Question and Answers along with drawings that may be easier to read. No changes have been made to the initial drawings that were posted.

View the file

Other files

File Type Posted
Amendment1.pdf PDF
AG-02NV-S-16-0056.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 1

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

2 05/27/2016

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

IDAWY Acquisition Service Center 1405 Hollipark Drive Idaho Falls, Idaho 83401

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

Prospective Quoters

AG-02NV-S-16-0056

9B. DATED (SEE ITEM 11)

05/20/2016

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning __ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

The purpose of this amendment is to answer all questions that have been asked and to provide drawings that may be easier to read.

See page 2 of 13 for question and answers.

See page 3 through 13 for drawings that may be easier to read.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

AMELIA RIOS VELASCO, Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

AG-02NV-S-16-0056 Bridget Material

Caribou-Targhee National Forest Service

Q: Will you create a list of sizes and quantities of lumber required for this project - to make certain that all bidders are bidding the same thing?

A: The Plans have a Bill of Materials on the last sheet of the drawings.

Q: Although you have identified 'FOHC' and some sizes, there does not appear to be a grade specified, a specie specified, moisture content specified, or surfacing specified. It appears there are 'Lumber Notes' on the first page of the Drawings - however, the type is so light it is almost impossible to read - and in that it is a PDF document, it is impossible to alter the document.

A: The LUMBER NOTES from the plans. They specify the necessary information.

AG-02NV-S-16-0056

LANES CREEK BRIDGE NO. 50107-0.2

ALL LUMBER SHALL BE COAST REGION DOUGLAS FIR GRADED IN ACCORDANCE WITH THE

WEST COAST LUMBER INSPECTION BUREAU STANDARD GRADING AND DRESSING RULES NO.

17. EACH ITEM SHALL CONFORM TO THE PARAGRAPH NUMBER LISTED IN THE BILL OF

MATERIAL.

ALL LUMBER OVER 2" NOMINAL THICKNESS SHALL BE INCISED ON ALL FOUR SIDES AND ALL

2" NOMINAL LUMBER SHALL BE INCISED ON TWO FACES ONLY. MEMBERS TOO LARGE FOR

MACHINE INCISING SHALL BE MANUALLY INCISED. ALL FABRICATION AND INCISING OF THE

GLUED-LAMINATED MEMBERS, SHALL BE DONE PRIOR TO TREATMENT.

GLUED-LAMINATED MEMBERS SHALL BE COAST REGION DOUGLAS FIR FABRICATED IN

ACCORDANCE WITH SPECIFICATIONS NOTED IN THE BILL OF LUMBER, CURRENT EDITION OF

"STRUCTURAL GLUED-LAMINATED TIMBER" AITC/ANSI A 190.1, CURRENT EDITION OF

AITC117 STANDARD SPECIFICATIONS FOR GLUED-LAMINATED TIMBER FOR SOFTWOOD

SPECIES, THE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS FP-03 SECTION 716.04, AND SHALL BE INDUSTRIAL

APPEARANCE GRADE FOR WET USE CONDITIONS USING PHENOL-RESORCINOL RESIN TYPE OF

ADHESIVE THROUGHOUT, USING ONLY SINGLE PIECE OR MULTIPLE PIECE LAMINATIONS

WITH BONDED EDGE JOINTS ON EXTERIOR SURFACES.

ALL TREATMENT SHALL BE IN ACCORDANCE WITH AASHTO M133 AND SHALL BE PRESSURE

TREATED BY THE EMPTY CELL PROCESS IN ACCORDANCE WITH ALL REQUIREMENTS OF

AWPA U1-08 WITH COPPER NAPTHENATE (CuN) OR PENTACHLOROPHENOL (PCP-A, HEAVY- OIL). THE MINIMUM PRESERVATIVE RETENSIONS (pcf) FOR SOLID SAWN TIMBER AND GLUED-

LAMINATED TIMBER SHALL CONFORM TO AWPA USE CATAGORY UC4B GROUND CONTACT

OR FRESH WATER FOR COASTAL DOUGLAS-FIR.

ALL SAWN LUMBER SUPPLIED FOR THIS BRIDGE, WITH THE EXCEPTION OF TREATED TIMBER

DEADMAN MEMBERS FOR ABUTMENTS AND WINGWALLS, SHALL BE 100% FREE OF HEART

CENTER AND HAVE A MOISTURE CONTENT LESS THAN 19% PRIOR TO TREATMENT, AND

MUST BE CERTIFIED PRIOR TO ANY PAYMENT TO THE CONTRACTOR.

SPECIAL NOTE: ALL MATERIALS SHALL BE PRODUCED IN COMPLIANCE WITH "BEST

MANAGEMENT PRACTICES FOR THE USE OF WOOD IN AQUATIC ENVIRONMENTS", CURRENT

EDITION.