United States Department of the Interior Bureau of Land Management
Tres Rios Field Office Colorado
Aqueduct and Turtle Lake Parking Lots
SPECIFICATIONS
Aqueduct and Turtle Lake Parking Lots BLM Colorado
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 12 00 GOVERNMENT SUPPLIED MATERIAL
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 57 60 SUPPLEMENTAL ENVIRONMENTAL CONTROLS
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 50 12 STEEL GATE - ROAD
DI VI SI ON 09 - FI NI SHES
09 90 10 PAINTING
DI VI SI ON 12 - FURNI SHI NGS
12 93 00 SITE FURNISHINGS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 31 26 WIRE FENCES AND GATES
DI VI SI ON 33 - UTI LI TI ES
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
The work includes, but is not limited to; road and parking area construction, fencing, gate, culvert, kiosk, parking delineators, signs, and demolition.
1.2 LOCATION
The project locations are near Mancos and Durango CO. Site locations can be found in google maps. Google maps keyword search:
Aqueduct Main Trailhead Parking Turtle Lake Bouldering, Durango, CO
Aqueduct Location - NORTH Latitude 37.358776° Longitude -108.334162°
Turtle Lake Location Latitude 37.333173° Longitude -107.882172°
1.3 WORK SCHEDULE
Work is not allowed at the Aqueduct sites between December 1st and April 30th to protect wildlife during winter.
Work shall be completed within 150 days of the Notice to Proceed. Work shall occur Monday - Friday, excluding federal holidays.
1.4 DRIVEWAY PERMIT
Obtain a driveway permit from La Plata County for the Turtle Lake parking area. The BLM already submitted the permit application. However, La Plata County requires a permit bond and permit fee from the contractor.
The BLM already has the driveway permits for the Aqueduct parking areas.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 12 00
GOVERNMENT SUPPLIED MATERIAL
PART 1 GENERAL
1.1 LOCATION
The Government supplied items are located at the BLM, Tres Rios field office:
29211 CO-184
Dolores, CO 81323
Contractor is responsible for loading and transporting items.
PART 2 PRODUCTS
The following items will be Government supplied:
2.1 KIOSK
Two kiosks are required. Only one kiosk will be Government supplied. The kiosk is new and needs to be assembled and painted. The Contractor is responsible for transportation of the kiosk from storage to the project site.
The kiosk was manufactured by "Wood Product Signs". Kiosk features include:
Custom 9' Utah Roof Kit with metal roof
(3) 6" x 6" x 10'4" Metal Posts
(2) 36" x 48" - Bulletin Boards
2.2 ENTRANCE SIGNS
Four 48" x 24" BLM entrance signs.
PART 3 EXECUTION
Not Used.
SECTION 01 12 00 Page 3
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
Payment items for the work of this contract for which contract payments will be made are listed in the SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job are included in the listed job item most closely associated with the work involved. The price and payment made for each item listed constitutes full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1 MOBILIZATION AND DEMOBILIZATION - AQUEDUCT NORTH
1.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization.
When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
When 15% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 8% of the original Contract amount, whichever is lesser, will be paid.
Upon completion of work for the project, payment of the amount bid for mobilization in excess of 8% of the original Contract amount, will be paid.
1.1.2 Unit of Measure
Unit of measure: job.
1.2 SURVEY - STAKE OUT - AQUEDUCT NORTH
1.2.1 Payment
Payment will be made for all costs associated with surveying and staking out the work.
1.2.2 Unit of Measure
Unit of measure: Job.
SECTION 01 20 00 Page 4
1.3 CLEARING AND GRUBBING - AQUEDUCT NORTH
1.3.1 Payment
Payment will be made for all costs associated with clearing and grubbing.
Including transportation and disposal of materials.
1.3.2 Unit of Measure
Unit of measure: Job.
1.4 DEMOLITION - AQUEDUCT NORTH
1.4.1 Payment
Payment will be made for all costs associated with demolition. Including transportation and disposal.
1.4.2 Unit of Measure
Unit of measure: job.
1.5 SITE GRADING - AQUEDUCT NORTH
1.5.1 Payment
Payment will be made for all costs associated with site grading.
1.5.2 Unit of Measure
Unit of measure: Job.
1.6 AGGREGATE BASE COURSE - AQUEDUCT NORTH
1.6.1 Payment
Payment will be made for all costs associated with providing aggregate base course. Including preparation, transportation, placement, moisture conditioning, and compaction. Submit weight tickets for payment.
1.6.2 Unit of Measure
Unit of measure: ton.
1.7 MOISTURE CONDITIONING AND COMPACTION - AQUEDUCT NORTH
1.7.1 Payment
Payment will be made for all costs associated with moisture conditioning and compaction of the subgrade and aggregate.
SECTION 01 20 00 Page 5
1.7.2 Unit of Measure
Unit of measure: Job.
1.8 STEEL PARKING DELINEATOR - AQUEDUCT NORTH
1.8.1 Payment
Payment will be made for all costs associated with providing steel parking delineators.
1.8.2 Unit of Measure
Unit of measure: Each.
1.9 CONCRETE PARKING STOP - AQUEDUCT NORTH
1.9.1 Payment
Payment will be made for all costs associated with providing parking stops.
1.9.2 Unit of Measure
Unit of measure: Each.
1.10 KIOSK (Government Provided) - AQUEDUCT NORTH
1.10.1 Payment
Payment will be made for all costs associated with providing a kiosk.
