Statement of Work Falls Lake – Wilmington District

Septic System Repairs and Improvements

1. GENERAL

1.1 Summary of Work

The purpose of this contract is to make repairs and improvements to the existing septic system at the Falls Lake Dam and Visitor Center. The work site includes septic infrastructure located near the Visitor Center public restrooms and septic drain field. Service to be provided under this contract shall include all equipment, labor, supervision, and materials (except otherwise specified).

The physical address of the Falls Lake Visitor Center is 11405 Falls of Neuse Rd, Wake Forest, NC, 27587.

Site Location Map:

Infrastructure Diagram:

1.2 Objective of Work

The septic system that serves the Visitor Center, public restrooms, and maintenance facility has several issues that need to be addressed. Reference the infrastructure labelled on the diagram above as “tank 1”, “tank 2”.

1.2.1 Task 1- Improve Tank 1

Tank 1 is located south-east of a public restroom building and is a 1,500-gallon septic tank with two chambers. It was installed 2-3 feet below ground, so it was necessary to excavate around the top of the tank for septic pump out, which was completed on January 7, 2022. It remains generally uncovered, but additional dirt and vegetative material may need to be removed for access. The contractor shall install 2 concrete risers above each hatch (hatches measure 20” X 20”) with removable manhole lids to allow for future pump out access without having to excavate material. The risers shall be sealed to the top of the existing septic tank to prevent any material or roots penetrating the joint between the risers and tank.

Previously excavated dirt around the septic tank shall be moved back over the tank, matched to the surrounding natural grade, and all disturbed ground shall be seeded (see specifications for seeding in section 1.3).

Side view of septic tank 1 Inside hatch 1 after Jan 7, 2022 pump-out

1.2.2 Task 2- Repair Tank 2

Tank 2 is a 1,500-gallon septic tank and is located under a series of 4 in-line manholes. Roots from a nearby tree have penetrated a joint between two concrete risers of Manhole 1 about 6 feet below grade.

The tree has been cut, but the root system is still present below ground.

The contractor shall remove all of the root system inside the riser, the tank, and in the surrounding soil. The contractor shall then repair or replace the concrete riser structures to ensure they are properly sealed. This will likely require excavating and removing part or all of the risers of Manhole 1. The contractor shall coordinate with the COR and choose one of following approved methods of repair:

Option 1: Replace/repair existing risers. Once the roots have been removed, the contractor may elect to replace the existing concrete risers if they are still serviceable. Any damaged concrete shall be patched and/or otherwise repaired to the industry standard. Concrete surface defects, cracks, and voids shall be filled flush and true with grouting, plugging, or patching compound. The compound should be applied as recommended by the manufacturer for each application and in accordance with ICRI Technical Guideline No. 03730 “Guide for Selecting Application Methods for the Repair of Concrete Surfaces”. Once any damaged concrete is repaired, a clean joint surface shall be established and the riser will be re-installed and sealed back in place.

Option 2: Install new concrete risers. Once the roots have been removed, the contractor may elect to replace the existing concrete risers with a new replacement riser system. New concrete riser(s) shall meet all industry standards and match the existing riser’s dimensions and overall function in providing manhole access to the underground septic tank. New riser(s) shall be sealed to each other and to the septic tank, and shall prevent any dirt or roots from penetrating the system.

Once the concrete risers above the septic tank have been put back in place, all earth material will be replaced around the excavation site, returned to the surrounding natural grade, and seeded (see specifications for seeding in section 1.3).

First manhole with redbud tree cut at ground level

Manhole 1

Tree roots visible inside first manhole, about 6 ft below ground

1.3 Work Requirements

All work must meet NC Building and Septic Code and Regulations as defined in NC Septage Management Rules 15A NCAC 13B.0800 - .0846.

All disturbed ground shall be re-seeded once work is complete. Prepare the disturbed sites for placement of a hard fescue-clover blend. Minimum seed specifications are 98% purity and 90% germination rate.

Seed shall be spread at a rate of 5 lbs/1000 sq ft. Site shall be tamped after seed is disbursed and covered in straw at a rate of 80 lbs/1000 sq ft. Straw shall contain no mold or fertile seed and shall not be held in place by netting.

