Addendum No. 4.pdf

PDF 103 KB Posted

Attached to
RFB-235-25 KRA Locks 2 & 3 Guide Wall Repairs Project
Solicitation number
RFB-785-2500000645-8
Issued by
Harrison County, Kentucky

About this file

This is Addendum No. 4 for Invitation to Bid No. RFB-235-25, issued by the Commonwealth of Kentucky's Department for Facilities and Support Services, Division of Engineering and Contract Administration, for the Upper Guide Wall Repairs Project at Kentucky River Locks 2 & 3 in Henry County, Kentucky. The addendum modifies two key aspects of the original bid: first, the bid due date is extended to July 30, 2025 at 1:30 PM ET, and second, the project schedule is extended by one year. The project will now have separate construction seasons for each lock, with Lock 3 having a substantial completion date of November 30, 2026 (construction season from July 1, 2026 through November 30, 2026) and Lock 2 having a substantial completion date of November 30, 2027 (construction season from July 1, 2027 through November 30, 2027).

The addendum indicates that all other information from the original invitation to bid remains unchanged. The project is associated with the Kentucky River Authority and involves repairs to the upper guide walls at two separate lock locations. The extended timeline suggests the intent is to allow one construction season per site, potentially to manage logistics, resources, or environmental considerations specific to each lock's location.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-235-25

FOR: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky

DATE: May 28, 2025

RFB-785-2500000645

ADDENDUM NO. Four (4)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Change Bid Due date to July 30, 2025 at 1:30 PM ET. All other information remains the same.

Item 2: The project schedule for the KY River Locks 2 and 3 Upper Guide Wall Project will be extended one (1) year. The revised Substantial Completion dates and updated construction seasons are listed below. The intent is to allow one construction season per site.

Substantial Completion for Lock 3 – November 30, 2026 Construction Season July 1, 2026, through November 30, 2026

Substantial Completion for Lock 2 – November 30, 2027 Construction Season July 1, 2027, through November 30, 2027

END OF ADDENDUM

Invitation to Bid No. RFB-235-25 For: Upper Guide Wall Repairs Project Kentucky River Locks 2 & 3 Kentucky River Authority Henry County, Kentucky

Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration

Item 2: The project schedule for the KY River Locks 2 and 3 Upper Guide Wall Project will be extended one (1) year. The revised Substantial Completion dates and updated construction seasons are listed below. The intent is to allow one construction sea...
END OF ADDENDUM