Including transportation, preparation, grading, foundation, erection, and painting.
1.10.2 Unit of Measure
Unit of measure: Each.
1.11 WIRE FENCING - AQUEDUCT NORTH
1.11.1 Payment
Payment will be made for all costs associated with providing wire fencing. Including access gate, end panels, and corner panels.
1.11.2 Unit of Measure
Unit of measure: Linear Foot.
SECTION 01 20 00 Page 6
1.12 CORRUGATED METAL PIPE CULVERT - AQUEDUCT NORTH
Payment will be made for all costs associated with providing a corrugated metal pipe culvert, including bedding material, earthwork, and compaction.
1.12.1 Unit of Measure
Unit of measure: linear foot
1.13 ENTRANCE SIGN - AQUEDUCT NORTH
1.13.1 Payment
Payment will be made for all costs associated with providing an entrance sign.
1.13.2 Unit of Measure
Unit of measure: Each.
1.14 GATE - ROAD - AQUEDUCT NORTH
1.14.1 Payment
Payment will be made for all costs associated with providing a road gate.
1.14.2 Unit of Measure
Unit of measure: Each.
1.15 MOBILIZATION AND DEMOBILIZATION - AQUEDUCT SOUTH
1.15.1 Payment
Payment will be made for costs associated with mobilization and demobilization.
When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
When 15% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 8% of the original Contract amount, whichever is lesser, will be paid.
Upon completion of work for the project, payment of the amount bid for mobilization in excess of 8% of the original Contract amount, will be paid.
1.15.2 Unit of Measure
Unit of measure: job.
SECTION 01 20 00 Page 7
1.16 SURVEY - STAKE OUT - AQUEDUCT SOUTH
1.16.1 Payment
Payment will be made for all costs associated with surveying and staking out the work.
1.16.2 Unit of Measure
Unit of measure: Job.
1.17 CLEARING AND GRUBBING - AQUEDUCT SOUTH
1.17.1 Payment
Payment will be made for all costs associated with clearing and grubbing.
Including transportation and disposal of materials.
1.17.2 Unit of Measure
Unit of measure: Job.
1.18 DEMOLITION - AQUEDUCT SOUTH
1.18.1 Payment
Payment will be made for all costs associated with demolition. Including transportation and disposal.
1.18.2 Unit of Measure
Unit of measure: job.
1.19 SITE GRADING - AQUEDUCT SOUTH
1.19.1 Payment
Payment will be made for all costs associated with site grading.
1.19.2 Unit of Measure
Unit of measure: Job.
1.20 AGGREGATE BASE COURSE - AQUEDUCT SOUTH
1.20.1 Payment
Payment will be made for all costs associated with providing aggregate base course. Including preparation, transportation, placement, moisture
SECTION 01 20 00 Page 8 conditioning, and compaction. Submit weight tickets for payment.
1.20.2 Unit of Measure
Unit of measure: ton.
1.21 MOISTURE CONDITIONING AND COMPACTION - AQUEDUCT SOUTH
1.21.1 Payment
Payment will be made for all costs associated with moisture conditioning and compaction of the subgrade and aggregate.
1.21.2 Unit of Measure
Unit of measure: Job.
1.22 CONCRETE PARKING STOP - AQUEDUCT SOUTH
1.22.1 Payment
Payment will be made for all costs associated with providing parking stops.
1.22.2 Unit of Measure
Unit of measure: Each.
1.23 GATE - ROAD - AQUEDUCT SOUTH
1.23.1 Payment
Payment will be made for all costs associated with providing a road gate.
1.23.2 Unit of Measure
Unit of measure: Each.
1.24 MOBILIZATION AND DEMOBILIZATION - TURTLE LAKE
1.24.1 Payment
Payment will be made for costs associated with mobilization and demobilization.
When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
When 15% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 8% of the original Contract amount, whichever is lesser, will be paid.
Upon completion of work for the project, payment of the amount bid for mobilization in excess of 8% of the original Contract amount, will be paid.
SECTION 01 20 00 Page 9
1.24.2 Unit of Measure
Unit of measure: job.
1.25 SURVEY - STAKE OUT - TURTLE LAKE
1.25.1 Payment
Payment will be made for all costs associated with surveying and staking out the work.
1.25.2 Unit of Measure
Unit of measure: Job.
1.26 CLEARING AND GRUBBING - TURTLE LAKE
1.26.1 Payment
Payment will be made for all costs associated with clearing and grubbing.
Including transportation and disposal of materials.
1.26.2 Unit of Measure
Unit of measure: Job.
1.27 SITE GRADING - TURTLE LAKE
1.27.1 Payment
Payment will be made for all costs associated with site grading.
1.27.2 Unit of Measure
Unit of measure: Job.
1.28 AGGREGATE BASE COURSE - TURTLE LAKE
1.28.1 Payment
Payment will be made for all costs associated with providing aggregate base course. Including preparation, transportation, placement, moisture conditioning, and compaction. Submit weight tickets for payment.
1.28.2 Unit of Measure
Unit of measure: ton.
SECTION 01 20 00 Page 10
1.29 MOISTURE CONDITIONING AND COMPACTION - TURTLE LAKE
1.29.1 Payment
Payment will be made for all costs associated with moisture conditioning and compaction of the subgrade and aggregate.
1.29.2 Unit of Measure
Unit of measure: Job.
