Actiflo_ATS_Breaker_and_Controller_Replacement_and_12KV_Breaker_Replacement_&_Testing.pdf

PDF 315 KB Posted

Attached to
Actiflo ATS Breaker and Controller Replacement and 12KV Breaker Replacement & Testing State and local contract opportunity
Solicitation number
25-096-ITB
Issued by
Yolo County, California

About this file

This is an Invitation to Bid (ITB #25-096) issued by the City of West Sacramento for electrical equipment replacement and testing services at its water treatment facility. The project scope encompasses two primary components: replacement of an Actiflo Automatic Transfer Switch (ATS) controller and breaker system, and replacement and testing of a 12KV vacuum circuit breaker. Specific equipment to be installed includes an Eaton ATC-900 controller with upgrade kit, a new power monitor, and a 3-phase 2500-amp breaker (Eaton SPB-100M), along with a Toshiba HVK 1500V/1200 Amp vacuum circuit breaker. The contractor is responsible for providing miscellaneous materials, labor, and performing all installation, testing, and coordination activities. A non-mandatory site walk is scheduled for November 19, 2025, at 10:00 am at 400 North Harbor Boulevard. Questions from bidders must be submitted by December 5, 2025, at 5:00 pm, with responses provided by December 12, 2025. Sealed bids must be submitted electronically through the City's OpenGov e-Procurement portal no later than December 19, 2025, at 2:00 pm. The contractor selection date is December 22, 2025. All bids must remain valid for ninety (90) business days after the proposal due date. The estimated project completion time is thirty (30) calendar days from the Notice to Proceed.

Bidders must submit pricing for two line items as lump-sum amounts: Actiflo ATS Breaker and Controller Replacement and 12KV Breaker Replacement and Testing, with the total project estimated at approximately $30,000. A 10% bid security (bid bond) is required. The project is subject to California prevailing wage requirements, and contractors must be registered with the California Department of Industrial Relations and possess a current C-10 Contractor's License. No explicit set-asides or disadvantaged enterprise restrictions are noted in the procurement. Insurance requirements are substantial, mandating $1,000,000 per occurrence for Commercial General Liability, $1,000,000 per accident for Commercial Automobile Liability, and statutory Workers' Compensation coverage, with the City named as additional insured and thirty days' notice required prior to policy cancellation. Payment will be processed through progress estimates with 95% paid within thirty days and 5% retained until final project completion and acceptance. The City reserves the right to reject any or all bids and will award to the lowest responsive and responsible bidder meeting all requirements.

View the file

Other files for this state and local contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID

25-096-ITB

ACTIFLO ATS BREAKER AND CONTROLLER REPLACEMENT AND

12KV BREAKER REPLACEMENT & TESTING

City of West Sacramento

1110 W Capitol Ave

West Sacramento, CA 95691

RELEASE DATE: November 14, 2025

DEADLINE FOR QUESTIONS: December 5, 2025

RESPONSE DEADLINE: December 19, 2025, 2:00 pm

RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:

https://procurement.opengov.com/portal/cityofwestsacramento https://procurement.opengov.com/portal/%7bproject.government.code%7d

City of West Sacramento

INVITATION TO BID

Actiflo ATS Breaker and Controller Replacement and 12KV Breaker

Replacement & Testing

I. Introduction II. Project Details

III. Terms and Conditions IV. Bid Submittal V. Cost Table

VI. Contract Award

Attachments:

A - Construction Bid Packet Actiflo ATS Breaker & Controller Replacement and

12KV Breaker Replacement & Testing

B - Insurance Checklist

Invitation to Bid #25-096-ITB Title: Actiflo ATS Breaker and Controller Replacement and 12KV Breaker Replacement & Testing

1. Introduction

1.1. Summary

The City of West Sacramento is accepting sealed responses for Actiflo ATS Breaker and Controller

Replacement and 12KV Breaker Replacement & Testing to be received no later than Friday, December

19, 2025 at 2:00 pm.

