A04_SOW.pdf
PDF 160 KB Posted
- Attached to
- ND-FWS KULM WMD-GEOTHERMAL HVAC SYSTEM
- Solicitation number
- 140F1B23R0006
About this file
This performance work statement outlines the requirements for installing an additional geothermal heat pump system at the Kulm Wetland Management District maintenance building in Kulm, North Dakota. The contractor will provide and install a 10-ton water-to-water geothermal heat pump on the mezzanine level tied into the existing piping in the mechanical room, install 12 new geothermal heat exchange loops to the east of the existing wellfield, and run insulated piping from the wellfield to the mezzanine in an enclosed sheet metal shelter matching the building. The contractor must test the completed system, use licensed workers, adhere to all applicable building and energy codes, protect existing facilities, perform load calculations, and provide training and manuals upon completion. The period of performance is 120 days from notice to proceed.
The related federal contract opportunity is solicitation number 140F1B23R0006 from the Department of the Interior Fish and Wildlife Service to install the geothermal HVAC system at the Kulm Wetland Management District in Kulm, North Dakota as outlined in the performance work statement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B03_Wage_Determinations.pdf | ||
| A06_Drawings.pdf | ||
| Provisions___Clauses_8_4_23.pdf | ||
| Sol_140F1B23R0006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
Installation of New Geo-Thermal Heat Pump – Maintenance Shop
Kulm Wetland Management District, Kulm, North Dakota
1.0 Introduction and Overview
Kulm Wetland Management District was established in July 1971. It is located in the Prairie Pothole Region of North America--a grassland landscape formed by glaciers and marked by numerous wetlands called potholes. This area extends from Canada and down through Montana, the Dakotas, Minnesota, and into northern Iowa. This area is sometimes referred to as "the Duck Factory" because over half of the continent's waterfowl are hatched and raised here. It provides the most productive breeding habitat in North America for hundreds of ducks, geese, and other migratory bird species.
The Maintenance Building (Asset# 35600100) completed in 2021 is a 4,000 square foot pre-engineered metal building with a 6-ton geothermal heat pump. This current system is unable to adequately maintain a comfortable temperature during the winter months resulting in the need for the auxiliary electric heat to operate. This project incorporates installation of an additional 10-ton water to water geothermal system to be installed on the mezzanine level of the Maintenance Building and tied into the existing piping in the mechanical room (Re: Drawings).
1.1 Scope of Work
The contractor shall provide and install an additional 10-ton water to water geothermal system to a heat pump. The heat pump shall be installed on the mezzanine and tied into the existing piping in the mechanical room, (12) new geothermal heat exchange loops to the east of the existing wellfield and install insulated piping from the wellfield to the mezzanine will be run outside of the building to an enclosure constructed by the contractor. The enclosure shall be constructed of sheet metal closely matching the color and look of the existing building. The existing geothermal system will have the valves turned off to the in-floor heating but remain operational so that adjustments to the valves can be made as needed to maintain comfort levels in the building. The existing unit will still provide forced air heating and cooling on demand as needed. Contractor shall also replace the non-functioning hydrozone control panel with similar panel.
1. The completed system shall be tested for proper operation upon completion of installation. The new HVAC system shall communicate with all the air handlers, pump, and valves, etc. seamlessly and efficiently, providing staff a comfortable work environment year-round.
2. The contractor shall be licensed in the state of South Dakota. All work and testing shall be in accordance with the International Building Code (IBC 2021), International Mechanical Code (IMC 2021), and International Energy Conservation Code (IECC 2018). Duct work shall be performed in accordance with NFPA90B. Electrical work shall be in accordance with NFPA National Electrical Code 2017. The contractor shall inspect buildings, perform, and submit load calculations (ACCA Manual N) and confirm that the specified system will be efficient and provide adequate capacity.
3. The contractor shall maintain and protect existing facilities from damage during all work.
· Protect building structure and interior from weather and water leakage and damage.
· Locate, identify, shutoff or disconnect utility services prior as needed.
· Notify the facility manager in advance of power and/or water disconnections
4. The contractor shall inspect buildings, perform, and submit load calculations (ACCA manual N) and confirm that the specified system will be efficient and provide adequate capacity
5. All system components shall be from the same manufacturer, including controls.
1.2 Period of Performance
The work shall be completed in 120 days from notice to proceed.
1.3 Project Safety
The Contractor shall be responsible for strict compliance with all provisions of Occupational Safety and Health Administration (OSHA) requirements 29 CFR 1910 and 29CFR 1926 during performance of the work.
2.0 Project Requirements
A. All work will adhere to local building codes. All work and materials shall be in compliance with all applicable building codes, and the applicable performance standards:
1. American Society of Mechanical Engineers (ASME)
2. American Society for Testing Materials (ASTM)
3. National Electric Code (NEC), National Energy Conservation Code (NECC), International Building Code (IBC), & International Mechanical Code (IMC).