1.30 CONCRETE PARKING STOP - TURTLE LAKE
1.30.1 Payment
Payment will be made for all costs associated with providing parking stops.
1.30.2 Unit of Measure
Unit of measure: Each.
1.31 KIOSK - TURTLE LAKE
1.31.1 Payment
Payment will be made for all costs associated with providing a kiosk.
Including transportation, preparation, grading, foundation, erection, and painting.
1.31.2 Unit of Measure
Unit of measure: Each.
1.32 CORRUGATED METAL PIPE CULVERT - TURTLE LAKE
Payment will be made for all costs associated with providing a corrugated metal pipe culvert, including bedding material, earthwork, and compaction.
1.32.1 Unit of Measure
Unit of measure: linear foot
1.33 ENTRANCE SIGN - TURTLE LAKE
1.33.1 Payment
Payment will be made for all costs associated with providing an entrance sign.
SECTION 01 20 00 Page 11
1.33.2 Unit of Measure
Unit of measure: Each.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 12
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule ; G
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution.
3.2.2 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of submittals.
b. Long procurement activities
c. Contractor's pre-final inspection.
d. Government's pre-final inspection.
e. Final inspection.
SECTION 01 32 01 Page 13
3.2.3 Government Activities
Include Government activities that could impact progress. These activities include, but are not limited to: Government inspections of work, Government approval of submittals.
3.3 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.
3.4 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
3.4.1 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.
3.4.2 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
SECTION 01 32 01 Page 14
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
1.2 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer's Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.3 GOVERNMENT APPROVING AUTHORITY
The Contracting Officer's Representative will:
a. Note the date on which the submittal was received.
b. Review submittals for approval within 10 days of receipt.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer's Representative and one copy of the submittal will be returned to the Contractor.
1.3.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with
SECTION 01 33 00 Page 15 appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.4 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer's Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.5 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 16
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 1 PAGES
Aqueduct and Turtle Lake Parking Lots
01 32 01 SD-01 Preconstruction Submittals
GInitial Project Schedule
01 57 60 SD-01 Preconstruction Submittals
3.4 GSpill Prevention And Cleanup
Plan
12 93 00 SD-03 Product Data
2.2 GKiosk
2.3 GNo Camping Sign
2.4 GConcrete Parking Stops
31 00 00 SD-03 Product Data
2.1 GAggregate Base Course
SD-07 Certificates
3.5Aggregate Weight Tickets
33 40 00 SD-03 Product Data
2.1 GCorrugated Steel Pipe
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SECTION 01 57 60
SUPPLEMENTAL ENVIRONMENTAL CONTROLS
PART 1 GENERAL
1.1 DEFINITIONS
Equipment: for the purpose of this specification, equipment shall include, but isn't limited to; dozers, backhoes, trackhoes, trailers, graders, compactors, or any other construction equipment used to accomplish the work. Passenger vehicles are not considered equipment.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Spill Prevention And Cleanup Plan ; G
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 EROSION CONTROL
Contractor shall inspect site after rain (or melt) events and mitigate areas where erosion or sediment runoff is occurring. Erosion includes wind. Contractor shall water exposed soils, as necessary, to prevent wind erosion.
3.2 FIRE PREVENTION
All equipment shall have a spark arrester installed. The Contractor shall have a fire extinguisher and shovel readily available to contain and extinguish fires.
3.3 EQUIPMENT CLEANING AND MAINTENANCE
Equipment shall be cleaned prior to arriving on site. Equipment shall arrive on site free from dirt, debris, weeds, and seeds. All equipment shall be inspected by the Contracting Officer's Representative prior to arriving on site. Notify the Contracting Officer's Representative at least 3 days prior to equipment delivery to coordinate inspection. If equipment leaves the jobsite and returns at a later date, then equipment shall be re-inspected before reentering the work site.
Equipment maintenance will not be allowed on site. Equipment leaking fluids shall be removed from site.
SECTION 01 57 60 Page 17
3.4 SPILL PREVENTION
The Contractor shall submit a spill prevention and cleanup plan. The spill prevention and cleanup plan shall identify foreseeable accidents, including spills while adding fluids to equipment, and identify an action plan to rapidly clean all accidents. Cleanup materials and equipment shall be on site during work.
3.5 WASTE CONTROL
All waste generated by the work shall be contained and removed from the site and disposed of in a legal manor.
SECTION 01 57 60 Page 18
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C387/C387M (2017) Standard Specification for Packaged, Dry, Combined Materials for Concrete and High Strength Mortar
PART 2 PRODUCTS
2.1 CONCRETE
Prepackaged concrete mix shall be identified as conforming to ASTM C387/C387M Normal Strength Concrete; Normal Weight Concrete, with a minimum compressive strength of 4,500 psi.
PART 3 EXECUTION
3.1 PREPACKAGED CONCRETE MIXTURE
Use the minimum amount of water to make the mixture. Adding too much water to the mixture will greatly reduce the overall compressive strength. Average slump shall be between 2" to 4".
3.2 FOOTINGS
Concrete for footings may be placed in excavations without forms.
Excavation width must be a minimum of 4 inches greater than indicated if forms are not used.
3.3 CONCRETE CONSOLIDATION
Concrete shall be adequately vibrated, rodded, or spaded into place to fill voids.
SECTION 03 30 00 Page 19
SECTION 05 50 12
STEEL GATE - ROAD
PART 1 GENERAL
Provide a steel gate as shown on the plans and as specified below.
