Statement of Work Paint Beale House: North & West Sides

PMIS: 258378

July 23, 2020 Page 2 of 32

Figure 1 West Side Main Building

Figure 2 North Side Addition & Porch

Figure 3 West Side Addition & North Side Main Building Screened in Porch Behind Bushes

Figure 4 Screened in Porch & Steps

June 26, 2020

SECTION 011000 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project: Paint Beale House North & West Sides

Park Alpha Code: ADAM United States Department of the Interior, National Park Service Adams National Historical Park 181 Adams Street Quincy, MA 02169

Description: Prepare prime and paint the north and west sides of the Beale House, from the foundation to the gutters. consisting of approximately 3,360 square feet of wooden clapboard siding with associated architectural details, gutters and trim, including, 20 windows, 2 doors, Screened in porch. 2 screen doors, and 16 pairs of wooden louvered shutters prepared and painted. The total square footage will be prepared to accept primer and finish paint according to The United States Secretary of the Interior's Standards for the Treatment of Historic Properties.

B. Project Location: The Project site is located at 181 Adams Street; Quincy, MA 02169

1.2 WORK COVERED BY THE CONTRACT:

A. The Work of this Contract shall be carried out as indicated and as specified herein and as required by field conditions and applicable regulatory requirements. In general the work consists of, but may not be limited to the following:

1. Painting

a. All materials, equipment, labor and supervision necessary for: Exterior Painting of the Beale House North and West Sides

2. The surface preparation and painting of exterior painted surfaces, such as:

1. Clapboard (2,200 sqft)

2. Horizontal and vertical trim (1,160 sqft)

3. Porches and steps (2)

4. Doors and door trim (2)

5. Window trim (20ea.)

6. Shutters (20 pairs)

7. Screen Door (1)

8. Porch screens and door (11)

9. Removal of exterior storm windows and painting of window sashes is NOT included in this contract.

B. Work shall be completed as specified in the Technical Specifications, which is this Project Manual, and as required by all applicable prevailing codes, including but not limited to The International Building Code, latest edition, and other construction codes, as applicable, referenced therein, as reasonably practicable, as determined by the Government. However preserving the Historic Fabric of the Structure is paramount. See Historic Nature of Project, Project Site and Surrounds below this Section. Job conditions may also determine Work.

C. In the event of a discrepancy between the requirements of the Technical Specifications and/or

Drawings and the Federal Acquisition Regulations (FAR), the FAR shall govern. The FAR can be accessed on the internet: https://www.acquisition.gov/far

D. In case of a discrepancy either in the figures in the Drawings or in the Specifications, the matter shall be promptly submitted by Contractor to the Contracting Officer (CO), who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at his own risk and expense with no additional time and/or expense to the Government.

1.3 SITE EXAMINATION

A. A pre-proposal conference will be conducted on site, date to be set in the solicitation documents.

The Contractor is strongly encouraged to attend and examine the existing conditions of the Project prior to submission of bid in order for the Contractor to better understand the work, verify quantities, and aid in forming any questions the Contractor may have prior to the submission of bid. Questions shall be formally submitted using a pre-proposal inquiry form. All questions will be responded to formally by solicitation amendment.

B. If the Contractor wishes to perform additional site examinations after the pre-proposal meeting, Contractor shall contact the Contracting Officer’s Representative (COR) for this project to coordinate a time. The COR is, and may be contacted at:

Name: Kevin Kelly Cell: 617-828-9220 Work Hours: 7:00a.m. – 3:00p.m., EST

1.4 FIELD VERIFICATION

A. The Contractor shall verify all existing conditions and new and existing dimensions prior to the commencement of work and/or ordering of products and materials that may affect the Work of this contract. Any and all discrepancies shall be forwarded to the Contracting Officer in writing for clarification prior to the commencement of work. Any work performed prior to said clarification, particularly and including that which may require correction shall be corrected by the Contractor with no additional costs to the Contract and/or Government and no time extension shall be made to the Contract Schedule.

