United States Department of the Interior Bureau of Land Management
Tres Rios Field Office
Summit Trailhead
SPECIFICATIONS
Summit Trailhead SUMMIT
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 79 00 AERIAL (DRONE) PHOTOGRAPHS
DI VI SI ON 05 - METALS
05 50 12 STEEL GATE - ROAD
DI VI SI ON 12 - FURNI SHI NGS
12 93 00 SITE FURNISHINGS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 31 26 WIRE FENCES AND GATES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
The project is the construction of a new trailhead. The work includes, but is not limited to; clearing and grubbing, earthwork, road and parking area construction, fence construction, sign and kiosk construction, gate construction, and parking delineator construction.
1.2 LOCATION
The project is located on public land, off state highway 184, between Dolores and Manco, CO. From Dolores, CO head southeast on State highway 184, travel approximately 8 miles to Country Road 35.6. Head south on
County Road 35.6 until the road turns 90 degrees to the east. From there, the project is located to the southwest, across the pipeline right of way.
Latitude: 37.399496° N
LLongitude: -108.396773° W
1.3 WORK SCHEDULE
Project shall be completed within 120 days of the Notice to Proceed. Work will not be allowed December 1st through April 30th in order to protect big game critical winter range habitat. Work shall occur Monday - Friday, excluding federal holidays.
1.4 ORDER OF WORK
The contractor shall stakeout the roads and parking areas as detailed on the drawings. The design intent is to minimize damage to existing vegetation. The Contracting Officer's Representative will review the layout as staked and may make minor modifications to the layout in order to minimize the damage to existing vegetation. The contractor shall receive approval of the stakeout prior to construction.
1.5 GOVERNMENT SUPPLIED MATERIAL
Aggregate for this project is available without cost to the contractor. The aggregate is located at the
Montezuma County Mancos Quarry, off state highway 42, northeast of Mancos, Colorado. Approximately 12 miles from the project site. Coordinate with the Contracting Officer's Representative prior to picking up the aggregate.
The contractor is responsible for loading the aggregate at the quarry, hauling, placing, and compacting.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 11 00 Page 3
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
Payment items for the work of this contract for which contract payments will be made are listed in the
SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job are included in the listed job item most closely associated with the work involved.
The price and payment made for each item listed constitutes full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1 MOBILIZATION AND DEMOBILIZATION
1.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization.
When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
When 15% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 8% of the original Contract amount, whichever is lesser, will be paid.
Upon completion of work for the project, payment of the amount bid for mobilization in excess of 8% of the original Contract amount, will be paid.
1.1.2 Unit of Measure
Unit of measure: job.
1.2 DEMOLITION
1.2.1 Payment
Payment will be made for all costs associated with demolition of the existing fence. Including transportation and disposal.
1.2.2 Unit of Measure
Unit of measure: job.
SECTION 01 20 00 Page 4
1.3 CLEARING AND GRUBBING
1.3.1 Payment
Payment will be made for all costs associated with clearing and grubbing. Including transportation and disposal of materials.
1.3.2 Unit of Measure
Unit of measure: Job.
1.4 SITE GRADING
1.4.1 Payment
Payment will be made for all costs associated with grading and compacting the roads, parking areas and ancillary features.
1.4.2 Unit of Measure
Unit of measure: Job.
1.5 AGGREGATE
1.5.1 Payment
Payment will be made for all costs associated with providing aggregate surfacing. Including preparation, transportation, placement, and compaction.
1.5.2 Unit of Measure
Unit of measure: square yard in place
1.6 STEEL TRAILER PARKING DELINEATOR - 30 FOOT LENGTH
1.6.1 Payment
Payment will be made for all costs associated with providing 30 foot steel trailer parking delineators.
1.6.2 Unit of Measure
Unit of measure: Each.
SECTION 01 20 00 Page 5
1.7 STEEL TRAILER PARKING DELINEATOR - 20 FOOT LENGTH
1.7.1 Payment
Payment will be made for all costs associated with providing 20 foot steel trailer parking delineators.