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
PART 2 PRODUCTS
2.1 STEEL
Steel shall pipe shall be in accordance with ASTM A53/A53M.
2.2 SIGNS
Signs shall comply with the Manual of Uniform Traffic Control Devices (MUTCD). OM4-1 signs shall be 18" x 18". OM2-2V signs shall be 12" x 6".
2.3 CONCRETE
In accordance with section 03 30 00 .
PART 3 EXECUTION
3.1 FABRICATION, WELDING, AND INSTALLATION
Verify all dimensions prior to fabrication. Perform welding in accordance with AWS D1.1/D1.1M . Field verify post locations prior to setting. Set posts vertically in concrete piers. Fill posts with concrete.
3.2 PAINT
Paint all surfaces in accordance with section 09 90 10 .
3.3 SIGNS
Firmly secure signs to the gate and gate posts. Provide galvanized or stainless steel hardware.
SECTION 05 50 12 Page 20
SECTION 05 50 12 Page 21
SECTION 09 90 10
PAINTING
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
Paint the gate and kiosk.
PART 2 PRODUCTS
2.1 PRIMER
Sherwin-Williams: "Multi-Purpose Interior/Exterior Latex Primer/Sealer".
2.2 PAINT
Wood and Metal Surfaces:
Sherwin-Williams: "All Surface Enamel Latex".
2.3 PAINT COLOR
Color shall be Sherwin Williams "7512 Pavilion Beige".
PART 3 EXECUTION
3.1 SURFACE PREPARATION
Remove dirt, splinters, loose particles, disintegrated coatings, and other foreign matter and substances prior to applying paint.
3.2 APPLICATION
Apply primer to metal surfaces.
Apply two coats of paint to all surfaces. Allow time between coats to permit thorough drying.
Only apply paints to surfaces that are completely free of moisture as determined by sight or touch.
Apply each coat of paint so that dry film is of uniform thickness and free from runs, drops, ridges, waves, pinholes or other voids, laps, brush marks, and variations in color, texture, and finish.
SECTION 09 90 10 Page 22
SECTION 12 93 00
SITE FURNISHINGS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Kiosk ; G
No Camping Sign ; G
Concrete Parking Stops ; G
PART 2 PRODUCTS
2.1 STEEL PARKING DELINEATORS
Steel parking delineators shall be schedule 40 steel pipe. Used pipe may be supplied; however pipe must be clean and free of oil, grease, rust, etc. Pipe must be straight and have no dents, bends, or obvious defects.
2.2 KIOSK
Note: Two kiosks are required. Only one kiosk will be Government supplied.
Kiosk shall be manufactured by "Wood Product Signs". Kiosk features include:
Custom 9' Utah Roof Kit with brown metal roof
(3) 4" x 4" x 10'4" Metal Posts, painted brown 36" x 48" - Bulletin Boards with routed pocket for digital graphic 33" x 32" - Digital Graphic inlay 36" x 48" - Bulletin Boards with routed pocket for corkboard 32" x 8.5" - Corkboard inlay
The bulletin board routed text and digital graphics will be provided after BLM acceptance of the submittal and will not impact the product cost or installation.
2.3 NO CAMPING SIGN
The "no camping" sign shall be as manufactured by "Rock Art Signs", sign number 10-146-8. 8" x 8" x 0.08" Aluminum sign, with brown background and red "prohibited line".
2.4 CONCRETE PARKING STOPS
Parking stops shall be reinforced concrete. With minimum dimensions of;
six foot length, eight inch width, and 5 inch height.
SECTION 12 93 00 Page 23
2.5 CONCRETE
In accordance with section 03 30 00 .
PART 3 EXECUTION
3.1 STEEL PARKING DELINEATORS
Steel parking delineators shall be installed as shown on the drawings.
Tops of the steel parking delineators shall be set three inches above the finished grade of the aggregate surfacing.
3.2 ENTRANCE SIGN
Install the sign posts plumb as shown on the drawings. Entrance signs shall be installed on both sides of the posts. The entrance signs and mounting hardware will be Government provided. Install the signs with the mounting hardware provided. A picture of the mounting hardware is on the plans for reference.
3.3 NO CAMPING SIGNS
Install the sign posts plumb as shown on the drawings. Firmly secure signs to the posts using galvanized or stainless steel hardware.
3.4 KIOSK
Install the kiosk posts plumb as shown on the drawings. Construct the kiosk according to the manufacturer's directions. Paint wood and structural metal surfaces in accordance with section 09 90 10 .
3.5 CONCRETE PARKING STOPS
Each parking stop shall be held in place with two (2) #4 rebars, 24 inches long.
SECTION 12 93 00 Page 24
SECTION 31 00 00
EARTHWORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Aggregate Base Course ; G
SD-07 Certificates
Aggregate Weight Tickets
PART 2 PRODUCTS
2.1 AGGREGATE BASE COURSE
Aggregate base course shall meet the requirements of Colorado Department of Transportation Standard Specifications for Road and Bridge Construction 2021, section 703 AGGREGATES. Aggregate base course gradation shall meet the gradation shown in Table 703-2, Class 6.
PART 3 EXECUTION
3.1 UNDERGROUND UTILITIES
The Contractor is responsible for locating underground utilities prior to construction. The Government is not aware of any underground utilities, however the Contractor shall verify the presence or absence prior to construction.