B. It is the Contractor’s responsibility during the course of the work to bring to the attention of the

Contracting Officer any latent, unforeseen defective conditions discovered where not previously identified.

1. Notify the Contracting Officer of existing condition differing from those indicated.

2. Upon identification of rotted/damaged components, the Contractor will provide an https://www.acquisition.gov/far independent cost estimate for repair. No rotted or questionable features will be painted unless approved by the Contracting Officer’s Representative (COR).

1.5 GOVERNMENT FURNISHED PRODUCTS

A. Government-Furnished Products: The following products will be furnished by Government and shall be installed by Contractor as part of the Work:

1. No Materials shall be supplied by the Government for this Project.

1.6 PROJECT STANDARDS AND APPROACH

A. Any work performed under this contract shall comply with The United States Secretary of the Interior's Standards for the Treatment of Historic Properties, with guidelines for Preserving, Rehabilitating, Restoring and Reconstructing Historic Buildings, available at:

http://www.nps.gov/history/hps/tps/standguide .

B. This is not a lead abatement project, however workers require certification in Lead Safe work practices. Best practices and engineering controls must be use to limit the exposer to lead dust: such as wet sanding / scrapping, HEPA vacuum, and debris containment.

C. It shall be incumbent upon the Contractor to furnish first-class mechanics and materials, take all necessary precautions and execute the work using historic materials and skills as appropriate and specified herein and as directed by the Contracting Officer (CO) in compliance with said standards.

D. Project Materials: All Project materials and products shall be furnished by Contractor.

E. Work shall be completed as depicted by the Drawings and Technical Specifications, as specified herein, and as required by the job conditions, and the implied intent of the Project as a whole to ensure the life safety, health and well-being of all end users and preserve the Historic Fabric of the Project components.

1.7 WORK RESTRICTIONS – USE OF PREMISES

A. Contractor's Use of Premises: During construction, Contractor will have limited use of site as indicated and confirmed by Contracting Officer. Contractor's use of premises is limited only by Government's right to perform work or employ other contractors on portions of Project. and as follows:

1. Government, Government employees and public will occupy premises and adjacent areas during construction. Conduct operations in a manner to cause the least disturbance to the occupants and visitors. Clean up work areas daily, disposal and/or recycling of materials and return to usable condition of the general area and adjacent areas at the end of each work period. Contractor is responsible for supplying “trip/fall” hazard signage when working with hoses, cords, etc.

2. Limits: No site or land disturbance shall occur with this project.

3. Driveways, Walkways, and Entrances: Keep driveways, pathways, pedestrian areas, sidewalks, parking areas, loading areas, and entrances serving premises clear and available to the Government, Government Employees, the public, park visitors, and emergency vehicles at all times. Do not use these areas for staging, parking of vehicles or equipment, http://www.nps.gov/history/hps/tps/standguide or storage of materials. Contractor parking will be determined and identified during the site visit. Vehicles and equipment will not be allowed, in any way, to impede fire equipment and/or fire personnel at any time.

4. Use of sinks, hoses, water is not allowed for cleaning paint brushes or tools.

Chemicals/solutions used for the cleaning of oil based products are not allowed inside site buildings. Cleaning method and location of oil based products must be approved by the Contracting Officer’s Representative. Cleaning of latex brushes shall be done in closed container provided by the Contractor.

5. Storage of materials and products: Confine to immediate worksite as directed by Contracting Officer. Contractor is allowed a storage container on the Project Site at a location mutually agreeable between Contractor and Contracting Officer. Size of container must be approved by the contractor’s representative prior to container arriving to the site.

See Temporary Facilities and Controls.

6. Preservation of Adjacent Finishes, Contents and Grounds: Throughout the entire duration of the Contract, including all Phases of the Work, confine all operations to the limits defined by the Contracting Officer. Prevent damage to adjacent finishes, contents and grounds.

Restore all damage, repairing and/or replacing as appropriate with no additional costs to the Government.