1.7.2 Unit of Measure
Unit of measure: Each.
1.8 WIRE FENCING
1.8.1 Payment
Payment will be made for all costs associated with providing wire fencing. Including the access gate and connecting the new fence where it intersects the existing fence.
1.8.2 Unit of Measure
Unit of measure: Job.
1.9 KIOSK
1.9.1 Payment
Payment will be made for all costs associated with providing a kiosk.
1.9.2 Unit of Measure
Unit of measure: Each.
1.10 ENTRANCE SIGN
1.10.1 Payment
Payment will be made for all costs associated with constructing an entrance sign.
1.10.2 Unit of Measure
Unit of measure: Each.
1.11 NO CAMPING SIGN
1.11.1 Payment
Payment will be made for all costs associated with providing no camping signs.
SECTION 01 20 00 Page 6
1.11.2 Unit of Measure
Unit of measure: Each.
1.12 EQUESTRIAN PARKING SIGN
1.12.1 Payment
Payment will be made for all costs associated with providing equestrian parking signs.
1.12.2 Unit of Measure
Unit of measure: Each.
1.13 GATE - ROAD
1.13.1 Payment
Payment will be made for all costs associated with providing a road gate.
1.13.2 Unit of Measure
Unit of measure: Each.
1.14 AERIAL (DRONE) PHOTOGRAPHS
1.14.1 Payment
Payment will be made for all costs associated with providing aerial (drone) photographs.
1.14.2 Unit of Measure
Unit of measure: Job.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 7
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule; G
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution.
3.2.2 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of submittals.
b. Long procurement activities
c. Contractor's pre-final inspection.
d. Government's pre-final inspection.
e. Final inspection.
SECTION 01 32 01 Page 8
3.2.3 Government Activities
Include Government activities that could impact progress. These activities include, but are not limited to:
Government inspections of work, Government approval of submittals.
3.3 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.
3.4 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
3.4.1 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the
Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default
(Fixed-Price Construction), and other contract provisions.
3.4.2 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15
Schedules for Construction Contracts.
SECTION 01 32 01 Page 9
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only.
1.2 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer's
Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the
Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the
Government.
1.3 GOVERNMENT APPROVING AUTHORITY
The Contracting Officer's Representative will:
a. Note the date on which the submittal was received.
b. Review submittals for approval within 10 days of receipt.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer's Representative and one copy of the submittal will be returned to the
Contractor.
1.3.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete.
SECTION 01 33 00 Page 10
A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed.
Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the
Government. This applies only to "information-only submittals" as previously defined.
1.4 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer's Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting
Officer.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.5 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 11
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 1 PAGES
Summit Trailhead
01 32 01 SD-01 Preconstruction Submittals
GInitial Project Schedule
12 93 00 SD-03 Product Data
2.2 GKiosk
2.3 GEquestrian Parking Sign
2.4 GNo Camping Sign
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SECTION 01 79 00
AERIAL (DRONE) PHOTOGRAPHS
PART 1 GENERAL
Provide all materials and labor necessary to obtain aerial photographs taken less than 400 feet from the ground.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Provide aerial (drone) photographs of the project after all other work is complete. Take photos from different perspectives, and include all work in the photographs. Provide aerial (drone) photographs on a portable hard
(flash) drive. Portable hard (flash) drive shall become property of the BLM.
SECTION 01 79 00 Page 12
SECTION 05 50 12
STEEL GATE - ROAD
PART 1 GENERAL
Provide a steel gate as shown on the plans and as specified below.
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and
Hot-Dipped, Zinc-Coated, Welded and Seamless
MASTER PAINTERS INSTITUTE (MPI)
MPI 23 (2012) Primer, Metal, Surface Tolerant
MPI 94 (2012) Alkyd, Exterior, Semi-Gloss (MPI Gloss Level 5)
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC SP 1 (2015) Solvent Cleaning
PART 2 PRODUCTS
2.1 STEEL
Steel shall pipe shall be in accordance with ASTM A53/A53M, and manufactured in the United States.