3.2 GENERAL EXCAVATION
Perform excavation of every type of material encountered to the lines, grades, and elevations indicated and as specified. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times.
3.3 GROUND SURFACE PREPARATION
Clear and grub in accordance with section 31 11 00 . Do not perform construction when surfaces are frozen or muddy. Prepare the subgrade to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Shape subgrade to drain.
3.4 AGGREGATE PLACEMENT LOCATIONS
3.4.1 Subgrade
Contractor shall prepare the subgrade to the lines and grades shown on the
SECTION 31 00 00 Page 25 plans.
3.4.2 Subgrade Compaction
Moisten material as necessary to achieve compaction. Compact the subgrade by operating vibratory compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.
3.4.3 Aggregate Base Course
Contractor shall receive approval of the subgrade prior to placing aggregate base course. Place base course aggregate to the lines and grades shown on the plans.
3.4.4 Aggregate Base Course Compaction
Moisten material as necessary to achieve compaction. Compact the base course aggregate by operating vibratory compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.
3.5 AGGREGATE WEIGHT TICKETS
Submit aggregate weight tickets . Weight tickets are required prior to payment.
3.6 EXCESS MATERIAL DISPOSAL
Excess cut material shall be spread uniformly on site, at designated locations near the site work. Excess cut material shall not be removed from the work site.
3.7 FINISHING
Finish the surfaces to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.2 foot of the grades and elevations indicated. Finish surfaces in a manner that will result in effective drainage, regardless of tolerance.
SECTION 31 00 00 Page 26
SECTION 31 11 00
CLEARING AND GRUBBING
PART 1 GENERAL
Not Used.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 SURVEY STAKE OUT
Prior to clearing and grubbing, the contractor shall stake out the roads and parking areas as detailed on the drawings. The Contracting Officer's Representative will review the layout as staked and may make minor modifications to the layout in order to minimize the damage to existing vegetation. The contractor shall receive approval of the stakeout prior to clearing and grubbing.
3.2 CLEARING AND GRUBBING LIMITS
Clearing and grubbing limits shall be within the road and parking areas, including the ditches.
3.3 PROTECTION
Protect trees and vegetation from damage incident to clearing, grubbing, and construction operations.
3.4 CLEARING
Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Trees, stumps, roots, brush, and other vegetation in areas to be cleared shall be cut off flush with or below the original ground surface.
3.5 GRUBBING
Grubbing consists of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas.
Remove material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, to a depth of not less than 12 inches below the original surface level of the ground in the area of new road construction. Fill depressions made by grubbing with suitable material and compact to make the surface conform with the original adjacent surface of the ground.
3.6 DISPOSAL OF CLEARING AND GRUBBING VEGETATION
Logs, stumps, roots, brush, rotten wood, and other organic material
SECTION 31 11 00 Page 27 resulting from the clearing and grubbing operations, shall be uniformly scattered on site in piles less than 12 inches off the ground.
SECTION 31 11 00 Page 28
SECTION 32 31 26
WIRE FENCES AND GATES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
AWPA U1 (2017) Use Category System: User Specification for Treated Wood
ASTM INTERNATIONAL (ASTM)
ASTM A121 (2013) Standard Specification for Metallic-Coated Carbon Steel Barbed Wire
ASTM A702 (2013) Standard Specification for Steel Fence Posts and Assemblies, Hot Wrought
PART 2 PRODUCTS
2.1 BARBED WIRE
Barbed wire shall be a strand of two (2) 12-1/2-gauge galvanized wires twisted together with 2-point barbs of 14-gauge wire spaced 4 inches apart. Wire and barbs shall be zinc-coated steel, with a Class 1 zinc coating as per ASTM A121. The minimum breaking strength of each wire shall be 950-lb force. The barbed wire shall conform to ASTM A121
2.2 BARBLESS WIRE
Barbless wire shall be a strand of two (2) 12-1/2-gauge, galvanized wires twisted together. Wire shall be a Class 1 zinc coating as per ASTM A121.
The minimum breaking strength of each wire shall be 950-lb force. The barbless wire shall conform to ASTM A121.
2.3 WOOD POSTS AND BRACES - PANELS AND GATES
Wood posts and braces used for the panels and gates shall be sound single-stem members of round cross section and have 5 inches minimum diameter at the small end. Provide posts free of ring shake, season cracks more than 1/4 inch wide, splits in the end, and unsound knots.
Treat posts in accordance with AWPA U1. Honey Locust, western red cedar (full stem with bark removed), Juniper, Osage Orange, and White Oak are acceptable without treatment.
2.4 WOOD FENCE POSTS
Wood fence posts shall be sound single-stem members of round cross section and have 4 inches minimum diameter at the small end. Provide posts free
SECTION 32 31 26 Page 29 of ring shake, season cracks more than 1/4 inch wide, splits in the end, and unsound knots. Treat posts in accordance with AWPA U1. Honey Locust, western red cedar (full stem with bark removed), Juniper, Osage Orange, and White Oak are acceptable without treatment. .
2.5 STEEL FENCE POSTS
Steel fence posts shall conform to ASTM A702; green with white or silver top "T" bar type, with a welded or riveted anchor plate. Furnish with clip-type wire fasteners (punched tabs for fastening wires are not acceptable). Steel posts shall be manufactured from wrought, rail or new billet steel, shall have a minimum weight of 1.33 pounds per linear foot.
The anchor plates shall weigh a minimum of 0.67 pounds and shall have a minimum area of 18 square inches.