The bid specifications, including instructions on how to bid, standards for a responsive bid, and project specifications, are attached hereto in Attachments and incorporated herein by reference as if set forth in full

1.2. Background

West Sacramento is a vibrant riverfront community centrally located in Northern California. West

Sacramento shares the Sacramento River with neighboring Sacramento, with the deep water ship canal serving the Port of Sacramento. Incorporated in 1987, West Sacramento encompasses approximately 22 square miles, with a population just over 55,000. West Sacramento has a Council/Manager form of government. Citizens elect four City Council Members by district (as of the November, 2022 election) who serve four year terms and directly elect the mayor who serves a four-year term. The City is full-service with nine (9) departments and nearly 500 full-time employees. The City provides the full range of municipal services including police and fire protection, park, street, fleet, and facility maintenance, economic development and housing, community development, capital projects, and parks and recreation. The City also provides water, wastewater, and solid waste services. In addition, the City maintains port, water, wastewater, and solid waste enterprise funds. Other activities and related entities include the West Sacramento Redevelopment Successor Agency, Reclamation District 900 and the West Sacramento Area Flood Control Agency.

1.3. Contact Information

Lorianne Landsaw

Senior Analyst

1110 West Capitol Avenue

West Sacramento, CA 95691

Email: loriannel@cityofwestsacramento.org

Phone: (916) 617-4579

Department:

Public Works Operations and Maintenance

1.4. Timeline

Release Project Date November 14, 2025 https://secure.procurenow.com/portal/cityofwestsacramento/projects/206560/document?section=undefined mailto:loriannel@cityofwestsacramento.org tel:(916)617-4579

Site Walk (Non-Mandatory) November 19, 2025, 10:00am

400 North Harbor Boulevard (Water Treatment

Plant)

West Sacramento CA 95605

Question Submission Deadline December 5, 2025, 5:00pm

Question Response Deadline December 12, 2025, 5:00pm

Proposal Submission Deadline December 19, 2025, 2:00pm

Microsoft Teams Meeting https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00Yz

MzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?c ontext=%7b%22Tid%22%3a%22284d74b9-2287-

48dd-86fa-

55c87b82bc40%22%2c%22Oid%22%3a%22c68793 a2-b930-4b69-ba73-6949deb7dff8%22%7d

Meeting ID: 241 373 307 691 06

Passcode: Rk3qo6zD

Dial in by phone

+1 619-485-0116,,570954541# United States, All locations

Find a local number

Phone conference ID: 570 954 541#

Contractor Selection Date December 22, 2025 https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmUyOGVkZTYtNDVhNS00YzMzLTlmNTYtZTcwYTBiNTE4NGQy%40thread.v2/0?context=%7b%22Tid%22%3a%22284d74b9-2287-48dd-86fa-55c87b82bc40%22%2c%22Oid%22%3a%22c68793a2-b930-4b69-ba73-6949deb7dff8%22%7d

2. Project Details

2.1. Important Instructions for Electronic Submittal

The City of West Sacramento is only accepting electronic bid submissions and only through its online bidding platform, OpenGov. Bidders shall create a FREE account by signing up at OpenGov.com. Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid.

The bid specifications, including instructions on how to bid, standards for a responsive bid, and project specifications, are attached hereto in Attachments and incorporated herein by reference as if set forth in full

2.2. Project Scope

12KV Breaker Replacement & Testing

City will be providing new vacuum circuit breaker – Toshiba HVK 1500V / 1200 Amp

Contractor is responsible for any miscellaneous materials to complete the job

City will coordinate with contractor and PG&E for power shutdown

Removal of old vacuum breaker (IEM VK-10M 25)

Insall new vacuum breaker (Toshiba HVK 1500V / 1200 Amp)

City will retain the old breaker (IEM VK-10M 25)

Adjust trip settings based on recent arc flash coordination study recommendations

Perform primary injection testing on new breaker

Re-energize and test as required

“Actiflo” Automatic Transfer switch Controller and Breaker Replacement

City will be providing new ATS controller Eaton ATC-900 with upgrade kit

City will be providing new Power monitor (Model Number)

City will be providing new 3 phase 2500amp breaker (Eaton SPB-100M)

Contractor is responsible for any miscellaneous materials to complete the job

Remove old Automatic Transfer Switch controller (Eaton ATC-600)

Install new upgraded Automatic Transfer switch controller (Eaton ATC-900 with upgrade kit)

Remove and install new power monitor (Model Number)