2.2 PAINT
Metal Primer MPI 23
Intermediate Coat MPI 94
Top Coat MPI 94
Dry Film Thickness 5.25 mils
SECTION 05 50 12 Page 13
Color Brown
2.3 SIGNS
Signs shall comply with the Manual of Uniform Traffic Control Devices (MUTCD). OM4-1 signs shall be 18" x
18". OM2-2V signs shall be 12" x 6".
2.4 CONCRETE
Concrete shall have a minimum compressive strength of 3,000 psi.
PART 3 EXECUTION
3.1 FABRICATION, WELDING, AND INSTALLATION
Verify all dimensions prior to fabrication. Perform welding in accordance with AWS D1.1/D1.1M. Field verify post locations prior to setting. Set posts vertically in concrete piers. Fill posts with concrete.
3.2 PAINT
Prepare surfaces for paint in accordance with SSPC SP 1. Apply a primer coat, intermediate coat, and finish coat of paint.
3.3 SIGNS
Firmly secure signs to the gate and gate posts. Provide galvanized or stainless steel hardware.
SECTION 05 50 12 Page 14
SECTION 12 93 00
SITE FURNISHINGS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Kiosk; G
Equestrian Parking Sign; G
No Camping Sign; G
PART 2 PRODUCTS
2.1 STEEL PARKING DELINEATORS
Steel parking delineators shall be schedule 40 steel pipe. Used pipe may be supplied; however pipe must be clean of excessive oil, grease, rust, etc. Pipe must be straight and have no dents, bends, or obvious defects.
2.2 KIOSK
Kiosk shall be as manufactured by "Wood Product Signs". Kiosk features include:
Custom 9' Utah Roof Kit with brown metal roof
(3) 6" x 6" x 10'4" Metal Posts, painted brown
36" x 48" - Bulletin Boards with routed pocket for digital graphic
33" x 32" - Digital Graphic inlay
36" x 48" - Bulletin Boards with routed pocket for corkboard
32" x 8.5" - Corkboard inlay
The bulletin board routed text and digital graphics will be provided after BLM acceptance of the submittal and should not impact the product cost or installation.
2.3 EQUESTRIAN PARKING SIGN
Equestrian parking signs shall be as manufactured by "Rock Art Signs", sign number 93-1043. 18"x24"x ¾", HDPE routed plastic sign.
2.4 NO CAMPING SIGN
The "no camping" sign shall be as manufactured by "Rock Art Signs", sign number 10-146-8. 8" x 8" x 0.08"
Aluminum sign, with brown background and red "prohibited line".
SECTION 12 93 00 Page 15
PART 3 EXECUTION
3.1 STEEL PARKING DELINEATORS
Steel parking delineators shall be installed as shown on the drawings. Tops of the steel parking delineators shall be set three inches above the finished grade of the aggregate surfacing.
3.2 ENTRANCE SIGN
The entrance sign and mounting hardware will be Government provided. Install the sign with the mounting hardware provided. A picture of the mounting hardware is on the plans for reference.
3.3 EQUESTRIAN PARKING AND NO CAMPING SIGNS
Install the sign posts plumb as shown on the drawings. Firmly secure signs to the posts using galvanized or stainless steel hardware.
3.4 KIOSK
Install the kiosk posts plumb as shown on the drawings. Construct the kiosk according to the manufacturer's directions.
SECTION 12 93 00 Page 16
SECTION 31 00 00
EARTHWORK
PART 1 GENERAL
Not Used.
PART 2 PRODUCTS
2.1 AGGREGATE
See Section 01 11 00 for aggregate.
PART 3 EXECUTION
3.1 UNDERGROUND UTILITIES
There are underground utilities in the work area. The Contractor is responsible for locating underground utilities prior to construction. Notify the Contracting Officer's Representative if any utilities will be impacted by the construction.