7. Existing Utilities and Utility Interruption: Notify Contracting Officer, Park Facility Manager and utility company in writing of any proposed disturbances or planned interruptions of existing utilities. Contractor shall submit a plan of operations for utility disturbance. See Temporary Facilities and Controls.

a. Contractor shall be responsible for locating and preventing damage to known utilities. If any damage occurs, contractor shall take action relative thereto and repair utility at no additional expense to the Government. No additional time shall be added to Contract for repairs from damages. Repairs shall commence immediately and carried out expeditiously and in professional manner pursuant to and compliant with all federal, state and local codes and regulations as applicable.

b. If damage occurs to an unknown utility, Contractor shall repair and reconnect utility immediately. An equitable adjustment shall be made in accordance with the Changes clause of the Contract. Repairs shall be conducted as cited above.

c. Interruption of Existing Utility Service: Contractor shall notify Contracting Officer and Park Manager forty-eight (48) hours in advance of utility interruption, and interruption shall only be permitted with prior consent of the Contracting Officer.

Two (2) hours is the maximum time allowed for planned utility disruptions unless otherwise approved by the Contracting Officer in writing. Any interruption beyond four (4) hours shall require temporary services.

d. Interruption of utilities serving facilities occupied by the Government shall be avoided. Temporary or a new utility service shall be in place prior to disturbing existing utility.

8. Hauling Restrictions: Contractor shall comply with all US DOT, State DOT and local legal load restrictions in the transport of all materials and products for the Project.

a. Contractor is responsible for obtaining any and all Permits, special or otherwise, required by authorities having jurisdiction that may be necessary for utilization of adjacent streets and sidewalks for construction operations.

b. Possession of a Permit by Contractor shall not relieve Contractor of liability for damage which may result from construction operations in utilization of said streets and sidewalks.

9. Contractor at all times shall conduct his operations to ensure the safety for all and minimize any inconveniences to the public. All operations shall be compliant with OSHA and other authorities’ regulations, including state and local bodies, having jurisdiction.

a. Contractor shall submit a schedule for safety meetings.

b. Contractor shall submit an emergency plan procedure for the Project.

c. Contractor shall provide workers with all ladder safety equipment required by

OSHA.

d. Contractor shall provide security measures

e. Contractor shall submit an accident prevention and response plan for the Project.

f. Contractor shall possess first aid equipment on site.

g. In so meeting mandated OSHA regulations, the Contractor should note that any safety equipment attached directly to historic elements of the structure must be installed by means of temporary attachment methods, and must be removed upon completion of the work; such that the original integrity and appearance of the element is restored.

B. On-Site Work Hours: Limit work on the existing buildings to normal business working hours of

6:30 a.m. to 3:00 p.m., Monday through Friday, other than federal holidays unless otherwise indicated. All contractors must be off of the premises by 3:00 p.m. of each working day.

1. Weekend Hours: Weekend work shall only be permitted with prior approval.

2. Work Hours: Work to be permitted only during normal business hours. Extended hours shall only be permitted with prior approval.

3. Verbal communication: All verbal communication must be articulated directly to the contractor’s representative in a manner which does not impede the operation of this contract.

The contractor must have a worker on site at all times to provide this communication method.

C. Non-smoking Building/Premises: Smoking is not permitted within park property.

D. The following items are prohibited on the premises, including the Project Site and Park grounds:

1. Firearms

2. Ammunition

3. Alcohol

4. Pets

5. Illegal drugs

6. Radios (to prevent noise disturbance)

E. Contractor’s commercial vehicles, including material and product delivery vehicles, will be allowed on the site, only through coordination with Contracting Officer and Park Manager.

1. All contractor and delivery vehicles shall be equipped with fire extinguishing equipment and first aid as required by U.S. D.O.T. and state D.O.T.

1.8 HISTORIC NATURE OF PROJECT, PROJECT SITE, AND SURROUNDS

A. The Contractor will note and respect the historical significance of the Project, Project Site and surrounds where the work will be performed. Due to this, certain aspects of the Work of this Contract may not be performed in a manner and/or with methods commonplace in the current construction industry of today.

Verify means and methods planned to be performed with Contracting Officer prior to the commencement of Work. This project is not a lead abatement project.