Remove old 3 phase 2500amp breaker (Eaton SPB-100M)

Install new 3 phase 2500amp breaker (Eaton SPB-100M) https://secure.procurenow.com/portal/cityofwestsacramento/projects/206560/document?section=undefined

Program and adjust trip settings based on recent arc flash coordination study recommendations

Perform testing as required

3. Terms and Conditions

3.1. Prevailing Wages

A. Contractor Registration. Pursuant to Labor Code section 1725.5, no contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations (DIR) pursuant to Labor Code section 1725.5. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the DIR pursuant to Labor Code section 1725.5. The work contemplated by this

ITB is subject to compliance monitoring and enforcement by the DIR.

B. Prevailing Wages. Proposers are hereby notified that the DIR has determined the general prevailing rate of wages for each craft, classification, or type of worker needed to execute the work. Copies of the current schedules for California prevailing wages are located in the City’s office, and the contents of those schedules are included herein as if set forth in full. Licensure and Special Certification.

3.2. Statement of Offer

Submission of a proposal is an offer to complete the Scope of Work. The offer, including the Cost

Proposal rates and budget, must remain valid for at least ninety (90) business days after the Proposal due date.

3.3. Questions and/or Objections

It is to the City and Proposer's benefit that questions and objections are brought to the City's attention so it may issue necessary amendments to the ITB and help prevent the opening of defective proposals upon which the City could not award a Contract. Proposer should carefully review this ITB and all attachments for comments, questions, defects, objections, or any other matter requiring clarification or correction (collectively, “Questions”).

A Proposer may submit Questions related to this RFP to the City through the City’s e-Procurement Portal at or before:

Friday, December 5, 2025 at 5:00 pm.

Questions shall be considered waived and invalid if not brought to the attention of the City in conformity with this subsection. Questions not submitted through the City's e-Procurement Portal will not be accepted or responded to. Questions submitted after the deadline will not be accepted or responded to. Questions and answers will be posted on the City's e-Procurement Portal and visible to all.

3.4. Amendment and Cancellation

The City reserves the right to amend, cancel, or reissue this bid at any time and at its sole discretion. Any amendment shall be in writing and posted to the City's e-Procurement portal. A potential Proposer is solely responsible for clicking "Follow" on the main page to receive notifications and shall be solely responsible for complying with such notifications.

https://secure.procurenow.com/portal/CityofWestSacramento

3.5. Right of Rejection

A. The City reserves the right, at its sole discretion, to reject any and all Proposals, no matter their level of responsiveness, or to cancel this ITB in its entirety.

B. A Proposer must comply with all of the terms and instruction of this ITB, and all applicable state and local laws and regulations. Any Proposal that does not meet the requirements of this ITB may be considered to be nonresponsive and rejected.

C. A Proposer may not restrict the rights of the City or otherwise qualify a Proposal. If a Proposer does so, the City may determine the Proposal is a nonresponsive counteroffer, and the Proposal may be rejected.

D. The City reserves the right, at its sole discretion, to waive variances in a Proposal, provided such action is in the best interest of the City. Where the City waives variances in a Proposal, such waiver does not modify the ITB requirements or excuse the Proposer from full compliance with the ITB. Notwithstanding any variance, the City may hold any Proposer to strict compliance with the ITB.

3.6. Prohibition of Respondent Terms and Conditions

A Proposer shall not submit their own contract terms and conditions in a Proposal. If a Proposal contains such terms and conditions, the City, at its sole discretion, may reject the Proposal. A Proposer may either submit Questions to gain clarification on a term of the City's standard contract or submit proposed revisions to the City's standard contract in redline as part of the Proposal Transmission Letter, both pursuant to the terms of this ITB.

3.7. Joint Ventures and Partnering

A Proposal from joint ventures or entities partnering for a specific service must be designed to minimize any administrative burden on the City as a result of the participation of multiple entities. Joint proposals must adhere to the following:

A. The Proposal shall respond to each section and subsection of this ITB.

B. The Proposal shall clearly set forth the respective responsibilities and functions that each

Principal of the joint venture or partnering entities would perform if awarded a Contract pursuant to this ITB.

