air content.

3.4 Concrete Placement

Notify COR a minimum of 24 hours prior to placement.

Convey concrete from a mixer to the forms as near final position as practical in a manner which will prevent segregation or loss of materials.

Place concrete in maximum 18 inch horizontal layers.

Immediately after placing, thoroughly compact concrete with mechanical vibrators.

Hand tamping or "spudding" when permitted, will be approved in writing by the COR.

Footings may be placed separate from foundation walls. Provide minimum 2 x 3 x 18 inch key at 3 foot intervals.

Place each concrete section in a continuous operation, such as bottom slab, walls, and top slab.

Do not drop concrete freely from higher than 4 feet above the surface of concrete being poured.

Do not place concrete in water or allow water to rise over freshly placed concrete until a set is sufficient to prevent damage.

3.5 Seal Concrete Placement

Seal concrete may be deposited under water in a compact mass and in approximate horizontal layers without vibrating or tamping. Vibrate or tamp seal concrete when not placed under water.

Use tremie tube, closed bottom-dump bucket, or other means approved in writing by the

COR.

Tremie tubes shall be not less than 10 inches in diameter and bottom-dump buckets shall not be less than 1/2 cubic yard capacity.

Place point of discharge upon the prepared foundation or upon concrete already placed, then discharge and raise slowly during the discharge travel.

Avoid agitating the mixture or allowing water to enter the tube or bucket.

3.6 Protection from Rainfall

Protect flat work during periods of precipitation with adequate waterproof covering.

Support covering so that finishing may be performed and initial set obtained without damage. Dragging of tarpaulins or other covering across unset concrete will not be permitted.

3.7 Curing

Commence curing and protection of concrete immediately after placing. Cure Type I and Type II Portland Cement 7 days continuously and Type III Portland Cement 3 days continuously by one of the following methods:

Water Curing.

Keep all surfaces of concrete and forms left on concrete wet. Shade concrete from sun with covering material or with sand or sawdust on slab, except during periods of required finishing. Use of sprinklers or flooding is permitted on slabs.

Membrane Curing.

A liquid membrane-forming material may be used for curing at the Contractor's option, except on slabs receiving resilient floorings. Complete required surface finish prior to application of curing compound; use water curing during finishing period. Spray material to surface at the rate of 1 gallon per 300 square feet in 2 applications, resulting in a coverage of 1 gallon per 150 square feet. Apply first coat immediately after acceptance of finish. Thoroughly wet concrete with water and apply material just as surface film of water disappears. Apply second coat after first application has set. Recoat any rupture to the membrane seal immediately or use water cure method.

Cold Weather Concreting and Curing When descending air temperature at the project falls below 40 degrees F the Contractor may at their option, continue concreting under conditions stated below. Normal concreting operations may resume when the temperature at the site exceeds 40 degrees F.

Provide cover and heating equipment sufficient to maintain the temperature of the concrete at not less than 50 degrees F for a period of 3 days for Type I and Type II cement. Maintain the temperature at not less than 50 degrees F for a period of 2 days for Type III cement or when one additional sack of Type I or Type II cement is added.

Provide additional protection to prevent the concrete temperature from dropping more then 40 degrees F in the 24 hour period following the required protection period.

Keep all surfaces of concrete and any forms remaining on concrete wet. Remove and replace any concrete injured by frost and freezing as directed by the COR.

field quality control All tests will be performed by and at the expense of the Contractor. Concrete for the samples shall be provided by the Contractor at no additional cost to the Government.

Samples will be taken per each truck. If the measured slump falls outside the specified limits, a check test shall be made immediately on another portion of the same load. In the event of a second failure, the concrete shall be considered to have failed the requirements of the specification.

3.8 TESTING

The following concrete tests will be taken:

Slump.

Testing will be in accordance with ASTM C143. If the slump is greater than the specified range, the concrete will be rejected.

Part 4 - MEASUREMENT AND PAYMENT (not used)

SECTION 03100

CONCRETE FORMS AND ACCESSORIES

PART 1 - GENERAL

1.1 SUMMARY

This section specifies construction of concrete forms.

PART 2 - PRODUCTS

2.1 MATERIALS

Plywood: B-B Plyform.

Steel.

Prefabricated.

Lumber.

Standard grade, (concealed surfaces only).

Form Ties and Spreaders.

Form Ties: Snap-off type, galvanized metal, fixed length, cone type, with waterproofing washer and leaving no metal within 1 inch of the concrete face.

Form Release Agent.

Colorless mineral oil which will not stain concrete, or absorb moisture, or impair natural bonding or color characteristics of coating intended for use on concrete.