Materials shall be installed in accordance with the industry’s specifications, details, and workmanship requirements and meet NC Building and Septic Code. The contractor shall be responsible for protecting Government property and undisturbed land not intended for modification, from damage. Any damaged property shall be repaired to its original condition by the contractor at their own expense. The contractor is also responsible for removing all debris and excess materials from Government property.

1.4 Period of Performance

The contractor shall commence work under this contract within FIFTEEN (15) days upon issuance of contract award. All work shall be completed within 45 days of contract award. The time stated for completion shall include final cleanup of the premises.

1.5 Work Schedule

Normal working hours for the contractor shall be Monday through Friday (0700-1630), unless otherwise specified, or as specifically approved in advance by the Contracting Officer Representative (COR). All federal holidays shall be observed by the Contractor and no work shall be performed on-site other than what is specified in this statement of work and what is permitted by specific approval by the COR.

1.6 Pre-proposal Site Visit

Interested vendors may schedule a site visit with Mr. Francis Ferrell, Chief Park Ranger, at (919) 846- 9332 ext. 2224.

1.7 Safety

The Contractor shall provide adequate warning and danger signage and barricades and take necessary safety measure to protect the public during construction operations. Before any excavations takes place, the Contractor shall be responsible for location all underground utilities. Any utilities damaged by the Contractor’s work shall be repaired by the Contractor at no additional cost to the Government.

The Contractor shall be responsible for safeguarding the worksite at all times and shall comply with all current OSHA regulations and all requirements contained in EM 385-1-1, US Army Corps of Engineers Safety and Health Requirements Manual;

https://www.publication.usace.army.mil/Portals/76/Publications/EngineerManuals/EM 385-1-1.pdf.

Prior to any work activities, the Contractor shall prepare and submit an Accident Prevention Plan (APP). The APP shall be prepared in accordance with paragraph 01.A.12 and Appendix A of EM 385- 1-1. Since the work involves high hazard activities, an Abbreviated APP is not allowed for this work.

Any item in the APP checklist that is not applicable should be noted Not Applicable in the APP.

Activity Hazard Analyses (AHAs) shall be submitted for all Definable Features of Work.

This work involves Permit-Required Confined Space (PRCS) entry and fall protection/rescue that is associated with PRCS entry. These are high hazard activities. The access riser may contain low oxygen, explosive and toxic gases. Entry may require an airline respirator, as an air-purifying respirator probably may not be sufficient. The space will also require forced air ventilating prior to entry. There is also the fall hazard associated with working inside the access riser. When using the full APP, any item not applicable should be noted as such in the APP. Written programs required for this project include Confined Space, Respiratory Protection, and Fall Prevention and Protection, and Excavation and Trenching. There should be Competent Persons for each. AHA(s) should address each Definable Feature of Work (DFOW).

1.8 AT-OPSEC

Any Contractor that will require access to government facilities without supervision from a government employee shall comply with the following:

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

Pre-screen candidates using E-Verify Program. Proposed language: "The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

http://www.uscis.gov/e-verify)

EM 385-1-1

30 Nov 14

A-1

APPENDIX A

Minimum Basic Outline for Accident Prevention Plans

1. Accident Prevention Plan (APP) - General. An APP is a safety and health policy and program document that is contract- or job- specific. It is an integral part of the planning process. > See Section 01 and 01.A.12.

a. The APP shall interface with the employer’s overall safety and health program. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate.

b. The APP shall be submitted to the GDA for acceptance prior to work starting.

(1) Understanding that the APP is submitted prior to work starting and that some project-specific information is not yet known (e.g., subcontractors to be used, type of fall protection to be used at a certain point in time, specific cranes or other load handling equipment (LHE) to be brought on site, etc.), the known information shall be provided and additional information added at each preparatory phase/meeting along with the appropriate Activity Hazard Analyses (AHAs).

(2) A copy of the contractor’s project-specific, accepted APP shall be available on the work site. > See ANSI/ASSE A10.38 for programmatic issues.