C. The Proposal must include a copy of the joint venture or partnering agreement(s) that identify the Principals involved, as well as their rights and responsibilities regarding the Contract pursuant to this ITB.

D. The Proposal Transmittal Letter must be signed by each Principal of the joint venture and include all required information.

3.8. Proposal of Alternate Services

A Proposal for alternate services (i.e., proposals that offer something different from that requested by the ITB) will be considered nonresponsive and rejected.

3.9. Proposal of Additional Services

A Proposal may indicate and offer services in addition to those required by this ITB. These additional services may be added to the Contract, at the sole discretion of the City. The cost for any such additional services shall be mutually agreed upon by the Contractor and the City, and incorporated into the

Contract before execution.

3.10. Severability

If any provision of this ITB is declared by a court to be illegal or in conflict with any law, the validity of the remaining terms and provisions shall not be affected, and the rights and obligations of the City and

Proposers shall be construed and enforced as if the ITB did not contain the particular provision held to be invalid.

3.11. Licensure and Special Certification

Before executing the Contract pursuant to this ITB, the Contractor must hold all necessary business and professional licenses and certifications to complete the Scope of Work. The City may require any or all

Proposers to submit evidence of proper licensure and certifications.

3.12. Disclosure of Proposal Contents

All Proposals and other materials submitted to the City related to this ITB shall become the property of the City. Selection or rejection of a Proposal does not affect this right. All proposal information, including detailed price and cost information, shall be held in confidence during the evaluation and selection process. Upon the completion of the evaluation and selection process, or by rejection of all Proposals, the Proposals and shall be open for review by the public to the extent required by the California Public

Records Act, Government Code section 6254 et seq.. By submitting a Proposal, a Proposer acknowledges and accepts that the contents of the Proposal and associated documents shall become open to public inspection.

Portions of a Proposal exempt from public disclosure by law may be protected from public disclosure by the City. A Proposer is required to clearly label such portion of a Proposal "CONFIDENTIAL" and list the grounds for non-disclosure. In doing so, the Proposer thereby agrees to indemnify and defend the City from any action arising from the non-disclosure of the information. The failure to so label any information shall constitute a complete waiver of all claims for damages caused by or related to any release of the information.

3.13. Conflict of Interest and Restrictions

By submitting a Proposal, the Proposer certifies that no amount shall be paid directly or indirectly to an employee or official of the City as wages, compensation, or gifts in exchange for acting as an officer, agent, employee, subcontractor, or consultant to the Proposer in connection with the procurement under this ITB.

3.14. Proprietary Information

A copy of each Proposal shall be retained for official files and will become public record after the award of a contract unless the Proposal, or specific parts of the Proposal, can be shown to be exempt by law.

Each Proposer may clearly label any part of a Proposal as "CONFIDENTIAL." In doing so, the Proposer thereby agrees to indemnify and defend the City for withholding the information from public inspection.

Failure to label information shall constitute a complete waiver of all claims for damages caused by or related to any release of the information.

If a public records request for appropriately-labeled information is received by the City, the City will endeavor to notify the Proposer of the request and delay access to the material until seven (7) working days after the City’s notice. Within that time delay, it will be the duty of the Proposer to act in protection of its labeled information. Failure to so act shall constitute a complete waiver.

4. Bid Submittal

4.1. Please upload a current 2024 W-9*

Please download the attached 2024 W9 form and upload a completed form.

• W-9_Form_ver._2024_-_BLANK.pdf

*Response required

4.2. Please enter Legal Company Name and related DBA*

Please state your company name and any related DBA's based on your California Secretary of State

Filing.

*Response required

4.3. Response*

Please upload your complete response here including all required forms into one (1) PDF document

*Response required

4.4. Cost Proposal using Electronic Pricing Table*

Cost Proposal using Electronic Pricing Table*

The respondent acknowledges that a Cost Proposal must be completed using the electronic pricing table provided in the City’s e-Procurement Portal and that this information will be kept separate from the rest of the response. The respondent further acknowledges that all pricing and related costs will be based solely on the information entered in the electronic pricing table. The City will not be responsible for any errors, omissions, or discrepancies contained in any additional or supplemental pricing documents submitted by the respondent.