3.2 GENERAL EXCAVATION
Perform excavation of every type of material encountered to the lines, grades, and elevations indicated and as specified. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times.
3.3 GROUND SURFACE PREPARATION
Clear and grub in accordance with section 31 11 00 . Do not perform construction when surfaces are frozen or muddy. Prepare the subgrade to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Shape subgrade to drain.
3.4 ROADS AND PARKING AREAS
3.4.1 Subgrade
Contractor shall prepare the subgrade to the lines and grades shown on the plans.
3.4.2 Subgrade Compaction
Moisten material as necessary to achieve compaction. Compact the subgrade by operating compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.
3.4.3 Aggregate
The Contractor shall receive approval of the subgrade prior to placing aggregate. Place aggregate to the lines and grades shown on the plans.
SECTION 31 00 00 Page 17
3.4.4 Aggregate - Compaction
Moisten material as necessary to achieve compaction. Compact the aggregate by operating compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.
3.5 FINISHING
Finish the surfaces to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.2 foot of the grades and elevations indicated. Finish surfaces in a manner that will result in effective drainage, regardless of tolerance.
SECTION 31 00 00 Page 18
SECTION 31 11 00
CLEARING AND GRUBBING
PART 1 GENERAL
Not Used.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 CLEARING AND GRUBBING LIMITS
Clearing and grubbing limits shall be within the road and parking areas, including ditches.
3.2 PROTECTION
Prior to clearing and grubbing, the contractor shall stake out the roads and parking areas as detailed on the drawings. The design intent is to minimize damage to existing vegetation. The Contracting Officer's
Representative will review the layout as staked and may make minor modifications to the layout in order to minimize the damage to existing vegetation. The contractor shall receive approval of the stakeout prior to construction.
Protect trees and vegetation from damage incident to clearing, grubbing, and construction operations.
3.3 CLEARING
Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Trees, stumps, roots, brush, and other vegetation in areas to be cleared shall be cut off flush with or below the original ground surface.
3.4 GRUBBING
Grubbing consists of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas. Remove material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, to a depth of not less than 12 inches below the original surface level of the ground in the area of new road construction. Fill depressions made by grubbing with suitable material and compact to make the surface conform with the original adjacent surface of the ground.
3.5 DISPOSAL OF MATERIALS
Logs, stumps, roots, brush, rotten wood, and other organic material resulting from the clearing and grubbing operations, shall be uniformly scattered on site in piles less than 12 inches off the ground.
SECTION 31 11 00 Page 19
SECTION 32 31 26
WIRE FENCES AND GATES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
AWPA U1 (2017) Use Category System: User Specification for Treated
Wood
ASTM INTERNATIONAL (ASTM)
ASTM A121 (2013) Standard Specification for Metallic-Coated Carbon Steel
Barbed Wire
ASTM A702 (2013) Standard Specification for Steel Fence Posts and
Assemblies, Hot Wrought
PART 2 PRODUCTS
2.1 BARBED WIRE
Barbed wire shall be a strand of two (2) 12-1/2-gauge galvanized wires twisted together with 2-point barbs of
14-gauge wire spaced 4 inches apart. Wire and barbs shall be zinc-coated steel, with a Class 1 zinc coating as per ASTM A121. The minimum breaking strength of each wire shall be 950-lb force. The barbed wire shall conform to ASTM A121
2.2 BARBLESS WIRE
Barbless wire shall be a strand of two (2) 12-1/2-gauge, galvanized wires twisted together. Wire shall be a Class
1 zinc coating as per ASTM A121. The minimum breaking strength of each wire shall be 950-lb force. The barbless wire shall conform to ASTM A121.
2.3 WOOD POSTS AND BRACES - PANELS AND GATES
Wood posts and braces used for the panels and gates shall be sound single-stem members of round cross section and have 5 inches minimum diameter at the small end. Provide posts free of ring shake, season cracks more than 1/4 inch wide, splits in the end, and unsound knots. Treat posts in accordance with AWPA U1.
