KreistCrk_RFP.doc

DOC document 365 KB Posted

Attached to
IPNF, Bonner Ferry RD, Kreist Creek Culvert
Solicitation number
AG-02RC-S-0101
Issued by

About this file

RFP Solicitation

View the file

Other files

File Type Posted
Kreist_Amend_2.doc DOC document
Kreist_Amend_1.doc DOC document
FoodStorage2011Signed.pdf PDF
WorkersCompForm.docx DOCX document
Kreist_Creek_AOP-FSSS.docx DOCX document
PAST_PERFORMANCE_SURVEY.docx DOCX document
Kreist_Creek-_Final_Plans.pdf PDF
WageDecision.docx DOCX document
SF24BidBondFillForm.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OFFEROR'S COPY

NOTE: Attached forms must be completed and submitted intact.

Issuing Office:

U.S. Department of Agriculture Forest Service Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene, ID 83815

Offers Are Solicited For:

PROJECT

Kreist Creek Culvert Bonners Ferry Ranger District

Solicitation No. RFP AG-02RC-S-15-0101
HELP PREVENT FOREST FIRES

IMPORTANT - NOTICE TO OFFEROR

1. This is a complete copy. Information and instructions for submission of proposals as well as contract provisions and specifications are contained in this OFFEROR REFERENCE COPY. This copy should be retained by offerors.

2. Note: An offer guarantee (Bid Bond) IS REQUIRED. Performance and Payment Bonds will be required of the successful offeror. (See Section I, FAR Clause 52.228-15.)

FS-6300-45 (11/79)

TABLE OF CONTENTS

Page(s)

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

1 - 2

SECTION B - SUPPLIES OR SERVICES AND PRICES

B- 1 - Schedule of Items

B- 2 - Payment for Bond Premiums

SECTION C - DESCRIPTION/SPECIFICATIONS

4-5

C- 1 - Scope of Contract

C- 2 - Project Location

C- 3 - Restrictions

C- 4 - Standard Specifications

C- 5 – Statement of Work/Specifications

C- 6 – Attachments to Statement of Work/Specifications

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 - Clauses Incorporated by Reference

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 - Clauses Incorporated by Reference

F- 2 - Commencement, Prosecution, and Completion of Work

SECTION G – CONTRACT ADMINISTRATION DATA

G- 1 – Post Award Conference

SECTION H - SPECIAL CONTRACT REQUIREMENTS

9-17

H- 1 - Physical Data

H- 2 - Key Personnel

H- 3 - Fire Control

H- 4 - Loss, Damage, or Destruction

H- 5 - Incidental Payment Items

H- 6 - Conformity with Drawings and Specifications

H- 7 - Local Material Sources

H- 8 - Samples, Tests, Cited Specifications

H-9 - Barricades, Warning Signs, and Other Devices

H-10 - Weed Free Equipment

H-11 – Equipment Rental

H-12 - Landscape Preservation H-13 - Invoice Processing Platform (IPP)

H-14 - Contractor Performance Assessment Reporting System

H-15 – Reference FAER 52.236-19 Accident Prevention

H-16 - State of Idaho’s Notice to Offeror

H-17 – Biobased Product Utilization

H-18 – Contractor Workforce Certification

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

18-32

I- 1 - Clauses Incorporated by Reference

I- 2 - Reporting Executive Compensation and First-Tier Subcontract Awards

I- 3 - System for Award Management Maintenance

I- 4 - Assurance Regarding Felony Conviction or Tax Delinquent Status for Corporate

Applicants Alternate I

I-5 - Post Award Small Business Program Representation

I-6 - Affirmative Procurement of Biobased Products Under Service and Construction Contracts

