Q_and_A_APR_26.pdf

PDF 38 KB Posted

Attached to
Yakutat Employee Housing Design-Build
Solicitation number
AG-0116-S-13-0003
Issued by

About this file

This document provides two questions and answers for the benefit of prospective Phase One offerors.

View the file

Other files

File Type Posted
Dates_for_PreProposal_meeting_and_responses.docx DOCX document
Phase_Two_Contractors.docx DOCX document
0003_QA_2013_04_11.pdf PDF
AG-0116-S-13-0003_Phase_One_Solicitation.pdf PDF
Atch_1_Specifications.pdf PDF
Atch_3_Wastewater_Design_Document.pdf PDF
Atch_2_Site_Utilities.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-0116-S-13-0003

Yakutat Employee Housing Design-Build Questions and Answers

April 26, 2013

The following questions and answers are provided for the benefit of all prospective Phase One offerors—

Q.1. Is the approximate location of the houses identified on the Site Plans in Attachment 2 of the solicitation where the Government desires the placement of the new constructed homes?

A.1. Yes, those are the house sites. Those plans were completed several years ago, but the placement hasn’t changed.

Q.2. Are pages 3 [Demolition & Existing Conditions] and 4 [Site Plan] of Attachment 2 available in electronic format (CAD, DWG, et cetera)?

A.2. Yes, they are available in drawing (.dwg) format. The Government will consider released them as part of the Phase Two solicitation.