About this file
This addendum provides additional specifications for bid item 12 under solicitation number 140L2623R0005 for Wilson Lake site improvements. The solicitation is for a construction project by the Bureau of Land Management Idaho Region.
Bid item 12 covers transporting and installing a single vault toilet at the location indicated in the plans. The item includes all materials, equipment, and labor needed for transport and installation according to manufacturer guidelines and government direction. It will be paid as a lump sum. The addendum also explains that the base bid covers all roads, campsites and vault toilets as shown in the drawings, while four additives include additional restrooms, signs, shade shelters and transporting and installing an east vault toilet with associated features.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B11_Wilson_Prebid_0001.pdf | ||
| Fire_rings_0001.pdf | ||
| Sol_140L2623R0005_Amd_0001.pdf | ||
| Wilson_Lake_Drawings.pdf | ||
| SF-24_Bid_Bond.pdf | ||
| Sol_140L2623R0005.pdf | ||
| Wilson_Lake_Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM
Add the following to Specification 012200:
A. BID ITEM 12 – Transporting and Setting Vault Toilet: Item includes transporting and installation of the Single Vault toilet in the location indicated on the plans. Item includes all materials, equipment, and labor necessary for transport and installation. Installation shall be per manufacturer guidelines and as directed by the Government. Item will be paid for as a lump sum.
Explanation of work:
BASE: Includes labor, equipment, and material necessary to complete the work associated with all roads, campsites, vault toilet locations shown on the Drawings. Pay items associated with the base includes Bid Items 1, 2, 3, 4, 5, and 10.
ADDITIVE 1: Includes labor, equipment, and material necessary is to complete the work associated with the west restroom items, including the vault restroom, concrete sidewalk, and concrete parking pad. Pay items associated with this additive includes Bid Items 6, 7, and 8.
ADDITIVE 2: Includes labor, equipment, and material necessary to complete the work associated with all signs, kiosk, and concrete pad. Pay items associated with this additive includes Bid Items 6, 7, and 11.
ADDITIVE 3: Includes labor, equipment, and material necessary to complete the work associated with the purchasing and installation of shade shelters, concrete pads associated with the shade shelters, and concrete parking pad. Pay items associated with this additive includes Bid Items 6, 7, and 9.
ADDITIVE 4: Includes labor, equipment, and material necessary to complete the work for the transportation and installation of the east vault restroom (located at Shoshone BLM 213 W F Street Shoshone, Idaho), concrete sidewalk, and concrete parking pad. Pay items associated with this additive includes Bid Items 6, 7, and 12.
A. BID ITEM 12 – Transporting and Setting Vault Toilet: Item includes transporting and installation of the Single Vault toilet in the location indicated on the plans. Item includes all materials, equipment, and labor necessary for transport and instal...
File details come from the government source that posted it. Updated .