I-7 - Buy American Act - Construction Materials

I-8 - Bid Guarantee

I-9 - Performance and Payment Bonds - Construction

I-10 - Alternative Forms of Security

I-11 – Federal, State, and Local Taxes

I-12 - Reimbursement For Bond Premiums - Fixed Price Construction Contracts

I-13 - Providing Accelerated Payment to Small Business Subcontractors

I-14 - Permits and Responsibilities

I-15 - Alterations In Contract

I-16 - Authorized Deviations in Clauses

I-17 - Order of Precedence - Construction

PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

33-34

J- 1 - Wage Determination

J- 2 – Supplemental Specifications

J- 3 - Drawings

J- 4 – Exhibits

J-5 – State of Idaho Certificate of Verification of Workers’ Compensation Insurance form

J-6 – SF24 Bid Bond Form

J-7 – Owner/Client past Performance Survey form

PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER

35-38

STATEMENTS OF OFFERORS AND RESPONDENTS

K- 1 - Annual Representations and Certifications

K- 2 – Commerical and Government Entity Code Reporting

K- 3 - Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction Alternate I

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

39-45

AND RESPONDENTS

L- 1 - Solicitation Provisions Incorporated by Reference

L- 2 – System for Award Management

L- 3 – Inquiries

L- 4 – Facsimile Proposals & E-Mail Proposals

L- 5 - Instructions for the Preparation of Technical and Business Proposals

L- 6 - Amendments to Proposals

L- 7 - Type of Contract

L- 8 – Construction Wage Requirements—Secondary Site of the Work

L- 9 - Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity

For Construction

L-10 - Notice of Buy American Act Requirements - Construction Materials

L-11 - Service of Protest

L-12 - Site Visit (Construction)

L-13 - Preparation of Proposals – Construction

L-14 - Authorized Deviations in Provisions

SECTION M - EVALUATION FACTORS FOR AWARD

46-47

M- 1 – Award Determination

M- 2 – Evaluation Criteria

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

RFP AG-02RC-S-15-0101

2. TYPE OF SOLICITATION

FORMCHECKBOX

SEALED BID (IFB)

FORMCHECKBOX

NEGOTIATED (RFP)

3. DATE ISSUED

7/2/2015

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

705955

6. PROJECT NO.

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

USDA, Forest Service

Idaho Montana Acquisition Team 3815 Schreiber Way Coeur d Alene, ID 83815 USDA, Forest Service

Idaho Montana Acquisition Team

3815 Schreiber Way

9. FOR INFORMATION

CALL:

a. NAME

RITA J. LOPER, C.O.

Josh Nelson (technical)

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(208) 765-7497

(208) 265-6610

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Kreist Creek Culvert Bonners Ferry Ranger District

Idaho Panhandle National Forests Boundary County, Idaho Price Range is:

Between $250,000 and $500,000.

This project is HUBZone set-aside

11. The Contractor shall begin performance within 10 calendar days and complete it within 10/30/2015 calendar days after receiving

FORMCHECKBOX

award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F, Clause 52.211-10)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12b.)

FORMCHECKBOX

YES

FORMCHECKBOX

NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a.

Sealed offers in original and * copies to perform the work required are due at the place specified in Item 8 by 4:00 pm local time 8/3/2015 date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

b.

An offer guarantee

FORMCHECKBOX

is, FORMCHECKBOX is not required. (If “is required” see AGAR Clause 452.228-70) c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212

1442-101

STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

Duns No. ______________________________________ email: ___________________________________________

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE

FACILITY CODE

17.

The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

FORMCHECKBOX

10 U.S.C. 2304(c)( )

FORMCHECKBOX

41 U.S.C. 253(c)( )

26. ADMINISTERED BY

CODE

27. PAYMENT WILL BE MADE BY

USDA – Forest Service

Idaho Montana Acquisition Team 3815 Schreiber Way

All invoices will be processed using the Department of Treasury’s Invoice Processing Platform (IPP), visit http://www.ipp.gov to learn more. Contractors must follow the instructions on how to register and submit invoices via IPP.