2. Abbreviated APP. In lieu of a fully-developed APP, for Limited-Scope Service, Supply and R&D Contracts (e.g. grass mowing, park attendant, rest room cleaning, etc.), the Contracting Officer (KO) and local Safety and Occupational Health Office (SOHO) may allow an Abbreviated APP to be developed and submitted for acceptance.

a. The non-mandatory Abbreviated APP Form, Form A-1 (or similar) may be used to insure each area of required information has been provided.

b. This APP is a short-version APP that can be used on low-risk, limited-scope contracts. > See 01.A.12.e, and Appendix A, paragraph 3.k.

c. Each sub-contractor shall be provided a copy of the APP by the prime contractor and be required to comply with it.

A-2

3. APP Format. The following areas are typically addressed in an APP, but besides being job-specific, the APP shall also address any unusual or unique aspects of the contract or job for which it is written. The non-mandatory Accident Prevention Plan (APP) Checklist, Form A-2 (or similar), may be used to insure each area of required information has been provided. > See ANSI A10.33 for multi-employer projects.

a. Signature Sheet: Include title, signature, and phone number of the following:

(1) Plan preparer (Qualified Person (QP), Competent Person (CP), Corporate safety staff person, QC) and their qualifications;

(2) Plan must be approved by company/corporate officers authorized to obligate the company;

(3) Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Contractors shall provide concurrence of other applicable corporate and project personnel.

b. Background Information. List the following:

(1) Contractor;

(2) Contract number;

(3) Project name;

(4) Brief project description, description of work to be performed, location (map), equipment to be used, anticipated high risk activities, and

(5) Major phases of work anticipated.

(6) Within these major phases of work identified, activities [includes Definable features of Work (DFOWs) and tasks] to be performed that will require an AHA shall be specifically highlighted. This information can then be used by QC, QA and Safety personnel to track AHA submittals. The AHAs for these activities, tasks of DFOWs are NOT submitted at this time (AHAs created/submitted at this time would not be activity-specific as they are intended to be). > See Sections 01.A.14 and 01.A.15.

c. Statement of Safety and Health Policy. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees. The Contractor’s written safety program goals, objectives, and accident experience goals for this contract shall also be provided.

A-3

d. Responsibilities and Lines of Authority. Provide the following:

(1) A statement of the employer’s ultimate responsibility for the implementation of his SOH program for his own employees, all sub-contractors and all others on the worksite (includes the strict enforcement of the program).

(2) Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes. Qualifications shall be in accordance with Section 01.A.17.

Note: Only official OSHA 30-Hour cards will be accepted or, if equivalent training is provided, appropriate instructor qualifications. > See also Section 01.A.17.i, Exception 2.

(3) If equivalent training to the OSHA 30-hour classes is being presented as qualification, the training shall have covered the following areas:

(a) OSH Act/General Duty Clause;

(b) 29 CFR 1904, Recordkeeping;

(c) Subparts C, CC, D, E, F, K and M of OSHA;

(d) Rigging, load handling equipment (LHE), welding and cutting, scaffolding, excavations, concrete and masonry, demolition, health hazards in construction, materials handling, storage and disposal, hand and power tools, motor vehicles, mechanized equipment, marine operations, steel erection, stairways and ladders, confined spaces or any others that are applicable to the work being performed;

(4) The names of CP(s) and/or QP(s) and proof of competency/qualification to meet specific OSHA CP/QP requirements must be attached. The local SOHO will review the qualifications for acceptance;

(5) Requirements and details of the employer’s Risk Management Process;

Note: USACE uses the Activity Hazard Analysis (AHA) as part of a total risk management process. Contractors and other individual employer’s may use the AHAs or their own version [Job Safety Analyses (JSAs), Job Hazard Analyses (JHAs), or similar Risk Management assessment tools]. These documents are considered equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA.

(6) Requirements for initial activity-specific AHAs to be submitted and accepted at preparatory meetings, prior to work being performed;

A-4

(7) Requirements that no work by the Contractor shall be performed unless a designated CP/SSHO is present on the job site;

(8) Policies and procedures regarding non-compliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;

(9) Lines of authority;

(10) Provide written company procedures for holding managers and supervisors accountable for safety.

e. Subcontractors and Suppliers. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:

(1) Identification of subcontractors and suppliers. If not known at the time of initial APP submittal, the contractor shall include the following statement in their initial APP: “The subcontractors for the following DFOWs/activities are not known at this time, but additional information will be submitted to the APP for acceptance prior to the start of any activities listed”;

(2) Safety responsibilities of subcontractors and suppliers.

f. Training.