2.6 STEEL TUBE GATE
Steel tube gate shall be welded pipe with minimum pipe diameter of 1-1/2 inches and be factory painted. Provide hinges, latches, and other hardware as required for the operation of the gate.
PART 3 EXECUTION
3.1 ALIGNMENT
The Contractor shall layout and stake the fence alignment for approval by the Contracting Officer's Representative. The fence and gate locations shall generally match the layout shown on the plans, with deviations for constructability. The fence shall align with the road gate. The maximum gap between the fence and the road gate shall be two feet.
3.2 CLEARING
Clearing shall be limited to cutting of brush in the fence line alignment. Maximum clearing width is 6 feet on each side of the fence line. Minimize disturbance to existing vegetation.
3.3 END PANELS, CORNER PANELS, AND GATE PANELS
Construct as shown on the drawings. Corner panels shall be constructed at the intersection with the existing fence. Tie (connect) existing fence into the new fence corner panel. Corner panels shall be constructed at changes in fence alignment. Gate panels shall be constructed at the gate.
Set posts plumb in dug or drilled holes. Post holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Place backfill in layers of 9 inches or less, moistened to optimum condition, and compacted with hand tampers.
3.4 WOOD LINE POSTS
Set posts plumb in dug or drilled holes. Post holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Place backfill in layers of 9 inches or less, moistened to optimum condition, and compacted with hand tampers.
3.4.1 Wood Line Post Frequency
Every third line post shall be a wood post.
SECTION 32 31 26 Page 30
3.5 STEEL LINE POSTS
Posts shall be driven plumb.
3.6 WIRE
Wire is properly stretched when it is springy to the touch. Stretch tightly and staple to wood posts or securely attach to steel posts with standard manufactured wire clips. Drive staples into wood until the staple comes in contact with the wire against the post, but not so tight as to crimp the wire or prevent free movement of the wire between the post and the staple. Do not drive staples parallel to the grain of the wood.
3.7 WIRE CLIPS
Wire clips shall be used on every wire at steel post locations. Secure wire to steel posts by bending clip ends over or around wire, crimping ends to secure wire on both sides of the post, but not so tight as to prevent free movement of the wire through the clip. Each side of the clip shall be twisted around the wire and back parallel to the clip itself.
3.8 BRACE WIRE
Shall be double looped in a crisscross fashion, twisted tight with either four plies of 9-gauge smooth wire or 8 plies of 12-1/2-gauge wires. Leave one end of the stick long enough to fasten behind the horizontal brace to prevent wire from unwinding.
3.9 SPIKING
Predrilled lead holes shall be used. The hole diameter shall be three-fourths the diameter of the spike and drilled to a depth that is one-half the length of the spike.
3.10 GATE ASSEMBLY
Provide standard metal gate assemblies, with fittings and hardware necessary for complete installation.
SECTION 32 31 26 Page 31
SECTION 33 40 00
STORM DRAINAGE UTILITIES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A760/A760M (2015) Standard Specification for Corrugated Steel Pipe, Metallic-Coated for Sewers and Drains
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Corrugated Steel Pipe ; G
PART 2 PRODUCTS
2.1 CORRUGATED STEEL PIPE
ASTM A760/A760M , aluminum-zinc alloy (Type 2) coated pipe:
a. Type I (circular) pipe with helical 2-2/3 by 1/2 inch corrugations.
b. 14 gage (0.079 inches).
c. 18 inch diameter.
d. 36 foot length.
2.2 BEDDING MATERIAL
Bedding material shall meet the following gradation:
Sieve Size Percent passing
1 inch 100%
Number 4 20% - 65%
Number 200 0% - 10%
SECTION 33 40 00 Page 32
PART 3 EXECUTION
3.1 TRENCHING
The width of trenches at any point below the top of the pipe shall not be less than the outside diameter of the pipe plus 24 inches to permit thorough tamping of the bedding material under and around the pipe.
3.2 BEDDING
The bedding surface for the pipe shall provide a firm foundation of uniform density throughout the entire length of the pipe.
3.3 JOINTING
Joints are not allowed. Install the culvert(s) in one full piece.
3.4 BACKFILLING
After the pipe has been properly bedded, selected material from excavation or borrow, at a moisture content that will facilitate compaction, shall be placed along both sides of pipe in layers not exceeding 6 inches in compacted depth. The backfill shall be brought up evenly on both sides of pipe for the full length of pipe. The fill shall be thoroughly compacted under the haunches of the pipe. Each layer shall be thoroughly compacted with mechanical tampers or rammers.
3.4.1 Backfill Material
Backfill material, within 12 inches of the culvert, shall be free of rocks or particles larger than 2 inches in diameter.