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

FORMCHECKBOX

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

FORMCHECKBOX

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

RITA J. LOPER

30b. SIGNATURE

30c. DATE

31b. UNITED STATES OF AMERICA

BY

31c. DATE

Computer Generated

STANDARD FORM 1442 BACK (REV. 4-85)

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Kreist Creek Culvert Bonners Ferry Ranger District

Idaho Panhandle National Forests Boundary County, ID

B- 1 - SCHEDULE OF ITEMS

ITEM

NO.

DESCRIPTION
METHOD of MEAS.
PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

15101
Mobilization
LSQ
LS
1
xx
15221
Construction Survey and Staking
LSQ
LS
1
xx
15713
Soil Erosion And Pollution Control
LSQ
LS
1
xx
20304
Removal of Existing Corrugated Metal Culvert
LSQ
LS
1
xx
20806
Structure Excavation & Backfill
LSQ
LS
1
xx
25101
Placed Riprap, Class 5
CQ
CY
110
27250
Geocell Abutment Stabilization, 6 Inch Depth
CQ
SY
145
30809
Crushed Aggregate
CQ
CY
25
553A01
Precast Concrete Member, Stemwall Footings
LSQ
LS
1
xx
60304
Steel Structural Plate Arch, 15' -0" Span, 6'-7" Rise, 0.111" Thickness
CQ
LF
96
62201a
Hydraulic Excavator With Thumb
AQ
HR
8
62201b
Large Dump Truck
AQ
HR
8
62503
Seeding And Mulch, Dry Method
LSQ
LS
1
xx
64808
Rock Cross-Vane Structure
AQ
EA
5
67050
Slash Filter Windrow
LSQ
LS
1
xx

* Designated Method of Measurement:

DQ – Designed Quantities; AQ - Actual Quantities, LSQ - Lump Sum Quantities; SQ – Staked Quantities; CQ – Contract Quantities

B- 2 Payment for Bond Premiums Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS

C- 1 Scope of Contract

This project includes removal of an existing 6’-6” x 6’-0” x 88’-0” culvert and replacing with a 15’-0” x 6’-7” x 96’-0” Structural Plate Arch with precast concrete footings. This work will consist of constructing a stream channel through the pipe and installing grade control structures within the culvert and potentially outside the culvert near the inlet and outlet. Additionally a segment of road shall be reconstructed and shaped to provide adequate approaches over the new structure together with commercial source surface aggregate placed on the reconstructed segment of road. This work will include placing commercial source riprap material at the inlet and outlet and for construction of the grade control structures.

C- 2 Project Location

Forest Service Road 2517 is approximately 38 miles Northeast of Bonners Ferry, Idaho. Located at T.64N. R. 2E. in the NW corner of section 13, Boise Meridian. Latitude and Longitude of the site is 48°54'15.68"N, 116° 9'4.06"W. Travel from Bonners Ferry, Idaho on U.S. Highway 95 North for approximately 30 miles to the Forest Service Road 2517 Junction. Turn right onto Forest Service Road 2517 South for approximately 6.8 miles to Forest Service Road 2517A. Turn right onto road 2517A and continue for approximately 0.7 miles to Kreist Creek culvert crossing.

C-3 Restrictions. In-stream work will be only allowed after July 15th and prior to September 15th of any construction year without prior approval by the Contracting Officer. Contractor shall develop and submit for Contracting Officer approval a Plan of Operation for de-watering and sediment containment to meet project BMP’s and Permits for Erosion and Sediment Control a minimum of 15 days prior to any in-stream work. Include in the Plan of Operation, Contractor’s proposed traffic and traffic sign placement and planned dates for any road closure.

C- 4 STANDARD SPECIFICATIONS: " FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this Solicitation and any resultant contract.

Copies of the " FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS" are available for download at the following URL:

http://www.wfl.fha.dot.gov/design/specs/fp03.htm.

The following “FHWA FP-03 Standard Specifications FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.

