Sample_Erosion_Control_Plan.docx
DOCX document 17 KB Posted
- Attached to
- Sandy Beach Road Bridge Replacement Federal contract opportunity
- Solicitation number
- AG-0116-S-14-0006
About this file
Sample Erosion Control Plan
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_007..pdf | ||
| Amendment_007.pdf | ||
| Amendment_007_continuation_sheet.doc | DOC document | |
| RFI_responses__3_.docx | DOCX document | |
| Amendment_006.pdf | ||
| Amendment_005.pdf | ||
| Amendment_004.pdf | ||
| FSSS_171.pdf | ||
| FSSS_571.03_for_LRFD.docx | DOCX document | |
| RFI_responses__2_.docx | DOCX document | |
| Amendment_003.pdf | ||
| RFI_responses__1.docx | DOCX document | |
| Amendment_002.pdf | ||
| Drawings.pdf | ||
| Solicitation_-AG-0116-S-14-0006_-_FINAL.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Calamity Carroll Road Stabilization Example Erosion Control Plan
Brief Project Description:
This project is designed stabilize existing roads in 2 separate locations, Upper Carroll and Shoal Cove. Upper Carroll experienced numerous landslides along several miles of road during a high rainfall event in 2010. A 70’modular bridge was washed downstream, many culverts were overwhelmed with debris, and several short segments of roads were covered with up to 6’ of logs and displaced soil. Shoal Cove road work involves removing drainage structures on roads to be stored.
General project objectives are to: improve natural hill slope and stream channel hydrology by installation of new road drainage structures; removal of stream crossing fills; construction of cross drains; and reducing existing and potential sedimentation into stream courses by removal of unstable fills and re-vegetation of disturbed soils. More specific objectives are the following:
· Remove drainage structures damaged or plugged with debris.
· Remove drainage structures on isolated roads not needed in the near future.
· Restore stream beds and banks to natural conditions on stored roads.
· Remove landslide material from roads and ditches, placing all material in a stable location.
· Restore drainage patterns by installing new culverts.
· Minimize cut slope disturbance (excavations).
· Avoid placement of materials in unstable areas (wet, swales, headwalls).
· Recover the displaced modular bridge from the stream.
· Establish cross drains to move ditch flow across the roadway prior to reaching streams.
Erosion Control Measures Temporary:
1. Seed and fertilize all disturbed areas within 14 days of completion of construction activities at the site.
2. Install temporary check dams and sediment fences as necessary to minimize the entry of silt-laden water into streams or other water bodies.
Permanent:
1. Space cross ditches to minimize erosion
2. Armor all cross drain outlets with large (12”+ size) rock obtained from the excavated road prism.
3. Armor with rock the entire length and width of the 108” culvert removal site on road 8444000.
4. Dispose of excess material (spoils) so it does not enter stream channels or other water bodies. Place excess material a minimum of 20’ for stream channels.
5.
Specific Sites of Concern: (large fills, stream-adjacent slopes, unstable soils):
Landslide areas at Upper Carroll Inlet on road 8448000 and road 8444000 at Shoal Cove.
Scheduling (includes timing, item/provision, and contract specifications/reference):
Contract Construction
| Site |
| Item/Provision |
| Timing |
| Specification |
| Entire project |
| Seed and fertilize |
| 14 days after completion of each site of disturbed soils |
| 625(02) |
| Entire project |
| Clearing: do not place removed brush in streams |
| During operations |
| 201(03) |
| Entire project |
| Culvert installation, removal and ditch cross drain construction |
| During operations |
| 833 |
| Entire project |
| Outlet pipes and cross drains |
| During operations |
| 251(01)a |
| Entire project |
| Landscape preservation |
| During operations |
| H.2 |
| Stream crossings |
| Number of crossings |
| During operations |
| H.10 |
| Entire Project |
| Endhaul disposal sites |
| During operations |
| C.1 |
| Fish bearing streams |
| Instream activities |
| Fish window |
| H.10 |
Contractor: Date:
Contracting Officers Representative: Date:
File details come from the government source that posted it. Updated .