Diesel or oil based release agents shall not be used.

PART 3 - EXECUTION

3.1 CONSTRUCTION

Construct forms to prevent leakage of mortar, and any shifting or deformation during the placement and finishing of concrete.

Wet forms to allow removal without damaging the concrete per manufacturer’s instructions.

Joints.

Arrange joints vertically or horizontally.

3.2 INSPECTION

Obtain COR inspection and approval of forms at least 4 hours prior to placing concrete. Notify

COR at least 24 hours in advance of concrete pour that forms will be ready for inspection.

3.3 CLEANING

Remove all sawdust, shavings, and other debris from within the forms.

Form Removal.

Do not disturb forms until concrete has gained enough strength to carry its own weight and such construction loads as may occur.

Loosen forms carefully. Do not wedge pry bars, hammers, or tools against finish concrete surfaces scheduled for exposure to view.

PART 4 - MEASUREMENT AND PAYMENT (NOT USED)

SECTION 03154

CONSTRUCTION JOINTS

PART 1 - GENERAL

1.1 SUMMARY

This section specifies construction joints in cast-in-place concrete.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION

Form construction joints horizontally or vertically as required. Provide #4 x 12 inch steel dowels at 18 inches on center in combination with required reinforcement.

3.2 INSTALLATION

Install waterstops in designated construction joints.

Before depositing new concrete on or against concrete that has set, thoroughly roughen and remove laitance or foreign matter, and saturate with water. Flush with a coat of neat cement.

Place a grout coat of equal parts of sand and cement of same materials used in the concrete.

Place new concrete before grout has set.

At horizontal joints where waterstops are used, place the first 4 to 5 inches of concrete containing a mix in which coarse aggregate is 1/2 or less the quantity used in the regular concrete mix.

Construct joints in structural concrete perpendicular to principle lines of stress and, in general, at points of minimum shear.

SECTION 03200

CONCRETE REINFORCEMENT

PART 1 - GENERAL

1.1 SUMMARY

This section specifies reinforcing bars and welded wire fabric.

1.2 REFERENCES

ACI 301 - Structural Concrete for Buildings.

ACI 318 - Building Code Requirements For Reinforced Concrete.

ACI SP-66 - American Concrete Institute - Detailing Manual.

ANSI/ASTM A497 - Welded Deformed Steel Wire Fabric for Concrete Reinforcement.

PART 2 - PRODUCTS

2.1 MATERIALS

Reinforcement Steel.

#4 Bar reinforcement - ASTM A615 Grade 60.

Reinforcing Fabric.

Welded wire fabric - ASTM A185.

2.2 ACCESSORY MATERIALS

Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for strength and support of reinforcement during concrete placement conditions including load bearing pad on bottom to prevent vapor barrier puncture.

PART 3 - EXECUTION

3.1 INSTALLATION

Secure reinforcement against displacement caused by construction loads or placing of concrete.

Tie all bar intersections with annealed iron wire of not less than 16 gauge. Hook or support wire mesh during placing concrete slabs to insure placement as detailed.

Field bending and cutting will be permitted if performed in accordance with the ACI Code.

Keep reinforcement free of dirt, oil, paint, grease, mill scale, and loose or thick rust.

Place, support and secure reinforcement against displacement. Do not deviate from required position.

Do not displace or damage vapor barrier. Accommodate placement of formed openings.

Conform to ACI 318 for concrete cover over reinforcement.

SECTION 13122

PRECAST CONCRETE VAULT TOILET

A. Work specified under this section consists of furnishing and installing precast concrete vault toilets. This work also includes clearing and grubbing, excavation, backfill, finish grading, forming and pouring concrete for accessible trails/pathways.

B. Location and orientation of toilets and paths shall be shown on the drawings and as staked in the field by the COR. Location on drawings are approximate.

C. Contractor shall coordinate the delivery with the supplier: The supplier shall be Missoula Concrete Construction or CXT Concrete Products or approved equal source and approved equal toilets. All toilets shall have vent in door, accessible signage, manufacturer supplied lock, and be ADA compliant.

Reva Gap Campground shall have two (2) Cascadian Style Vault Toilets, one left hand and one right hand model, full screen, dark brown siding, with simulated dark gray shake roof.

McNabb Pond Picnic Area shall have a Gunnison/Aspen style or equal right hand model, full screen, simulated dark brown barnwood siding, with simulated dark gray shake roof.