Spec No Title Section 101 – Terms, Format, and Definitions Section 102 – Bid, Award, and Execution of Contract

Section 103 – Scope of Work

Section 104 – Control of Work

Section 105 – Control of Material

Section 106 – Acceptance of Work

Section 107 – Legal Relations and Responsibility to the Public

Section 108 – Prosecution and Progress

Section 109 – Measurement and Payment

Section 151 – Mobilization

Section 152 – Construction Survey and Staking

Section 153 – Contractor Quality Control

Section 155 – Schedules for Construction Contracts

Section 156 – Public Traffic

Section 157 – Soil Erosion Control

Section 203 – Removal of Structures and Obstructions

Section 204 – Excavation and Embankment

Section 208 – Structure Excavation and Backfill for Selected Major Structures

Section 251 – Riprap

Section 308 – Minor Crushed Aggregate

Section 553 – Prestressed Concrete

Section 603 – Structural Plate Structures

Section 622 – Rental Equipment

Section 625 – Turf Establishment

Section 703 – Aggregate

Section 704 - Soil

Section 705 – Rock

Section 707 – Metal Pipe

Section 713 – Roadside Improvement Material

Section 718 – Traffic Signing and Marking Material

Section 725 – Miscellaneous Material

See Section J for list of Supplemental Specifications and Drawings.

C-5 AGAR 452.211-3 Statement of Work/Specifications. (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C-6 AGAR 452.211-4 Attachments to Statements of Work/Specifications. (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract

PART I - THE SCHEDULE

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996) 52-246-6 Inspection-Time and Materials and Labor Hour (MAY 2001)

PART I - THE SCHEDULE

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984) F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 15, 2015. The time stated for completion shall include final cleanup of the premises.

SECTION G - Contract Administration Data

AGRICULTURE ACQUISITION REGULATIONS (48 CFR CHAPTER 4) CLAUSES

http://www.dm.usda.gov/procurement/policy/agar.html

G-1 AGAR 452-215-73 Post Award Conference (NOV 1996). A post award conference with successful offeror is required. It will be scheduled and held before work begins, after the date of contract award. The conference will be held at a location to be determined as agreed upon.

PART I - THE SCHEDULE

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H- 1 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.

H- 2 AGAR 452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

Superintendent/On-site Contractor Representative (on-site supervisor)

Quality Control Officer

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H- 3 Fire Control

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. NOT REQUIRED

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Obtain a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H- 4 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

All claims arising under this clause will be submitted to the Contracting Officer.

H- 5 Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H- 6 Conformity With Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H- 7 Local Material Sources

(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.

The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.

When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.

Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.

(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.

H- 8 Samples, Tests, Cited Specifications Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H-9 Barricades, Warning Signs, and Other Devices The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

H-10 Weed-Free Equipment In order to prevent the potential spread of noxious weeds into the project area, the Contractor shall be required to furnish the Contracting Officer with proof of weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment (equipment that operates off existing roads) prior to entry on the project area. This cleaning shall remove all dirt and plant parts and material that may carry noxious weed seeds into the project area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within the project area. All subsequent move-ins of construction equipment shall be treated the same as the initial move-in.

Prior to initial move-in of all construction equipment, and all subsequent move-ins, the Contractor shall make equipment available for inspection at an agreed location.

H- 11 Equipment Rental. This work consists of furnishing and operating equipment for work ordered by the CO not otherwise provided for under the contract. This work shall be authorized in advance by the Government and there is no guarantee that any hourly work will be ordered. Make equipment available for inspection and approval before use. Furnish and operate equipment with such auxiliary attachments, oilers, etc., as are usually needed for efficient operation of the equipment. Keep the equipment in good repair and operating condition. Daily written records, such as shift tickets to record the number of unit‑hours of operation are required to be signed and submitted with invoices. Do not measure time for moving equipment between project work sites. Do not measure non-operable equipment or equipment dependent upon another piece of non-operable equipment.

