Addendum 2 26405.pdf

PDF 131 KB Posted

Attached to
751/26405. JGH; Lake Orion BAS - Site Improvements
Solicitation number
RFP 171 260000002453 3
Issued by
Michigan

About this file

This is Addendum No. 2 to a Request for Proposal issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration Design and Construction Division for the Lake Orion Boating Access Site Improvements project. The addendum addresses clarifications regarding project scope and specifications for the site improvements. Key clarifications include confirmation that the attendant booth and restroom structures may be premanufactured, with the State having previously prepared plans for premanufactured restroom units available for proposers to use. The project will not include electrical or sink facilities in the new restrooms, which will replace existing pit toilets, and no utilities are planned for the attendant booth or vault toilet replacements. Pavement replacement at the right-of-way should be consistent with existing design documents from Addendum 01. The proposal due date is 8/27/26, with the addendum issued on 8/20/26 and approved by Project Director Jared Gavin-Helfrich.

Regarding survey and geotechnical requirements, proposers should assume responsibility for providing any additional geotechnical information and survey work needed for ADA compliance grade confirmation of the parking lot and vault toilet access, though an allowance may be included for this work. All existing design documentation has been provided to prospective bidders. State forces are available for survey assistance if needed but are not the preferred option. The addendum does not contain pricing information, set-asides, funding sources, or other financial terms in this document.

View the file

Other files

File Type Posted
10-SOIL DETAILS.PDF PDF
08-LANDSCAPING (1).pdf PDF
04A-GRADING DET (1).pdf PDF
04-PAV-GRADE (1).pdf PDF
DTMB-0441 (R 19.02).pdf PDF
DTMB-0430 RFP Billable Rate 751-26405-JGH.pdf PDF
05-SECTIONS (1).pdf PDF
06-DETAILS (1).pdf PDF
09-SOIL EROSION (1).pdf PDF
Addendum 1 26405.pdf PDF
03-REMOVAL (1).pdf PDF
DTMB-0427 Project Statement 751-26405-JGH.pdf PDF
01_COVER Model (1).pdf PDF
SAMPLE Billable Rate Contract (Rev 04-25).pdf PDF
07-GEOMETRIC (1).pdf PDF
02-TOPO (1).pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 2/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 02

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.

Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

8/20/26

PROJECT NAME

Lake Orion Boating Access Site Improvements

FILE NUMBER

751/26405.JGH

PROJECT DIRECTOR

Jared Gavin-Helfrich

PROPOSAL DUE DATE:

8/27/26

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

Question: Can the attendant booth be premanufactured? Yes, this can be a premanufactured structure.

Question: Could the restroom structure be pre-manufactured? The State has previously prepared plans for premanufactured units, these would be acceptable and can be made available for use by proposing firms.

Question: The current restrooms are just a pit toilet, is there a need for electricity or a sink in the new restrooms? There is no intent to add electrical or sink facilities.

Question: Can you confirm the extent of pavement replacement along the drive off Indianwood Rd? Should proposed work include approach pavement replacement within the ROW? The paving replacement at the ROW should be consistent with existing design documents issued in addendum 01.

Question: Can you confirm that there will be no utilities required for the attendant booth or vault toilet replacements? This is correct, no utilities are planned at this area.

Question: Were geotechnical borings and reports provided as part of the previous 2010 work and if so, can those be made available to prospective bidders? All existing design documentation has been provided; any additional geotechnical information should be added within the proposal.

Question: Can we assume DNR surveyors will be available as needed for grade confirmation of ADA compliance for the parking lot and vault toilet access? Please provide an allowance for any additional survey information needed. State forces are available if needed but not preferred.

APPROVED BY:

PROJECT DIRECTOR Jared Gavin-Helfrich DATE 8/20/26 http://www.buy4michigan.com/

File details come from the government source that posted it. Updated .