SECTION 33 40 00 Page 33
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 11 00 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 PROJECT DESCRIPTION |
| 1.2 LOCATION |
| 1.3 WORK SCHEDULE |
| 1.4 DRIVEWAY PERMIT |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 12 00 - GOVERNMENT SUPPLIED MATERIAL |
| PART 1 GENERAL |
| 1.1 LOCATION |
| PART 2 PRODUCTS |
| 2.1 KIOSK |
| 2.2 ENTRANCE SIGNS |
PART 3 EXECUTION
| 01 20 00 - PRICE AND PAYMENT PROCEDURES |
| PART 1 GENERAL |
| 1.1 MOBILIZATION AND DEMOBILIZATION - AQUEDUCT NORTH |
| 1.1.1 Payment |
| 1.1.2 Unit of Measure |
| 1.2 SURVEY - STAKE OUT - AQUEDUCT NORTH |
| 1.2.1 Payment |
| 1.2.2 Unit of Measure |
| 1.3 CLEARING AND GRUBBING - AQUEDUCT NORTH |
| 1.3.1 Payment |
| 1.3.2 Unit of Measure |
| 1.4 DEMOLITION - AQUEDUCT NORTH |
| 1.4.1 Payment |
| 1.4.2 Unit of Measure |
| 1.5 SITE GRADING - AQUEDUCT NORTH |
| 1.5.1 Payment |
| 1.5.2 Unit of Measure |
| 1.6 AGGREGATE BASE COURSE - AQUEDUCT NORTH |
| 1.6.1 Payment |
| 1.6.2 Unit of Measure |
| 1.7 MOISTURE CONDITIONING AND COMPACTION - AQUEDUCT NORTH |
| 1.7.1 Payment |
| 1.7.2 Unit of Measure |
| 1.8 STEEL PARKING DELINEATOR - AQUEDUCT NORTH |
| 1.8.1 Payment |
| 1.8.2 Unit of Measure |
| 1.9 CONCRETE PARKING STOP - AQUEDUCT NORTH |
| 1.9.1 Payment |
| 1.9.2 Unit of Measure |
| 1.10 KIOSK Government Provided - AQUEDUCT NORTH |
| 1.10.1 Payment |
| 1.10.2 Unit of Measure |
| 1.11 WIRE FENCING - AQUEDUCT NORTH |
| 1.11.1 Payment |
| 1.11.2 Unit of Measure |
| 1.12 CORRUGATED METAL PIPE CULVERT - AQUEDUCT NORTH |
| 1.12.1 Unit of Measure |
| 1.13 ENTRANCE SIGN - AQUEDUCT NORTH |
| 1.13.1 Payment |
| 1.13.2 Unit of Measure |
| 1.14 GATE - ROAD - AQUEDUCT NORTH |
| 1.14.1 Payment |
| 1.14.2 Unit of Measure |
| 1.15 MOBILIZATION AND DEMOBILIZATION - AQUEDUCT SOUTH |
| 1.15.1 Payment |
| 1.15.2 Unit of Measure |
| 1.16 SURVEY - STAKE OUT - AQUEDUCT SOUTH |
| 1.16.1 Payment |
| 1.16.2 Unit of Measure |
| 1.17 CLEARING AND GRUBBING - AQUEDUCT SOUTH |
| 1.17.1 Payment |
| 1.17.2 Unit of Measure |
| 1.18 DEMOLITION - AQUEDUCT SOUTH |
| 1.18.1 Payment |
| 1.18.2 Unit of Measure |
| 1.19 SITE GRADING - AQUEDUCT SOUTH |
| 1.19.1 Payment |
| 1.19.2 Unit of Measure |
| 1.20 AGGREGATE BASE COURSE - AQUEDUCT SOUTH |
| 1.20.1 Payment |
| 1.20.2 Unit of Measure |
| 1.21 MOISTURE CONDITIONING AND COMPACTION - AQUEDUCT SOUTH |
| 1.21.1 Payment |
| 1.21.2 Unit of Measure |
| 1.22 CONCRETE PARKING STOP - AQUEDUCT SOUTH |
| 1.22.1 Payment |
| 1.22.2 Unit of Measure |
| 1.23 GATE - ROAD - AQUEDUCT SOUTH |
| 1.23.1 Payment |
| 1.23.2 Unit of Measure |
| 1.24 MOBILIZATION AND DEMOBILIZATION - TURTLE LAKE |
| 1.24.1 Payment |
| 1.24.2 Unit of Measure |
| 1.25 SURVEY - STAKE OUT - TURTLE LAKE |
| 1.25.1 Payment |
| 1.25.2 Unit of Measure |
| 1.26 CLEARING AND GRUBBING - TURTLE LAKE |
| 1.26.1 Payment |
| 1.26.2 Unit of Measure |
| 1.27 SITE GRADING - TURTLE LAKE |
| 1.27.1 Payment |
| 1.27.2 Unit of Measure |
| 1.28 AGGREGATE BASE COURSE - TURTLE LAKE |
| 1.28.1 Payment |
| 1.28.2 Unit of Measure |
| 1.29 MOISTURE CONDITIONING AND COMPACTION - TURTLE LAKE |
| 1.29.1 Payment |
| 1.29.2 Unit of Measure |
| 1.30 CONCRETE PARKING STOP - TURTLE LAKE |
| 1.30.1 Payment |
| 1.30.2 Unit of Measure |
| 1.31 KIOSK - TURTLE LAKE |
| 1.31.1 Payment |
| 1.31.2 Unit of Measure |
| 1.32 CORRUGATED METAL PIPE CULVERT - TURTLE LAKE |
| 1.32.1 Unit of Measure |
| 1.33 ENTRANCE SIGN - TURTLE LAKE |
| 1.33.1 Payment |
| 1.33.2 Unit of Measure |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 32 01 - PROJECT SCHEDULE |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS |
| 3.2.1 Level of Detail Required |