Payment. The working rate specified in the Schedule of Items shall be paid for all hours of actual operation of equipment on authorized work. Only quantities approved by the CO shall be accepted under this contract. The accepted quantities will be paid at the contract price per unit of measurement for the Rental Equipment pay item listed in the schedule of items. Payment will be full compensation for the work done and accepted. Adjustment of contract prices as described in FAR 52.211-18 Variation in Estimated Quantities shall not apply to hourly work. The Government reserves the right to reduce or eliminate entirely the work under this item with no adjustment in the contract unit prices.

H-12 Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H-13 Invoice Processing Platform (IPP)

Beginning February 24, 2014, the Forest Service will utilize the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.

Upon award of a contract, Contractors must register at https://www.ipp.gov/vendors/enrollment-vendors.htm. Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.

H-14 Contractor Performance Assessment Reporting System (FEB 2011)

(a) General. This contract is subject to Federal Acquisition Regulations (FAR), Agriculture Acquisition Regulations (AGAR), and Forest Service Acquisition Regulations (FSAR) that require past performance evaluations to be completed and entered into the Contractor Performance Assessment Reporting System (CPARS).

(b) Contact Information. At the Prework Meeting, the name and email address of the Contractor Representative will be required.

(c) Assessment. Upon completion of the work associated with the contract/delivery orders, an evaluation will be initiated by the Contracting Officer in the CPARS system and the Contractor Representative will receive an auto-email from CPARS with instructions for completion of the evaluation.

H-15 Reference FAR 52.236-13, Accident Prevention.

Safety. Contractors shall comply with OSHA regulations and provide employees a work environment that is sanitary and not hazardous, which includes providing personal protective equipment. Contractors must maintain a health and safety plan and an accident prevention program, which includes frequent and regular inspections of the project site, materials, and equipment. Contractors are responsible for risk management regarding contractor/employee and public safety, which include experience of operator to handle road and terrain conditions, getting to the worksite, traffic control, and coordination with other users.

H-16 State of Idaho’s Notice to Offeror Idaho Workers Compensation Law

(a) Prior to award of any contract subject to Idaho Workers' Compensation Laws, the contractor must provide (1) evidence that they have the required workers' compensation coverage or, (2) documentation from the State of Idaho exempting the contractor from such coverage.

(b) Contractors should obtain and complete a State of Idaho Certificate of Verification of Workers' Compensation Insurance as documentation of insurance coverage or exemption. These certificates may be obtained from and returned to the Employee Compliance Division of the Idaho Industrial Commission at the following offices:

North Idaho

Southwest Idaho

1221 Ironwood Street, Suite 100

317 Main Street

Coeur d'Alene, ID 83814

P.O. Box 83720

(208) 769-1565

Boise, ID 83720-0041

Fax No. (208) 769-1465

(208) 334-6032

(800) 950-2110

Fax No. (208) 334-5145

Southeast Idaho

1070 Hiline, Suite 300

Pocatello, ID 83201

(208) 236-6366

Fax No. (208) 236-6040

(c) This certificate of verification shall be fully executed by the contractor and signed by the Industrial Commission Compliance Officer prior to award of the contract.

H-17 Biobased Product Utilization (Reference: I-6, FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts) The Contractor must comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February 2012, to provide biobased products.

The Contractor shall utilize products and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative (COR).

The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.

(*Sample of biobased products for construction projects)

Grease Removers Insulating Foam Concrete and Asphalt Release Fluids

Fluid-filled Transformers Wood and Concrete Sealers Composite Panels

Adhesive and Mastic Removers Carpets Roof Coatings

Hydraulic Fluid Water Tank Coatings

(*Sample of biobased products for building mtce – light construction projects (Operations and Maintenance) Hydraulic Fluids Penetrating Lubricants Concrete and Asphalt Release Fluids

Absorbents Diesel Fuel Additives Greases

Dust Suppressants 2-Cycle Engine Oil Wood and Concrete Sealers

Fertilizers Roof Coatings Water Tank Coatings

Adhesive and Mastic Removers Cleaners Sorbents

Floor Finish Floor Stripper Composite Panels

Insulating Foam Sealers Carpet

Metalworking Fluids Graffiti and Grease Removers Stain Removers

Degreasers De-icers

Biobased products that are designated for preferred procurement under USDA’s Biopreferred Program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material.