Poker Jim Lookout Toilet shall be a Gunnison/Aspen style or equal left hand model, full screen, simulated dark brown barnwood siding, with simulated dark gray shake roof. Access to Poker Jim lookout may be difficult.

Sand Dunes Picnic Area shall have one left hand and one right hand Gunnison/Aspen style or equal, full screen, simulated dark brown barnwood siding, with simulated dark gray shake roof.

Toilets shall be installed per manufacturer’s recommendations and the following specifications. Contractor shall verify the toilet will have vent stack oriented in the southern direction before ordering materials.

1.2 Measurement and Payment

The contract will be paid for at a Lump Sump price per each toilet. The Lump Sum payment per each toilet shall include the installation of each precast concrete toilet as shown on the drawings and in accordance with the manufacturer’s specifications and these specifications. Lump Sum payment shall include all demolition, vault pumping, seeding, site grading, excavation, aggregate placement, and other related site work that is required for a complete and finished job.

Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.

2.1 MATERIALS

A. Bedding material to be sand or 1/2” minus crushed or screened gravel or as recommended by manufacturer.

B. Sealant between vault and toilet floor to be 1"x1" Butyl Rubber Sealant or as recommended by manufacturer.

C. Crushed aggregate shall as shown in other specifications.

3.1 LOCATION

A. Toilet location(s) and orientation(s) will be staked in the field by the COR. Plans are for approximate location only. All toilet vent pipes shall be located in the southern orientation.

3.2 CLEARING AND GRUBBING

A. Clearing of any brush or trees may be required to place toilets and to allow safe operation of the crane. Remove all brush, stumps, trees, organic matter, and other deleterious materials form the excvation, parking and trail areas. All materials may be scattered in the Forest.

B. The removal of the existing toilets structures and vaults shall be in accordance with Demolition.

3.3 EXCAVATION AND ELEVATION

A. Comply with applicable OSHA standards for excavation.

B. Excavate for the installation of the toilet vault to a depth that will allow the structure site to be free-draining after installation is completed. Allow for a 2-inch leveling course beneath the toilet vault. Stockpile topsoil in separate pile at sites where topsoil is present.

Excavate a hole sufficient enough to place the toilet to meet finished floor requirements as staked, and as recommended by manufacturer.

C. Finish floor elevation shall be 6 inches above natural grade measured at the front

(entrance) of the exterior slab unless otherwise shown on the plans, staked in the field, or approved by the COR. All sides of the toilet shall slope away at minimum 5% for 5 feet.

Installation shall provide drainage away from the toilet for a minimum of 5 feet.

Contractor shall install buildings at these sites with the floor elevation within plus or minus

0.05 feet of the specified floor elevation. Finish floor elevation shall be set so it is accessible, less than a 5% grade to enter toilet.

D. No excavation shall be left open more than 5 days unless otherwise approved by the COR.

E. All excavations left open overnight shall be enclosed with plastic orange mesh fencing secured to steel posts, and approved by the COR.

F. All cut slopes shall be 2:1 or flatter. All fill slopes shall be 4:1 or flatter, or as approved by

COR.

3.4 BACKFILL AND COMPACTION

A. Compact the bottom of the vault excavation with a minimum of three passes with a whacker-type mechanical compactor. Add water as necessary to achieve 90% optimal compaction.

B. Install a 2-inch thick lift of crushed gravel material at bottom of vault excavation for leveling course. Compact leveling course with mechanical compactor. Grade leveling course so there will be no high spots in the middle of vault bottom. Compact with second pass of mechanical compactor.

C. Set vault in place with suitable equipment. Verify vault is level within 1/4 inch between corners. Backfill around structure. Use excavated material for backfill except that rocks larger than four inches in maximum dimension shall not be placed within six inches of exterior of vault walls.

D. Backfill material shall be placed in eight-inch loose lifts and mechanically compacted with minimum of three passes with a mechanical compactor and until visual displacement ceases. Add water to ensure proper compaction.

3.5 FINISH GRADING

A. Place excess excavated material around structure. Finish grade shall be approximately 6 inches above native ground. Slope material away from structure for drainage. Provide smooth transition with surrounding undisturbed material. Minimum slope away from structure shall be 5%.

B. Place crushed aggregate to within ½” of top of concrete slab. Aggregate shall encircle toilet and shall be a minimum of 5’ wide and 6” compacted depth. Compact aggregate with minimum three passes with mechanical compactor. Add water to ensure proper compaction.

C. Construct 5’ accessible path with a 6” compacted depth of crushed aggregate as shown on plans or as staked in field by COR. Plans are for approximate location only. Side slopes of path shall be 4:1.