4. Air-Conditioning, Heating, and Refrigeration Institute (AHRI)
5. American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE)
B. Field Measurements:
On site field investigation and measurements shall be made prior to procurement of the new HVAC system, to ensure that the proposed mechanical equipment will fit the site of the installation.
C. HVAC Equipment and appurtenant work:
The Contractor shall furnish and install all required equipment to include piping, valves, electrical wiring, switches, and appurtenant items as required for a fully functional energy efficient (95% minimum) HVAC system.
D. HVAC equipment shall meet the following performance requirements:
1. Provide and install a new HVAC system for heating, ventilation, and cooling. The HVAC system shall be in compliance with the following applicable performance standards: Air-Conditioning, Heating, and Refrigeration Institute (AHRI), and the American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE).
2. The Contractor shall provide all required adjustments or components so the HVAC unit will properly function when installed. Contractor shall replace the insulation that has been removed.
Provide and install all incidental materials required to install the HVAC unit, including piping, valves, regulators, electrical wiring, switches, connections, drain pan, air filters, and compatible thermostats.
3. The system shall be a minimum 90% energy efficient Energy Star rated.
4. Upon completion of the installation, the HVAC system shall be complete and fully operational.
Perform startup operations with the presence of Refuge personnel.
5. The installer shall provide training to refuge personnel on operation and maintenance needs of the system. O&M manuals shall be provided to the refuge personnel.
6. All workmanship and function of the system shall be warranted for one year. All equipment warranties shall be provided to the Refuge personnel upon completion of the work.
7. Contractor shall provide a one-year maintenance contract covering system components and operability.
8. New geothermal pump shall have a 10-year manufacturer’s warranty.
9. Ground loop shall have a 20-year manufacturer’s warranty.
E. HVAC system installation requirements:
1. All ductwork, equipment, and system installation shall be performed per industry standards and NECC code requirements.
2. Any installation through walls or ceilings shall be patched and painted by the contractor to match existing.
3.0 Material Submittals
A. Material submittals consisting of material and manufacturer's product information shall be provided to Contracting Officer Representative (COR) for approval prior to any materials are purchased on this project.
4.0 End Results/Deliverables
A. Provide and install all materials required to install the additional HVAC system. Upon completion of the installation, the HVAC system shall be fully balanced and fully operational. Provide all Operations and Maintenance Manuals to the Refuge, including warranty information on the parts and equipment.
B. Upon completion of the project, all work areas shall be free of rubbish and debris. All HVAC equipment will be removed, disposed, and recycled per federal and state laws.
C. Contractor shall train refuge staff on proper operation and maintenance of equipment.
5.0 Special considerations
1. Technical / government liaison for this contract is the USFWS Facilities Manager, Wayne Henderson located at the HQ building, 701-647-2866. Normal working hours for Facility Staff are from 7:00 AM to 3:30 PM Monday through Friday except for Government holidays and special events.
2. Contractor allowable work hours are 7AM to 6:00 PM Monday through Friday. Weekend work is acceptable with prior arrangements with onsite staff from 8:00 am to 6:00 pm.
3. Building shall be occupied by refuge personnel through-out the contract period. Coordination of work with refuge staff will be necessary.
4. Utility Companies that provide service are:
Water – Southwest Water
Electric – Dakota Valley Electric Co-Op
Natural Gas – None
5. Water and power are available for the contractor to use during the project.
6. Restroom facilities are available onsite for the contractor to use during the project.
7. Onsite parking is available at the jobsite for the contractor to use during the project.
8. Laydown area is available onsite and will be coordinated between refuge staff and the contractor.
| Kulm Wetland Management District was established in July 1971. It is located in the Prairie Pothole Region of North America--a grassland landscape formed by glaciers and marked by numerous wetlands called potholes. This area extends from Canada and do... |
| The Maintenance Building (Asset# 35600100) completed in 2021 is a 4,000 square foot pre-engineered metal building with a 6-ton geothermal heat pump. This current system is unable to adequately maintain a comfortable temperature during the winter mont... |
| The contractor shall provide and install an additional 10-ton water to water geothermal system to a heat pump. The heat pump shall be installed on the mezzanine and tied into the existing piping in the mechanical room, (12) new geothermal heat exchan... |
| 1. The completed system shall be tested for proper operation upon completion of installation. The new HVAC system shall communicate with all the air handlers, pump, and valves, etc. seamlessly and efficiently, providing staff a comfortable work envir... |
| 2. The contractor shall be licensed in the state of South Dakota. All work and testing shall be in accordance with the International Building Code (IBC 2021), International Mechanical Code (IMC 2021), and International Energy Conservation Code (IECC ... |
| 3. The contractor shall maintain and protect existing facilities from damage during all work. |
| 8. New geothermal pump shall have a 10-year manufacturer’s warranty. |
| 9. Ground loop shall have a 20-year manufacturer’s warranty. |