Honey Locust, western red cedar (full stem with bark removed), Juniper, Osage Orange, and White Oak are acceptable without treatment.
2.4 WOOD FENCE POSTS
Wood fence posts shall be sound single-stem members of round cross section and have 4 inches minimum diameter at the small end. Provide posts free of ring shake, season cracks more than 1/4 inch wide, splits in the
SECTION 32 31 26 Page 20 end, and unsound knots. Treat posts in accordance with AWPA U1. Honey Locust, western red cedar (full stem with bark removed), Juniper, Osage Orange, and White Oak are acceptable without treatment. .
2.5 STEEL FENCE POSTS
Steel fence posts shall conform to ASTM A702; green with white or silver top "T" bar type, with a welded or riveted anchor plate. Furnish with clip-type wire fasteners (punched tabs for fastening wires are not acceptable). Steel posts shall be manufactured from wrought, rail or new billet steel, shall have a minimum weight of 1.33 pounds per linear foot. The anchor plates shall weigh a minimum of 0.67 pounds and shall have a minimum area of 18 square inches.
2.6 STEEL TUBE GATE
Steel tube gate shall welded pipe with minimum pipe diameter of 1-1/2 inches and be factory painted. Provide hinges, latches, and other hardware as required for the operation of the gate.
PART 3 EXECUTION
3.1 ALIGNMENT
The Contractor shall layout and stake the fence alignment for approval by the Contracting Officer's
Representative. The fence and gate locations shall generally match the layout shown on the plans, with deviations for constructability.
3.2 CLEARING
Clearing shall be limited to cutting of brush in the fence line alignment. Maximum clearing width is 6 feet on each side of the fence line. Minimize disturbance to existing vegetation.
3.3 END PANELS, CORNER PANELS, AND GATE PANELS
Construct as shown on the drawings. End panels shall be constructed at the ends of the fence, corner panels at changes in fence alignment. Gate panels shall be constructed at the gate.
Set posts plumb in dug or drilled holes. Post holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Place backfill in layers of 9 inches or less, moistened to optimum condition, and compacted with hand tampers.
3.4 WOOD LINE POSTS
Set posts plumb in dug or drilled holes. Post holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Place backfill in layers of 9 inches or less, moistened to optimum condition, and compacted with hand tampers.
3.4.1 Wood Line Post Frequency
Every third line post shall be a wood post.
3.5 STEEL LINE POSTS
Posts shall be driven plumb.
SECTION 32 31 26 Page 21
3.6 WIRE
Wire is properly stretched when it is springy to the touch. Stretch tightly and staple to wood posts or securely attach to steel posts with standard manufactured wire clips. Drive staples into wood until the staple comes in contact with the wire against the post, but not so tight as to crimp the wire or prevent free movement of the wire between the post and the staple. Do not drive staples parallel to the grain of the wood.
3.7 WIRE CLIPS
Wire clips shall be used on every wire at steel post locations. Secure wire to steel posts by bending clip ends over or around wire, crimping ends to secure wire on both sides of the post, but not so tight as to prevent free movement of the wire through the clip. Each side of the clip shall be twisted around the wire and back parallel to the clip itself.
3.8 BRACE WIRE
Shall be double looped in a crisscross fashion, twisted tight with either four plies of 9-gauge smooth wire or 8 plies of 12-1/2-gauge wires. Leave one end of the stick long enough to fasten behind the horizontal brace to prevent wire from unwinding.
3.9 SPIKING
Predrilled lead holes shall be used. The hole diameter shall be three-fourths the diameter of the spike and drilled to a depth that is one-half the length of the spike.
3.10 GATE ASSEMBLY
Provide standard metal gate assemblies, with fittings and hardware necessary for complete installation.
SECTION 32 31 26 Page 22