In addition to the biobased products designated by the U.S. Department of Agriculture in the Biopreferred Program, the Contractor is encouraged to use other commercially available biobased products.

The Contractor shall submit with the initial proposal a complete list of biobased products, indicating the name of the manufacturer, cost of each material, and the intended use of each of the materials that are to be used in carrying out the requirements of this contract (see Section L, Clause L- 4 - Instructions for the Preparation of Technical and Business Proposals).

Additionally, the winning Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes (see Section I, FAR Clause 52.223-2).

Within thirty (30) days of contract award, the Contractor shall submit an Operation Plan. This submittal will be approved by the COR in writing. The Contractor shall not commence work until this submittal is approved by the COR in writing. The Plan must be reviewed and updated annually, and as required by the COR. The Plan must contain and define the following elements:

· The Contractor’s written policy stating its commitment to the use of biobased products, employee health and safety, and sound environmental management practices.

· Detail on how the Contractor intends to keep abreast of the development and increasing availability of designated and non-designated biobased products and how any new or improved products will be incorporated on an ongoing basis into contract performance.

· Proposed biobased construction products which must be selected in accordance with the criteria included above. At a minimum, the Plan must identify products by brand name for each of the product types.

NOTE: A Contractor may propose more than one product within a product category and/or propose a product or products addressing more than one product category.

· The product guides which define standard operating procedures for instructing staff in the proper use, storage, and disposal of biobased products; proper maintenance of equipment; and other procedures/instructions to accomplish work under this contract.

The Contractor shall provide data on the quantity and dollar values of biobased products used in this contract. The data shall be submitted to the COR quarterly.

A demonstration of proper use, an effective training program, and technical assistance are essential to the success of the purchase and use of some biobased products that may function differently than a conventional product.

H-18

CONTRACTOR WORKFORCE CERTIFICATION

Bonners Ferry Ranger District is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

Upon the request of the Contracting Officer, the Contractor shall submit a written report containing the following elements:

· Contractor Name and Address

· Contract Number

· Date of Report

· Identification of individual Contractor and/or Subcontractor employees, and identification of the city and state in which each individual employee maintains a primary residence.

· The following statement: “I hereby certify this list identifies all Contractor employees and subcontractor employees engaged in performance of this contract, and that the information contained in this report is accurate as of the date of this report.”

Contractor signature and date of signature

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1 Definitions (NOV 2013)

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (May 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government (SEPT 2006) 52.203-7 Anti-Kickback Procedures (May 2014)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)

52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (DEC 2014)

52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records - Negotiation (OCT 2010) 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award (NOV 2011) 52.219-8 Utilization of Small Business Concerns (Oct 2014) 52.219-14 Limitations on Subcontracting (NOV 2011) 52.222-3 Convict Labor (JUNE 2003) 52.222-4 Contract Work Hours and Safety Standards Act--Overtime Compensation (May 2014)

52.222-6 Davis-Bacon Act (May 2014)

52.222-7 Withholding of Funds (May 2014)

52.222-8 Payrolls and Basic Records (May 2014)

52.222-9 Apprentices and Trainees (JULY 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Veterans (JUL 2014)

52.222-36 Affirmative Action for Workers with Disabilities (Jul 2014)

52.222-37 Employment Reports on Veterans (JUL 2014)

52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)

52.222-50 Combating Trafficking in Persons (FEB 2009)

52.222-54 Employment Eligibility Verification (AUG 2013)

52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2014)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts (MAY 2008) 52.223-18…

This is the start of the file's text. The full file is on GovTribe.