WageDecisionID140088.docx

DOCX document 22 KB Posted

Attached to
Idaho Panhandle NF, Deer Creek Bridge Federal contract opportunity
Solicitation number
AG-02RC-S-14-0073
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

Wage Decision ID

View the file

Other files for this federal contract opportunity

Other files attached to Idaho Panhandle NF, Deer Creek Bridge, newest first.
File Type Posted
DeerCrkBridge_sol.doc DOC document
SuppSpcsDeerCrkFSSS.doc DOC document
DrawingsDeerCreekBridge.pdf PDF
PAST_PERFORMANCE_SURVEY.docx DOCX document
WorkersCompForm.docx DOCX document
SF24BidBondFillForm.pdf PDF
FoodStorage2011Signed.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: ID140088 01/03/2014 ID88

Superseded General Decision Number: ID20130091

State: Idaho

Construction Type: Highway

Counties: Benewah, Boundary, Clearwater and Lewis Counties in Idaho.

HIGHWAY CONSTRUCTION PROJECTS

Modification Number Publication Date 0 01/03/2014

LABO0238-013 06/01/2013

Rates Fringes

LABORER (MASON TENDER

(Cement/Concrete))...............$ 24.10 10.65

PLAS0072-001 06/01/2013

ZONE 1:

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 26.01 12.14

Zone Differential (Add to Zone 1 rate): Zone 2 - $2.00

BASE POINTS: Spokane, Pasco, Lewiston, Wenatchee

Zone 1: 0-45 radius miles from the main post office

Zone 2: Over 45 radius miles from the main post office

SUID2013-016 06/17/2013

Rates Fringes

CARPENTER (Form Work Only).......$ 26.57 8.10

ELECTRICIAN......................$ 26.83 11.94

HIGHWAY/PARKING LOT STRIPING:

Painter.........................$ 23.80 6.67

LABORER: Asphalt, Includes Raker, Shoveler, Spreader and Distributor......................$ 22.86 9.40

LABORER: Common or General......$ 22.92 10.01

LABORER: Concrete Saw (Hand Held/Walk Behind)................$ 23.98 11.05

LABORER: Grade Checker..........$ 23.41 10.78

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 25.97 10.95

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 25.35 11.55

OPERATOR: Broom/Sweeper.........$ 26.82 11.55

OPERATOR: Bulldozer.............$ 25.73 11.51

OPERATOR: Crane.................$ 27.18 10.97

OPERATOR: Crusher...............$ 25.06 9.23

OPERATOR: Grader/Blade..........$ 26.00 10.30

OPERATOR: Hydroseeder...........$ 24.76 11.51

OPERATOR: Loader................$ 25.76 10.31

OPERATOR: Mechanic..............$ 26.00 9.93

OPERATOR: Oiler.................$ 25.66 9.23

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 25.66 11.03

OPERATOR: Roller (Subgrade).....$ 22.24 8.57

OPERATOR: Roller................$ 25.49 11.55

OPERATOR: Rotomill..............$ 29.78 4.52

OPERATOR: Screed................$ 25.71 11.55

TRAFFIC CONTROL: Flagger.......$ 21.46 10.12

TRAFFIC CONTROL:

Laborer-Cones/ Barricades/Barrels - Setter/Mover/Sweeper.............$ 22.66 10.90

TRUCK DRIVER: Dump Truck........$ 23.40 10.75

TRUCK DRIVER: Lowboy Truck......$ 22.12 13.20

TRUCK DRIVER: Oil Distributor Truck................$ 22.54 12.35

TRUCK DRIVER: Water Truck.......$ 23.12 10.75

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

File details come from the government source that posted it. Updated .