☐ Please confirm

*Response required

4.5. Statement of Offer*

Submission of a proposal is an offer to complete the Scope of Work. The offer, including the Cost

Proposal rates and budget, must remain valid for at least ninety (90) business days after the Proposal due date.

☐ Please confirm

*Response required

4.6. Bid Bond*

Bid contents, including requisite declarations and forms to be signed and included in the Bid, are included in the Attachments - Bid Docs

*Response required https://government-project.s3.us-west-2.amazonaws.com/4013/4713e161-0e9b-428f-be7a-2b0ae306a414_W-9_Form_ver._2024_-_BLANK.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4EEEANR67%2F20251115%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20251115T015445Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEKr%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJGMEQCIC%2F94%2Fa4YJ5pwn6LkrNn37fyuwz452CQqZ9lqyEtUNH%2FAiALw1LZvfX1IFeb0G%2BbKUch%2BaG%2Fumnu7yoIN%2B%2BSe7SmniqFBQhzEAIaDDg5MjM2NDY4NzY3MiIMbZug4gKRtItZx6U9KuIEMByxMRf7zvzgyYl5LpShQzltKXo38fuCoUJMVySNmMGRPGz0dSR78TuvaDbJFWXW9bj6wbOFZpOFYX5RFaMkGHDKddbP32k6RjvGWwzuSd5JTWpSBsAFdWpLcNL47TERbWGAgYtWpmdIKDNoQ8x4%2BmEK%2Bk119CMrnMkZKkjiRzzXOQECG5f0KSQ%2BenEkCWfjX%2B9ZAABhM%2FwSDBcVtrpZavDSohjzauFPq6Ut4AtlHOEQrFCixCNJSEwl0NGyogc7KVg1oDtSJ9kXyW0irbbq1LFPEsMAbFEcFchuftv%2BmQDbmGBktlAo7Dijc9ydaz0wr0ioFhmsL%2F%2F%2BlhYBtycwxQQyTWM1%2Bqy33BjcpQinhYqQHqTer5oB1qWhQbAi5t8zex9%2Fk%2FZ3Fr5PUX4xdxGe4ibMeEWZgE5pf8VkyGerUz4yuyJ6GUxrLyjRx6AXyE%2BNstKIOKWSCaaJ2jIRJdpB5crytQshWehBFSEBtGJ3lpsFxwfmJKeQwiR2fVGx2jyADoHMeMh8Di6zqTR3%2Bng%2FieTb%2BV%2Fd5FO2XHgBxEIbo3MPhEGJqidLSpoGfAf%2BtEfFsCx2qrZrC7p5EbnL25dQO7T5FEWfCnn1a1oY3ASgJKWQ9QcbMEOf0bd5ZxA0mmnL3DRxqlwt5ETw%2FC4tpscq66hfyRtP%2FqmhpL9t%2FIt0ItL%2FNtiLG2eQzU3NOkSrQiBTLcqdJ3ltxhWO4nd8pSAMEvRir3D1CB8Go1dPHUANyiy7MNluiFYI%2BqDqD8TmA6vNUof%2BybfpuMM4e%2F80VqgauMXn1h7wYlTIb0PdedGBpaqXgzDKsN%2FIBjqaAZc8vpFfn2CQVy8fJvJ50XlfK9udZK6Wcq00yCzlrAQkWhd8PCP8WkcHrC8wXcG3cM8oTayaiG0t5oM1aNc835uAWpKNbhAt7reww4GmqRUnmhHhCTtq5qT7mAkuBl%2Fb621Lcp%2F5KDPmOG%2BFraU8JDLDJrFcvoeZ5coWgsM2dw7ObZLs1jv8zDFQWZw214kleuKEbL54yaZTtc8%3D&X-Amz-Signature=ee3b0b88fcf5d1fbae2ebdfa20d31a438a74968051be5d6b9f554de03b7c9eb9&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22W-9_Form_ver._2024_-_BLANK.pdf%22&x-id=GetObject https://secure.procurenow.com/portal/cityofwestsacramento/projects/206560/document?section=1933040

4.7. California Contractors State License Board

Please enter your contractor license number for verification.

4.8. Certification regarding Debarment

The City performs a SAM.GOV verification check to confirm debarment status. Please download the attached document, complete the form, and upload.