(1) Requirements for new hire SOH orientation training at the time of initial hire of each new employee.

(2) Requirements for mandatory training and certifications that are applicable to this project (e.g. explosive actuated tools, confined space entry, crane operator, underwater diver, vehicle operator, HAZWOPER training and certification, PPE, etc.) and any requirements for periodic retraining/recertification.

(3) Procedures for periodic safety and health training for supervisors and employees.

(4) Requirements for emergency response training.

g. Safety and Health Inspections.

(1) Specific assignment of responsibilities for a minimum daily jobsite SOH inspection during periods of work activity: Who will conduct (e.g., SSHO, PM, QC, supervisors, employees – depends on level of technical proficiency needed to perform said inspections), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, deficiency tracking system, and follow-up procedures;

A-5

(2) Any external inspections/certifications that may be required (e.g. USCG).

h. Mishap Reporting and Investigation. The Contractor shall identify means to provide the following:

(1) Exposure data (man-hours worked);

(2) Mishap reports, investigations, and documentation. Report all accidents per the requirements covered in Section 01.D. Mishaps shall be reported as soon as possible but not more than 24 hours afterwards to the KO/COR. The contractor shall report, thoroughly investigate, and analyze all mishaps occurring incidentally to an operation, project or facility for which this manual is applicable. Implement corrective actions as soon as reasonably possible and provide notice to the KO/COR when corrective actions are completed;

i. Plans, Programs and Procedures, required by this manual. Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable SOH risks and associated compliance plans.

(1) Include a project-specific compliance plan, as applicable to the work being performed, and as identified below. The plans shall incorporate project-wide procedures to control hazards to which the employees of all project employers may be exposed.

(2) These procedures shall be coordinated with all project employers and shall include project-specific, project-wide emergency response and evacuation procedures, PPE requirements, recordkeeping and reporting requirements, and training requirements.

(3) The plans shall be prepared prior to the start of any work activities on the job site (as much as the information can be known at that point in time). The plans shall be updated throughout the life of the project to include changes in personnel, equipment, conditions, etc. Additional revisions shall be incorporated as necessary to reflect changing site conditions, construction methods, personnel roles and responsibilities and construction schedules.

(4) No activity (DFOW) shall be started on site until the APP is revised and submitted to the GDA for acceptance, with the site-specific plans, programs and procedures required to complete the project. Using the EM 385-1-1 as a guide, plans, programs, procedures (assessments and evaluations) may include but not be limited to:

• Fatigue Management Plan (01.A.20);

• Emergency Plans (01.E);

• Site Sanitation/Housekeeping Plan (02.B);

A-6

• Medical Support Agreement (03.A.01; 03.A.03);

• Blood-Borne Pathogen Program (03.A.05);

• Exposure Control Plan (03.A.05);

• Automatic External Defibrillator (AED) Program (03.B.04);

• Site Layout Plan (04.A);

• Access/Haul Road Plan (04.B);

• Hearing Conservation Program (05.C);

• Respiratory Protection Plan (05.G);

• Health Hazard Control Program (06.A);

• Hazard Communication Program (06.B.01);

• Process Safety Management Program (06.B.04);

• Lead Compliance Plan (06.C.02 & specifications);

• Asbestos Abatement Plan (06.C.03 & specifications);

• Radiation Safety Program (06.F);

• Abrasive Blasting Procedures (06.I.01);

• Heat Stress Monitoring Plan (HSMP) (06.J.02);

• Cold Stress Monitoring Plan (CSMP) (06.J.04)

• Indoor Air Quality Management (06.L);

• Mold Remediation Plan (06.L.04);

• Chromium (VI) Exposure Evaluation (06.M);

• Crystalline Silica Evaluation (06.N.02);

• Lighting Plan for Night Operations (07.A.06);

• Traffic Control Plan (08.C.05);

A-7

• Fire Prevention Plan (09.A.01);

• Wild Land Fire Management Plan (09.L);

• Arc Flash Hazard Analysis (11.B);

• Assured Equipment Grounding Control Program (AEGCP) (11.D.05, Appendix E);

• Hazardous Energy Control Program & Procedures (12.A.01);