| 3.2.2 Mandatory Tasks |
| 3.2.3 Government Activities |
| 3.3 WEEKLY PROGRESS MEETINGS |
| 3.4 FAILURE TO ACHIEVE PROGRESS |
| 3.4.1 Failure to Perform |
| 3.4.2 Recovery Schedule |
| 01 33 00 - SUBMITTAL PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 INFORMATION ONLY SUBMITTALS |
| 1.3 GOVERNMENT APPROVING AUTHORITY |
| 1.3.1 Review Notations |
| 1.4 DISAPPROVED SUBMITTALS |
| 1.5 APPROVED SUBMITTALS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 57 60 - SUPPLEMENTAL ENVIRONMENTAL CONTROLS |
| PART 1 GENERAL |
| 1.1 DEFINITIONS |
| 1.2 SUBMITTALS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 EROSION CONTROL |
| 3.2 FIRE PREVENTION |
| 3.3 EQUIPMENT CLEANING AND MAINTENANCE |
| 3.4 SPILL PREVENTION |
| 3.5 WASTE CONTROL |
| DIVISION 03 - CONCRETE |
| 03 30 00 - CAST-IN-PLACE CONCRETE |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| PART 2 PRODUCTS |
| 2.1 CONCRETE |
| PART 3 EXECUTION |
| 3.1 PREPACKAGED CONCRETE MIXTURE |
| 3.2 FOOTINGS |
| 3.3 CONCRETE CONSOLIDATION |
| DIVISION 05 - METALS |
| 05 50 12 - STEEL GATE - ROAD |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| PART 2 PRODUCTS |
| 2.1 STEEL |
| 2.2 SIGNS |
| 2.3 CONCRETE |
| PART 3 EXECUTION |
| 3.1 FABRICATION, WELDING, AND INSTALLATION |
| 3.2 PAINT |
| 3.3 SIGNS |
| DIVISION 09 - FINISHES |
| 09 90 10 - PAINTING |
| PART 1 GENERAL |
| 1.1 DESCRIPTION OF WORK |
| PART 2 PRODUCTS |
| 2.1 PRIMER |
| 2.2 PAINT |
| 2.3 PAINT COLOR |
| PART 3 EXECUTION |
| 3.1 SURFACE PREPARATION |
| 3.2 APPLICATION |
| DIVISION 12 - FURNISHINGS |
| 12 93 00 - SITE FURNISHINGS |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| PART 2 PRODUCTS |
| 2.1 STEEL PARKING DELINEATORS |
| 2.2 KIOSK |
| 2.3 NO CAMPING SIGN |
| 2.4 CONCRETE PARKING STOPS |
| 2.5 CONCRETE |
| PART 3 EXECUTION |
| 3.1 STEEL PARKING DELINEATORS |
| 3.2 ENTRANCE SIGN |
| 3.3 NO CAMPING SIGNS |
| 3.4 KIOSK |
| 3.5 CONCRETE PARKING STOPS |
| DIVISION 31 - EARTHWORK |
| 31 00 00 - EARTHWORK |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| PART 2 PRODUCTS |
| 2.1 AGGREGATE BASE COURSE |
| PART 3 EXECUTION |
| 3.1 UNDERGROUND UTILITIES |
| 3.2 GENERAL EXCAVATION |
| 3.3 GROUND SURFACE PREPARATION |
| 3.4 AGGREGATE PLACEMENT LOCATIONS |
| 3.4.1 Subgrade |
| 3.4.2 Subgrade Compaction |
| 3.4.3 Aggregate Base Course |
| 3.4.4 Aggregate Base Course Compaction |
| 3.5 AGGREGATE WEIGHT TICKETS |
| 3.6 EXCESS MATERIAL DISPOSAL |
| 3.7 FINISHING |
| 31 11 00 - CLEARING AND GRUBBING |
| PART 1 GENERAL |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 SURVEY STAKE OUT |
| 3.2 CLEARING AND GRUBBING LIMITS |
| 3.3 PROTECTION |
| 3.4 CLEARING |
| 3.5 GRUBBING |
| 3.6 DISPOSAL OF CLEARING AND GRUBBING VEGETATION |
| DIVISION 32 - EXTERIOR IMPROVEMENTS |
| 32 31 26 - WIRE FENCES AND GATES |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| PART 2 PRODUCTS |
| 2.1 BARBED WIRE |
| 2.2 BARBLESS WIRE |
| 2.3 WOOD POSTS AND BRACES - PANELS AND GATES |
| 2.4 WOOD FENCE POSTS |
| 2.5 STEEL FENCE POSTS |
| 2.6 STEEL TUBE GATE |
| PART 3 EXECUTION |
| 3.1 ALIGNMENT |
| 3.2 CLEARING |
| 3.3 END PANELS, CORNER PANELS, AND GATE PANELS |
| 3.4 WOOD LINE POSTS |
| 3.4.1 Wood Line Post Frequency |
| 3.5 STEEL LINE POSTS |
| 3.6 WIRE |
| 3.7 WIRE CLIPS |
| 3.8 BRACE WIRE |
| 3.9 SPIKING |
| 3.10 GATE ASSEMBLY |
| DIVISION 33 - UTILITIES |
| 33 40 00 - STORM DRAINAGE UTILITIES |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| PART 2 PRODUCTS |
| 2.1 CORRUGATED STEEL PIPE |
| 2.2 BEDDING MATERIAL |
| PART 3 EXECUTION |
| 3.1 TRENCHING |
| 3.2 BEDDING |
| 3.3 JOINTING |
| 3.4 BACKFILLING |
| 3.4.1 Backfill Material |