A unique entity identifier is requested for contracts greater than $25,000 or funded with Federal dollars.

Your entity may register for a unique entity identifier on SAM.GOV at the following link https://sam.gov/content/entity-registration.

For all other proposers, the completed form is sufficient.

• Certification_Regarding_Deb...

4.9. City Contract *

The Proposer acknowledges and is presumed to have accepted the Contract and be capable of completing the Scope of Work, as well as all reasonably associated managerial tasks, without reservation or qualification pursuant to the Contract.

☐ Yes

☐ No

*Response required

4.10. Insurance Requirements*

The Proposer acknowledges the City's insurance requirements and endorsements as outlined in the

Insurance Checklist in Attachments. Any Proposal unable to meet the Insurance Checklist requirements shall be considered nonresponsive and ineligible for Contract award.

☐ Yes

☐ No

*Response required

4.11. Authorized Contract Signer *

Please provide the name, title and email address of the authorized contract signer.

*Response required https://government-project.s3.us-west-2.amazonaws.com/4013/7fbcd8f3-7d1e-4b79-a50c-03f71fe54e62_Certification_Regarding_Debarment_Form_COWS.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4EEEANR67%2F20251115%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20251115T015445Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEKr%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJGMEQCIC%2F94%2Fa4YJ5pwn6LkrNn37fyuwz452CQqZ9lqyEtUNH%2FAiALw1LZvfX1IFeb0G%2BbKUch%2BaG%2Fumnu7yoIN%2B%2BSe7SmniqFBQhzEAIaDDg5MjM2NDY4NzY3MiIMbZug4gKRtItZx6U9KuIEMByxMRf7zvzgyYl5LpShQzltKXo38fuCoUJMVySNmMGRPGz0dSR78TuvaDbJFWXW9bj6wbOFZpOFYX5RFaMkGHDKddbP32k6RjvGWwzuSd5JTWpSBsAFdWpLcNL47TERbWGAgYtWpmdIKDNoQ8x4%2BmEK%2Bk119CMrnMkZKkjiRzzXOQECG5f0KSQ%2BenEkCWfjX%2B9ZAABhM%2FwSDBcVtrpZavDSohjzauFPq6Ut4AtlHOEQrFCixCNJSEwl0NGyogc7KVg1oDtSJ9kXyW0irbbq1LFPEsMAbFEcFchuftv%2BmQDbmGBktlAo7Dijc9ydaz0wr0ioFhmsL%2F%2F%2BlhYBtycwxQQyTWM1%2Bqy33BjcpQinhYqQHqTer5oB1qWhQbAi5t8zex9%2Fk%2FZ3Fr5PUX4xdxGe4ibMeEWZgE5pf8VkyGerUz4yuyJ6GUxrLyjRx6AXyE%2BNstKIOKWSCaaJ2jIRJdpB5crytQshWehBFSEBtGJ3lpsFxwfmJKeQwiR2fVGx2jyADoHMeMh8Di6zqTR3%2Bng%2FieTb%2BV%2Fd5FO2XHgBxEIbo3MPhEGJqidLSpoGfAf%2BtEfFsCx2qrZrC7p5EbnL25dQO7T5FEWfCnn1a1oY3ASgJKWQ9QcbMEOf0bd5ZxA0mmnL3DRxqlwt5ETw%2FC4tpscq66hfyRtP%2FqmhpL9t%2FIt0ItL%2FNtiLG2eQzU3NOkSrQiBTLcqdJ3ltxhWO4nd8pSAMEvRir3D1CB8Go1dPHUANyiy7MNluiFYI%2BqDqD8TmA6vNUof%2BybfpuMM4e%2F80VqgauMXn1h7wYlTIb0PdedGBpaqXgzDKsN%2FIBjqaAZc8vpFfn2CQVy8fJvJ50XlfK9udZK6Wcq00yCzlrAQkWhd8PCP8WkcHrC8wXcG3cM8oTayaiG0t5oM1aNc835uAWpKNbhAt7reww4GmqRUnmhHhCTtq5qT7mAkuBl%2Fb621Lcp%2F5KDPmOG%2BFraU8JDLDJrFcvoeZ5coWgsM2dw7ObZLs1jv8zDFQWZw214kleuKEbL54yaZTtc8%3D&X-Amz-Signature=b5611a93144ca8aba8fece57cc4bdca399ef395e8dd43f780d3234476937bef3&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Certification_Regarding_Debarment_Form_COWS.pdf%22&x-id=GetObject https://secure.procurenow.com/portal/cityofwestsacramento/projects/206560/document?section=undefined

5. Cost Table

TOTAL INSTALLATION COSTS

This should be inclusive of all labor and additional costs as well as any small miscellaneous items required to perform the work, such as tools, sundry parts, etc.