B. It shall be incumbent upon the Contractor to furnish mechanics capable of executing first-class workmanship in the materials and methods specified, and who have the knowledge to take any necessary precautions to protect elements of historic significance, structural and decorative, not scheduled to receive work.

C. Contractor shall repair or replace any damaged items caused by the Contractor at no additional cost to the federal government.

1.9 ARCHEOLOGICAL FINDINGS

A. There may be archeological remains in the work area: Artifacts, structural features, domestic and/or archeological objects of nature, historic or prehistoric, above or sub-surface, found within the construction work area or otherwise on the premises, are property of the Government. Should the contractor’s operation uncover, reveal or his employees find any archeological remains, do not remove. Notify the Contracting Officer immediately of the findings. Included in the notification to the Contracting Officer shall be a brief statement of the location and details of the findings. A digital photograph of the location and the object(s) may be a part of the statement.

1.10 HAZARDOUS MATERIALS

A. This project is not a lead abatement project, however workers require certification in Lead Safe work practices.

B. When Hazardous materials are encountered upon the site, or when carrying out the Work.

1. Best practices and engineering controls must be use to limit the exposer to lead dust: such as wet sanding / scrapping, HEPA vacuum, and debris containment.

C. If any Hazardous Material Other than lead paint is encountered, all work shall stop in the area of the encounter and Contractor shall notify Contracting Officer immediately of discovery and its extent as known. Contractor shall not work in the encounter area until a resolution is established.

1. Contractor shall continue work in all other areas of the Project without interruption or delay.

2. Contractor shall adjust work and/or begin other work on the Project that is not dependent upon the encounter area.

PART 2 – PRODUCTS

SALIENT CHARACTERISTICS AND PROPERTIES OF PRODUCTS

A. Any products cited by manufacturer within any Division Section of the Technical Specifications, this Project Manual, and/or the Drawings is for clarification purposes in order to communicate to the Contractor, delineating the minimum requirements of the salient characteristics of the product(s) and / or material(s) to be utilized in the construction activities for the Work of the Project.

B. Where an item, of equipment or material, is designated by reference to a particular brand-name, manufacturer or trade name, in the Drawings or Specifications, it shall be understood by all entities participating in the Project that the citing of such is to establish the minimum acceptable standard of quality allowed by the Government and is not intended to preclude manufacturers of similar products believed by the Offeror/Contractor to possess the characteristics to the item cited.

C. The Contractor shall be required to demonstrate to the satisfaction of the Contracting Officer (CO) that the item to be utilized in the Work match and/or exceed the quality and/or durability of the item(s) referenced.

PART 3 - EXECUTION

3.1 PROJECT EXECUTION

A. The Project shall be executed and all construction activities completed by the Contractor as cited within the Contract Documents.

END OF SECTION 011000

SECTION 013000 – ADMINISTRATIVE REQUIREMENTS

PART 1 – GENERAL

1.1 SUMMARY

A. The Work of this Section includes the following:

Project Meetings Preconstruction Submittals Close-Out Submittals Submittal Requirements Requests for Information Project Schedule Time Impact Analysis for Contract Modifications Contract Documents Photographic Documentation Substantial Completion and Final Acceptance

1.2 PROJECT MEETINGS

A. The Preconstruction Conference: Contracting Officer will notify Contractor of date for the Preconstruction Conference following Contract Award.

1. If all of the required Preconstruction Documents have not been received at least seven

(7) calendar days prior to the scheduled Preconstruction Conference date, the conference may be cancelled, Notice to proceed may not be issued, and the Contracting Officer may consider other contractual remedies.

2. The meeting agenda will include the following as a minimum:

a. Roles & Responsibilities/ Lines of Authority.

b. Park rules and regulations.

c. Contractor’s use of site.

d. Resolution of comments on required Division 01 documents.

e. Coordination of Subcontractors.

f. Labor law application.

g. Modifications.

h. Payments to Contractor.

i. Payroll reports.

j. Contract time.

k. Liquidated damages.

l. Display of Hotline posters.

m. Notice to proceed.

n. Correspondence procedures.

o. Acceptance/rejection of Work.

p. Progress meetings.

q. Submittal procedures.

r. Environmental requirements.

s. Record Documents.

t. Saturday, Sunday, holiday and night work.

u. Reference materials.

v. Value engineering.