• Standard Pre-Lift Plan – Load Handling Equipment (16.A.03);

• Critical Lift Plan – Load Handling Equipment (16.H);

• Naval Architectural Analysis – Load Handling Equipment (Floating) (16.L);

• Floating Plant Inspection and Certification (19.A.01);

• Severe Weather Plan for Marine Activities (19.A.03);

• Emergency Plan for Marine Activities (19.A.04);

• Man Overboard/Abandon Ship Procedures (19.A.04);

• Float Plan for Launches, Motorboats, and Skiffs (19.F.04);

• Fall Protection and Prevention Plan (21.D);

• Demolition/Renovation Plan (to include engineering survey) (23.A);

• Rope Access Work Plan (24.H);

• Excavation/Trenching Plan (25.A.01);

• Fire Prevention and Protection Plan for Underground Construction (26.D.01);

• Compressed Air Work Plan for Underground Construction (26.I.01);

• Erection and Removal Plan for Formwork and Shoring (27.C);

• Precast Concrete Plan (27.D.01);

• Lift-Slab Plans (27.E);

• Masonry Bracing Plan (27.F.01);

A-8

• Steel Erection Plan (28.B);

• Explosives Safety Site Plan (ESSP) (29.A);

• Blasting Plan (29.A; 26.J);

• Dive Operations Plan (30.A.14, 30.A.16);

• Safe Practices Manual for Diving Activities (30.A.15)

• Emergency Management Plan for Diving (30.A.18)

• Tree Felling and Maintenance Program (31.A.01);

• Aircraft/Airfield Construction Safety & Phasing Plan (CSPP) (32.A.02);

• Aircraft/Airfield Safety Plan Compliance Document (SPCD) (32.A.02);

• Site Safety and Health Plan for HTRW (33.B);

• Confined Space Entry Procedures (34.A.05);

• Confined Space Program (34.A.06).

j. Risk Management Process (AHAs). Detailed project-specific hazards and controls shall be provided by AHAs for each activity (DFOW). No work will begin on an activity (DFOW) until the initial AHA has been accepted by the GDA addressing the project-specific hazards. > See Section 01.A.14 and 01.A.15.

Note: USACE uses the Activity Hazard Analysis (AHA) as part of a total risk management process. Contractors and other individual employer’s may use the AHAs or their own version [Job Safety Analyses (JSAs), Job Hazard Analyses (JHAs), or similar Risk Management assessment tools]. These documents are considered equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA.

(1) The AHA defines the work sequence, anticipated hazards, conditions, equipment, materials, personnel and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk, and the Risk Assessment Code for each step.

(2) Once this process has occurred, an overall RAC shall be assigned to the activity, based on the highest RAC assigned to an individual step.

A-9

(3) Acceptance of risk. The residual risk is that which remains after controls have been applied. This residual risk must be communicated to the proper authority for acceptance in order to proceed with the activity.

(4) Before beginning each work activity/DFOW, the Contractor performing that work activity shall prepare the initial AHA, which will include a RAC for that activity.

(5) No work will begin on the activity until the initial AHA has been accepted by the GDA addressing the activity-specific hazards.

(6) AHA’s are intended to be created by the contractor field crews/workers performing the work, with the assistance of others (SSHO, QC, Superintendent, etc) as needed. They are living documents and are intended to be created in the field and updated (by the workers) as needed.

(7) The AHA shall be reviewed and modified as necessary to address changing site conditions, operations, or change of CP(s)/QP(s).

(a) If a new CP/QP (not on the original list) is added, the list shall be updated (an administrative action not requiring an updated AHA). The new person shall acknowledge in writing that he or she has reviewed the AHA and is familiar with current site safety issues.

(b) If the initial RAC increases due to a change made to the AHA by the workers, the AHA shall be resubmitted to GDA for acceptance prior to work proceeding.

(c) Changes to or updates of an AHA that do not increase the RAC are not required to be resubmitted for acceptance by the GDA.

(8) Workers/crews shall have in their possession the current AHA that reflects current site conditions, personnel, equipment, control measures, etc while the work is being performed.

(9) The AHA shall be used by the contractor and USACE personnel to assure work is being performed consistent with the AHA. In the event that the work is not being conducted in a safe manner, the contractor and/or the USACE shall stop the unsafe work being conducted until it is in compliance with this manual, APP and the AHA or the APP/ AHA is revised and accepted by the GDA, if necessary. > See Section 01.A.14.