Line Item Description Quantity Unit of

Measure Unit Cost Total

1 Actiflo ATS Breaker & Controller

Replacement 1 lump sum

2 12KV Breaker Replacement & Testing 1 lump sum

TOTAL

6. Contract Award

6.1. Opening & Award of Contract

Bids will be opened publicly and read aloud at the time and date established in the invitation to Bidders.

Bid Summaries may be made available to Bidders after the Bid Date.

The City reserves the right to accept or reject any and all Bids for a period of sixty (60) days after the date of opening, and to waive any informality or irregularity in any Bid. No Bid can be withdrawn during that period, except pursuant to Public Contract Code section 5102, et seq. 1751480.1 7203-001

The City reserves the right to reject any or all Bids, including, without limitation, the right to reject any non-conforming, non-responsive, or conditional bids.

Before a Bid is considered for award, the City may, in addition to the Experience & Qualifications form included in the Bid documents, require a Bidder to submit a statement of facts and detail as to its business, technical organization and financial resources and equipment available and to be used in performing the work. Additionally, the City may require evidence that the Bidder has performed other work of comparable magnitude and type. The City expressly reserves the right to reject any Bid if it determines that the business and technical organization, equipment, financial and other resources or other experience of the Bidder (including the bidder’s Subcontractors) is not sufficiently qualified for the work Bid upon and, therefore, justifies such rejection.

The award of the Contract, if it is awarded, will be to the lowest responsive, responsible Bidder whose

Bid complies with the requirements set forth herein.

The issuance by the City of a notice to the successful Bidder of the award of the Contract (“Notice of

Award”) shall be deemed the Award of Contract.

6.2. Bid Protests

The lack of a prompt procedure to resolve disputes regarding the bidding process would impair the

City’s ability to carry out its purpose of constructing this project in a timely manner. Therefore, to the maximum extent authorized by law and notwithstanding any other procedures specified in documents referenced herein, all disputes and/or protests regarding the bidding process shall be subject to the following procedure. In submitting a Bid to the City for this project, the Bidder agrees to comply with and to be bound by this procedure.

Any Bid protest must be submitted in writing to the Director of Capital Projects & Transportation of the

City of West Sacramento before 5:00 p.m. on the fifth (5th) working day following Bid opening.

(a) The initial protest document must contain a complete statement of the basis for the protest, and all supporting documentation.

(b) The party filing the protest must have actually submitted a Bid for the Work. A Subcontractor of a party submitting a Bid for the Work may not submit a Bid protest. A party may not rely on the Bid protest submitted by another Bidder, but must timely pursue its own protest.

(c) The protest must refer to the specific portion of the Contract Documents which forms the basis for the protest.

(d) The protest must include the name, address and telephone number of the person representing the protesting party.

(e) The party filing the protest must concurrently transmit a copy of the initial protest document and any attached documentation to all other parties with a direct financial interest which may be adversely affected by the outcome of the protest. Such parties shall include all other Bidders who appear to have a reasonable prospect of receiving an award depending upon the outcome of the protest.

(f) The City will give the protested Bidder five (5) working days after the receipt of the protest to submit a written response. The responding Bidder shall transmit the response to the protesting Bidder concurrent with delivery to the City.

(g) The procedure and time limits set forth in this paragraph are mandatory and are the Bidder’s sole and exclusive remedy in the event of Bid protest. The Bidder’s failure to comply with these procedures shall constitute a waiver of any right to further pursue the Bid protest, including filing a Government

Code Claim or legal proceedings.

(h) If the City determines that a protest is frivolous, the protesting Bidder may be determined to be non-responsible and that Bidder may be determined to be ineligible for future contract awards.

File details come from the government source that posted it. Updated .