Addendum One .pdf
PDF 90 KB Posted
- Attached to
- RFB-66-24 HVAC Replacement WKCC
- Solicitation number
- RFB 785 2400000114 5
- Issued by
- Leslie County, Kentucky
About this file
This addendum to Invitation to Bid No. RFB-66-24 is issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for HVAC replacement operations at the West Kentucky Correctional Complex in Lyon County, Kentucky. The project involves specified modifications to the original bid documents, including updates to manufacturer specifications, omission of certain control system requirements, and operational constraints specific to the correctional facility environment. The addendum, dated October 4, 2023, becomes binding upon the contract issued in response to the invitation to bid.
The addendum establishes critical operational requirements for contractor personnel and activities at the correctional complex. Personnel must complete background checks and minimum three-hour site orientation and PREA training before facility access, and employees will be searched upon each entry and exit. Contractor vehicles are prohibited within the compound, though pre-approved equipment such as lifts, forklifts, cranes, and trailers may be used with daily movement by the owner. Work is restricted to daylight hours between sunrise and sunset, and all tools, materials, and debris must be removed daily with nothing remaining overnight. Contractors must furnish portable toilet and handwashing facilities, provide temporary heat units for occupied areas, wear distinguishing company-identified clothing (avoiding tan or orange), and are prohibited from bringing cellphones into the facility. Additionally, the contractor must supply all trash and waste removal facilities independent of the owner's dumpsters, and training documentation must be videotaped using professional equipment rather than personal devices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-66-24
FOR: HVAC Replacement Operations Building West Kentucky Correctional Complex Department of Corrections Lyon County, Kentucky
DATE: October 5, 2023
RFB-785-2400000114
ADDENDUM NO. One (1)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-66-24 For: HVAC Replacement Operations Building West Kentucky Correctional Complex Department of Corrections Lyon County, Kentucky
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
OPERATIONS BUILDING HVAC
WEST KENTUCKY CORRECTIONAL COMPLEX
FREDONIA, KENTUCKY
ACCT. NO. 527-CA4V-WK17-00
MARCUM NO. 21646
ADDENDUM 1.00
OCTOBER 4, 2023
The following Addendum Items shall be made part of the Contract Documents for the referenced project.
1.01 Refer to Section 10000 Special Conditions, Article 4, 2). The Contractor shall include a minimum of three (3) hours per employee for site orientation and PREA training. Personnel shall not be allowed to enter the compound until after background checks have been approved and trainings are completed.
1.02 Refer to Section 10000 Special Conditions, Article 4, 3). Contractor vehicles shall not be allowed within the compound. Equipment that will be allowed in the compound shall be approved in advance by the Warden and shall include, but not be limited to: Equipment lifts, fork-lifts, cranes, lulls, and trailers
(open/enclosed). The Owner will move trailers with tools into and out of the compound daily.
1.03 Refer to Section 10000 Special Conditions, Article 4, 4). No cellphones shall be allowed in the compound. Special circumstances shall be considered, and final approval shall be by the Warden.
1.04 Refer to Section 10000 Special Conditions, Article 4, 11). The Owner shall take pictures for the Contractor for Daily Field Reports.
1.05 Refer to Section 10000 Special Conditions, Article 4, 14). The Owner recommends the Contractor utilize an enclosed trailer with “Shadow Board” for inventory of tools to expedite daily inventory. No tools shall remain in the compound overnight.
1.06 Refer to Section 10000 Special Conditions, Article 4, 16). The Warden shall require the Contractor’s personnel to attend a site orientation and training session for all workers.
1.07 Refer to Section 10000 Special Conditions, Article 4, 17). Contractor personnel shall be searched each time they enter and leave the facility.
1.08 Refer to Section 10000 Special Conditions, Article 4, 18). Contractors shall wear distinguishing clothing. It is not recommended to wear tan or orange. It is recommended to wear clothing with company logo’s that are visible or to wear hi-vis yellow vests or shirts.
1.09 Refer to Section 10000 Special Conditions, Article 4, 19). All tools, trash, unused materials, scraps, etc. shall be removed from inside the compound daily.
Nothing shall be left inside the compound overnight.
1.10 Refer to Section 10000 Special Conditions, Article 4, Worktimes. Contractors shall not be allowed on the compound before sunrise or after sunset.
1.11 Refer to Section 10000 Special Conditions, Article 4. The following areas shall remain fully operational during the
1.12 Refer to Section 10000 Special Conditions, Article 6, Portable Toilet Facilities.
The Contractor shall furnish portable toilet facilities and handwashing facilities within the compound for personnel use. The Contractor shall coordinate location with Owner.
1.13 Refer to Section 10000 Special Conditions, Article 6. The Contractor shall be responsible for furnishing all trash/waste facilities. Use of Owner’s dumpsters is not acceptable for removal of construction debris/materials.
1.14 Refer to Section 10000 Special Conditions, Article 6. The Contractor shall provide temporary heat units for occupied areas during construction.
1.15 Refer to Section 230900. Update the Manufacturers List to include “Distech”.
Final approval will be reserved for the Shop Drawing review stage.
1.16 Refer to Section 230900. 1.1.B.4. Omit this item in its entirety. The Owner will not be furnishing JACE’s for this project.
1.17 Refer to Section 230900. 1.7.J and 230900. 1.7.K. Omit these items in their entirety. The Temperature Controls Contractor is not required to use Niagara AX
Framework for this project.
1.18 Refer to Section 230900. 2.11. Omit this Item in its entirety. The Temperature
Controls Contractor is not required to furnish Variable Frequency Drives for this project.
1.19 Refer to Section 230900.3.7.A. Training shall occur at the Correctional Complex.
The Contractor shall be responsible for videoing the training. Use of cell phones, tablets, etc. are not acceptable for recording the training.
1.20 Refer to Drawing H5.1 – Hydronic Pump Schedule and Section 232123. Update the Manufacturers List to include “Grundfos”. Final approval will be reserved for the Shop Drawing review stage.
Attachments:
1. None
END OF ADDENDUM 1.00