(10) Once the activity has been completed, the AHA shall be available and kept on file on site for the length of the contract.

A-10

k. Abbreviated APP for Limited-Scope Service, Supply and R&D Contracts. If service, supply and R&D contracts with limited-scopes are awarded, the contractor may submit an abbreviated APP in lieu of a full APP. The abbreviated APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well. The non-mandatory Abbreviated APP Form, Form A-01 (or similar) may be used to insure each area of required information has been provided.

(1) Title, signature, and phone number of the plan preparer.

(2) Background Information to include:

(a) Contractor;

(b) Contract number;

(c) Project name;

(d) Brief project description, Note: The project description shall provide a means to evaluate the work being done (see AHA requirements in 01.A.14), associated hazards involved and a RAC assigned to each. The overall RAC for the activity must be determined (based on highest task RAC) and accepted at the appropriate level in order for work to proceed.

(e) Description of work to be performed, and

(f) Location of work being performed, to include a map.

(3) Statement of Safety and Health Policy detailing their commitment to providing a safe and healthful workplace for all employees.

(4) Responsibilities and Lines of Authorities – to include a statement of the employer’s ultimate responsibility for the implementation of his SOH program; Identification and accountability of personnel responsible for safety at all levels to include designated site safety and health officer (SSHO) and associated qualifications. The District SOHO will be asked to review the qualifications for acceptance.

(5) Training - new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements.

(6) Procedures for job site inspections - assignment of responsibilities and frequency.

A-11

(7) Procedures for reporting man-hours worked and reporting and investigating any mishaps required by Section 01.D.

(8) Emergency Planning. Employees working alone shall be provided an effective means of emergency communication. This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.

(9) Drinking Water provisions, toilet and washing facilities.

(10) First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kits (types/size).

(11) Personal Protective Equipment (PPE).

(a) Work Clothing - Minimum Requirements. Employees shall wear clothing suitable for the weather however minimum requirements for work shall be short-sleeve shirt, long pants (excessively long or baggy pants are prohibited) and leather work shoes. If analysis determines that safety-toed (or other protective) footwear is necessary (i.e., mowing, weedeating, chainsaw use, etc), they shall be worn.

(b) Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed, however, all involved in chainsaw use, chipping, stump grinding, pruning operations, grass mowing, weedeating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.

(c) Hearing Protection. Hearing protection must be worn by all those exposed to high noise activities (to include grass mowing and trimming, chainsaw operations, tree chipping, stump grinding and pruning).

(d) Head Protection. Hard hats shall comply with ANSI Z89.1 and shall be worn by all workers when a head hazard exists, per Section 05.D.

(e) High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.

(f) Protective Leg chaps shall be worn by all chainsaw operators.

(g) Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.

(h) If work is being performed around water and drowning is a hazard, PFDs must be provided and worn as appropriate.

A-12

(12) Machine Guards and safety devices. Power tools/equipment must have appropriate guards and safety devices in place and operational.

(13) Hazardous Substances. When any hazardous substances are procured, used, stored or disposed, a Hazard Communication Program must be in place and MSDSs (SDSs) shall be available at the worksite. Employees shall have received training in hazardous substances being used. When the eyes or body of any person may be exposed to corrosives, irritants or toxic chemicals, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within 10 seconds of the worksite.

(14) Traffic control shall be accomplished in accordance with DOT’s MUTCD.

(15) Control of Hazardous Energy (Lockout/Tagout). Before an employee performs any servicing or maintenance on any equipment where the unexpected energizing or startup of the equipment could occur, procedures must be in place to ensure adequate control of this energy. > See Section 12.

(16) High hazard activities should not be encountered on these types of jobs. If they are (i.e., driving/operating equipment on slopes, working from/in boats, etc), a determination shall be made by the KO and local SOH Office as to whether an abbreviated APP is applicable. If so, they shall be fully addressed in the APP. AHAs are required on work activities which include high hazard activities.

Statement of Work
1.2 Objective of Work
1.3 Work Requirements
1.4 Period of Performance
1.8 AT-OPSEC
Full APP Format.pdf