About this file

This is Addendum No. 2 for the John Chavis Memorial Park – Phase 2 Aquatic Center project located in Raleigh, North Carolina, issued by the project management team on September 22, 2026. The addendum modifies the original bidding documents dated August 31, 2026, and comprises 450 pages of revisions and clarifications. Acknowledgement of receipt of this addendum on the bid form is mandatory, and failure to do so may result in bidder disqualification. The addendum includes responses to 18 Requests for Information (RFIs) addressing design clarifications including siphonic design, lighting fixtures, transformer specifications, EV charger installation, photovoltaic roofing details, and building pad elevation. Additionally, the addendum contains revisions to three bid packages with strikethrough removals, clarifications regarding EV charger scope, and correction of alternate bid numbers.

The addendum references CMAR (Construction Manager at Risk) files and design team files available through a shared link, including an Evoke Addendum 1 coversheet published concurrently with this addendum. The RFI responses and design team files are provided to ensure all bidders thoroughly review the complete 450-page addendum prior to bid submission. No pricing terms, set-asides, funding amounts, or contract award dates are specified within this addendum document itself.

View the file

Other files

File Type Posted
Addendum 3 - Chavis.pdf PDF
ADDENDUM 1_17SEP2026_EVP (1).pdf PDF
Chavis Advertisement for Bids 1 (CMAR).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PO Box 7948, 800 Tiffany BLVD, Suite 200 Rocky Mount, NC 27804 919-781-7210 Fax 919-781-5348

JOHN CHAVIS MEMORIAL PARK- PHASE 2; AQUATIC CENTER

RALEIGH, NORTH CAROLINA

ADDENDUM NO. 2

September 22, 2026

To: ALL BIDDERS OF RECORD

This addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated August 31, 2026. Acknowledgement of receipt of this Addendum in the space provided on the Bid Form is mandatory. Failure to do so may subject the Bidder to disqualification. This addendum contains Four Hundred Fifty (450) pages. All bidders need to make sure that this entire addendum is thoroughly reviewed.

CMAR ADDENDUM FILES https://barnhill.egnyte.com/dl/rQkDhxC6bP4F

RFI No. Description RFI PB-001 Clarification of Work on M100 (Design Team Answer Omitted in Previous Addendum) RFI PB-005 Siphonic Design Questions RFI PB-006 Skateboard Deterrent Attachement on Seatwall RFI PB-011 Brick Types on Exterior Elevations RFI PB-016 Exterior Panel and Transformer RFI PB-017 Lighting Fixture Clarification RFI PB-018 Transformer BC-X-P1 and Panel BC-2-P1 NEMA Rating RFI PB-021 Cabinet Lighting RFI PB-023 Drywall Ceiling Access Panel Above Security Doors RFI PB-024 Men’s Locker Room SF12C Light Fixtures RFI PB-025 Security Door Ceiling Access Panel RFI PB-026 Garden/Paver Roof Area XPS Substitution Request RFI PB-030 EV Charger Installation RFI PB-031 R-Value for Project RFI PB-032 Photovoltaic Roofing Details RFI PB-035 Light Pole Water Line Deconfliction RFI PB-051 Building Pad Elevation

Bid Package No. Description BP0740 Strikethrough of reference to BP0750 Strikethrough Removed BP2600 Added Clarification of EV Charger Scope BP3300 Alternate #24 Corrected to Alternate #19

DESIGN TEAM FILES

1. See Evoke Addendum 1 Coversheet regarding details of Evoke Addendum 1 published with CMAR

Addendum 2 (see link below)

a. https://barnhill.egnyte.com/dl/rQkDhxC6bP4F

END OF ADDENDUM NO.2

https://barnhill.egnyte.com/dl/rQkDhxC6bP4F https://barnhill.egnyte.com/dl/rQkDhxC6bP4F https://barnhill.egnyte.com/dl/rQkDhxC6bP4F

Chavis CMAR ADDENDUM 2 Coversheet
Request For Information (RFI) Responses Received to Date