3. The Contracting Officer will prepare meeting minutes and distribute them to all attendees and interested parties within seven (7) calendar days of each meeting.

B. Progress Meetings: The Contractor shall schedule and conduct progress meeting at regular intervals throughout the Construction Period.

1. Attendees: In addition to Contracting Officer and/or designees, each Contractor, Subcontractor and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of offsite fabrication and delivery schedules (if any)

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

g. Construction Schedule update

h. Status of Project Record Drawings (if any)

i. Other business relating to Work.

3. Meeting Minutes:

a. The Contractor shall prepare meeting minutes and distribute them to all attendees and interested parties (as defined at Preconstruction Conference) within seven (7) calendar days of each meeting.

b. Meeting Minutes recipients shall review Minutes and return comments within three (3) business days.

c. Meeting Minutes shall incorporate or respond to all comments prior to each succeeding meeting.

1.3 PRECONSTRUCTION SUBMITTALS

A. The following items shall be submitted a minimum of seven (7) calendar days prior to the

Preconstruction Conference. Submit Preconstruction Documents under separate cover letter on Contractor’s letterhead. Do not use Transmittal CM 16 for these documents.

1. List of Subcontractors: Provide the following information:

a. Business name.

b. Business address and telephone number.

c. Mobile telephone number.

d. Email address.

2. List of Key Personnel: Provide the following of Forman and/or Superintendent for this project:

a. Name.

b. Position.

c. Mobile telephone number.

d. Email address.

3. Schedule of Values (if any)

4. Project Schedule

5. Accident Prevention Plan

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Written statements from subcontractors certifying compliance with applicable quality assurance requirements

8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

9. Quality Control/Assurance Plans.

1.4 CLOSEOUT SUBMITTALS

A. Submit the following items to Contracting Officer for review and approval, prior to requesting final inspection.

1. Record Photos

2. Warranties, Guarantees and Bonds: As specified in individual Sections of the

Specifications.

a. Warranties: Place a copy of each manufacturer, supplier, and installer warranty extending for a period greater than one year in a single separately identified tabbed section of the manual.

1.5 SUBMITTAL REQUIREMENTS

A. Contractor shall submit information required by specified Section of these specifications.

B. Coordination:

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. (if any)

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

3. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow enough time for submittal review, including time for re- submittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Action submittals

a. Initial Review: Allow fifteen (15) calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

b. Re-submittal Review: Allow five (5) days for review of each re-submittal.

2. Informational submittals

a. Review: Allow five (5) calendar days for review of each submittal.

3. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

D. Number of Submittals: Wherever possible submit one (1) electronic copy of submittals.

1. Action Submittals: If not possible to submit electronic copies, submit five (5) hard copies of submittals. Contracting Officer will return three (3) copies of each action submittal to the Contractor and retain two (2) copies.

2. Informational submittal: If not possible to submit electronic copies, submit two

(2) Hard copies of Informational Submittals. Contracting Officer will not return copies to Contractor.

E. Contractor shall review all submittals including those from all subcontractors, for accuracy, completeness, coordination with other Work of the Contract, and compliance with the Contract Documents. Contractor shall mark each submittal with an approval stamp and forward to Contracting Officer with the approved Transmittal Form.

1. Both paper and electronic submittals shall be accompanied with Government

Transmittal Form CM16.

2. Paper Submittals: Place a permanent label or title block on each submittal for identification. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Government.

Include the following information on the label:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name and address of subcontractor or supplier.

e. Number and title of appropriate Specification Section.

f. Identify options requiring selection by Contracting Officer.

g. Identify deviations from the Contract Documents on submittals.

3. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

a. Assemble complete submittal package into a single indexed *.PDF file incorporating submittal requirements for each Specification Section and transmittal form with links enabling navigation to each item.

b. Name file with unique identifier, including project identifier, Specification Section number, and revision identifier.

c. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by the Government.

d. Identify options requiring selection by Contracting Officer.

e. Identify deviations from the Contract Documents on submittals.

4. Contracting Officer will discard submittals received from sources other than Contractor.

F. Action Submittals:

1. Product Data: Mark each copy to show applicable products and options. Include the following:

a. Manufacturer’s written recommendations, product specifications, and installation instructions.

b. Safety Data Sheets (SDS): For each product required by OSHA to have a SDS, submit an SDS. MDS shall be prepared within the previous five years.

2. Operation and Maintenance Manuals: Comply with requirements specified in individual Specifications Sections. (if any)

3. Samples: Submit Samples for review of kind, color, and texture. Include name of manufacturer and product name on label.

G. Government Review and Approval of Submittals:

1. Action Submittals: The Contracting Officer Representative (COR) will review each

Action Submittal, indicate corrections or modifications required, stamp each submittal with an action stamp, and mark stamp appropriately to indicate action, as follows:

a. APPROVED: Acceptable with no corrections.

b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the Work.

c. DISAPPROVED - RESUBMIT: Submittal is not in accordance with the contract or requires significant corrections and/or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

2. Informational Submittals: Contracting Officer will review each submittal.

a. Acceptable: If submittal is acceptable, Contracting Officer will notify Contractor and retain submittal for the files. Contracting Officer will not return acceptable Informational Submittals.

b. Resubmit: Contracting Officer will return Informational Submittals that do not comply with the Contract Documents, with notations as to why they do not comply. Contractor shall revise and resubmit as required.

3. Submittals not required by the Contract Documents may not be reviewed and may be discarded.

1.6 REQUESTS FOR INFORMATION (RFI)

A. On discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI.

1. Use form approved by the Contracting Officer.

1.7 PROJECT SCHEDULE

A. The Contractor shall develop a Project Schedule that includes all required tasks of the

Construction Period from Notice to Proceed through Project Close-out and shall reflect the contractual start and completion dates.

B. Purpose: The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the Work by the Contractor. The project schedule will assist the Contractor and Contracting Officer in monitoring the progress of the Work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

C. Project Schedule Updates: Update the Project Schedule at regular intervals, at least monthly, throughout the entire Contract Period. Provide updated Project Schedules at each Progress Meeting.

1. Procedure: The Contractor shall meet with the Contracting Officer at a Project

Schedule Update Meeting to review actual progress made through the status Date of the Project Schedule update, including dates activities were started and/or completed and the percentage of work completed on each activity started and/or completed.

2. Progress Payments: The updated Project Schedule shall be an integral part of the process upon which Progress Payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of his monthly payment may be retained until such revisions/corrections have been made.

D. The Project Schedule shall be prepared using the Critical Path Method (CPM).

E. Project Schedule Development:

1. The Start Date shall be the same date as Notice to Proceed is issued.

2. The Finish Date shown on the schedule shall be the same date as the last day of the

Contract Period.

3. The Contractor's project schedule shall include procurement activities (including mobilization, submittal, the fabrication and delivery of key and long- lead procurement items, if any) and construction activities and project close-out activities including, but not limited to, the following for each activity:

a. Identify each and every activity with numerical designations.

b. Provide concise description of the work represented by the activity. Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to a single trade.

4. In developing the project schedule, ensure that subcontractor work at all tiers, as well as the prime contractor's work, is included and coordinated in the Project Schedule.

5. The Project Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the project schedule shows a coordinated plan for the Work.

6. Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity within the parameters of the contractual project start and completion dates.

7. Consider seasonal weather conditions in planning and scheduling all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the Contract Time. Show anticipated weather conditions on project calendar.

F. Joint Review, Revision, and Acceptance:

1. Within seven calendar days of receipt of the Contractor's proposed Project Schedule, the Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the proposed project schedule. Any areas which, in the opinion of the Contracting Officer, conflict with timely completion of the project shall be subject to revision by the Contractor.

2. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, when discovered by the Contractor or Contracting Officer, shall be corrected by the Contractor at the next Project Schedule update and shall not affect the Contract Time.

3. Within seven (7) calendar days after the joint review between the Contractor and Contracting Officer, the Contractor shall revise and resubmit the Project Schedule in accordance with agreements reached during the joint review.

4. Upon acceptance of the Project Schedule by the Contracting Officer, the Project Schedule will be used to evaluate the Contractor's monthly applications for payment.

1.8 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS

A. Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the contract completion date, the Contractor shall submit to the Contracting Officer a written request that includes a Time Impact Analysis illustrating the influence of each modification, change, delay, or Contractor Request on the contract completion date.

B. Time Extensions: Activity delays shall not automatically mean that an extension of the contract completion date is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical path activities or cause non- critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the Project Schedule, thereby not causing any effect on the contract completion date. Time extensions will be granted in accordance with the terms of the Contract.

C. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor.

Extension of the contract completion date will be granted only to the extent the net time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) Float available on a particular activity.

D. Procedure: Each Time Impact Analysis shall be submitted within the time period stated in a Request for Proposal, or the time period designated under the clauses entitled Changes or Default. In cases where the Contractor does not submit a written request for extension of the contract completion date and a Time Impact Analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract completion date. Upon acceptance, the Time Impact Analysis shall be incorporated into the Project Schedule at the next monthly schedule update.

E. Daily Reports: The Contractor’s daily reports may be utilized by the Contracting Officer to determine if additional time is justified.

1.9 CONTRACT DOCUMENTS

A. Government will provide Contractor one (1) set of the digital data drawing file types in

*.pdf or similar format for use in preparing Shop Drawings and Project Record Documents.

(if any)

B. Government makes no representations as to the accuracy or completeness of digital data drawing files as they relate to the Contract Drawings.

1.10 PHOTO DOCUMENTATION

A. Contractor shall document progress of the Work of this Contract photographically at regular intervals.

B. Format Requirements: Media: CD-R Archival Gold or DVD-R Archival Gold

1. Images: Provide 24 bit, three channel (RGB) color images as original-capture JPEG File Format. Minimum sensor size of six (6) mega pixels, and at an image resolution of not less than 1024 by 768 pixels.

2. Images taken from a cell phone are not acceptable. Media Labels: Archival CD/DVD labeling markers, archival labels, or direct print CD/DVD.

C. Each photo shall be marked as follows:

1. Include date, time and number (sequentially number all images) in filename.

2. Provide description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

3. Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.

D. Existing Conditions Images: Show existing conditions of adjoining construction and historic materials prior to beginning the Work of this Contract.

1. The purpose of these photographs is to document the existing condition of areas adjacent to the Work and document existing damage or deterioration that might be misconstrued as damage caused by the Contractor while performing the Work of this Contract.

2. Submit digital images to Contracting Officer prior to proceeding with any Work of this Contract.

E. Construction Images: Take a minimum of ten (10) photos each week and at regular intervals throughout the Contract Period. Submit images to the Contracting Officer electronically within seven (7) calendar days of taking the image.

F. Additional Images: Contracting Officer may issue requests for additional images, in addition to periodic Construction images specified.

1. Three days’ notice will be given, where feasible.

2. In emergency situations, take additional images within twenty-four (24) hours of request.

G. Closeout: Submit a complete set of digital image electronic files of all photos taken throughout the Contract Period, as a Project Record Document. Submit on either a Compact Disc (CD) or Digital Video Disc (DVD).

1. Provide an index as a separate file on the Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.

2. Submit images that have the same aspect ratio as the sensor, un-cropped.

1.11 SUBSTANTIAL COMPLETION AND FINAL ACCEPTANCE

A. When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.

B. If, following final inspection, the Work is determined to be Substantially Complete, Contracting Officer’s Representative will prepare a list of deficiencies to be corrected before final ac- acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within fourteen (14) calendar days, unless delayed by weather.

C. If, following final inspection, the Work is determined not to be substantially complete;

Contracting Officer will notify Contractor in writing. After completing work, Contractor shall request a new final inspection.

D. After all deficiencies have been corrected; a Letter of Final Acceptance will be issued.

E. Contractor shall perform final warrantee walk-thru with the Contracting Officer’s Representative within 30 days of warrantee expiration.

PART 2 – PRODUCTS Not Used

PART 3 – EXECUTION Not used.

END OF SECTION 013000

SECTION 013600 – ACCIDENT PREVENTION

1.1 WORK COVERED BY THE CONTRACT:

A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2 SUBMITTALS

A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:

1. Name of responsible supervisor to carry out the program.

2. Weekly and monthly safety meetings.

3. First aid procedures.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.

5. Training, both initial and continuing.

B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.

C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

D. Submit a report of safety meetings and of inspections.

E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

1.3 QUALITY ASSURANCE

A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the contract. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees:

1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

1.4 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.

B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

PART 2 - PRODUCTS

2.1 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

2.2 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of NIOSH and MSHA.

PART 3 - EXECUTION

3.1 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.2 FIRE AND LIFE SAFETY

A. Provide and maintain the fire and life safety requirements in NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).

B. Contractor shall have a Hazard Communications Plan; store hazardous materials in accordance with manufacturer’s and OSHA recommendations; immediately report all spills of hazardous materials to the park; and maintain a spill emergency response kit.

3.3 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.4 SAFETY MEETINGS

A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

B. Conduct monthly safety meetings for all levels of supervision. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The Contracting Officer Representative will attend the meeting and enter the results of the meetings into the daily log.

3.5 TRAINING

A. First Aid: Provide adequate training to ensure prompt and efficient first aid.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

END OF SECTION 013600

SECTION 015000 – TEMPORARY FACILITIES AND CONTROLS

1.1 SECTION REQUIREMENTS

A. Use Charges: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated.

B. Water and Electric Power: Available from Park existing system without metering and without payment of use charges. The Park will not provide hoses for use of washing the house. Contractor to provide connections and extensions of services (including hoses) as required for construction operations. It is recommended that the Contractor investigate the amount of hose necessary before the contract begins.

C. Electric Service: If additional power is required, comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

D. Accessible Temporary Egress: Comply with applicable provisions in ABAAS & ADA as applicable to the project.

E. Sanitary Facilities: Use of site bathrooms and slop sink is permitted.

2.1 MATERIALS

A. Fencing:

1. Plastic Snow Fencing: 1.5” x 1.25” diamond pattern, premium grade minimum four foot high color orange. Supported by appropriate metal stakes. To be used in areas to cordon off public access from active work areas. Coordinate installation with COR.

B. The Contractor shall provide sufficient ladders or staging to give complete access to the work of this section prior to the commencement of the work. Contractor shall erect staging in a way to allow the Park to maintain two means of egress at all times and provide protection for staff and visitors entering the building. Pump and/or pipe staging is allowed for this project. COR must approve the point of attachment.

2.2 TEMPORARY FACILITIES

A. Provide field offices, storage and fabrication sheds, and other support facilities as necessary for construction operations. Do not store combustible materials on site property.

2.3 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

3.1 SUPPORT FACILITIES INSTALLATION

A. Install project identification and other signs in locations approved by Contracting Officer to inform the public and persons seeking entrance to Project.

B. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations.

3.2 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. The National Park Service is not responsible for the security of the contractor’s equipment. All ladders must be taken down, locked, and stored each day.

B. Proposed security measures shall be approved in writing. Security measures shall be in effect 24-hours a day.

C. Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

D. Special precautions must be taken to protect, rain gutters and base courses from damage such as that caused by the leaning of ladders.

E. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion as directed by Contracting Officer and COR.

F. Furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering site except by entrance gates.

G. Barricades, Warning Signs, and Lights: Comply with requirements of Contracting Officer, Park facility Manager, Park Safety Officer or Lead Ranger having jurisdiction for erecting and maintaining structurally adequate barricades, including warning signs and lighting as appropriate for the project.

H. Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weather tight enclosure for building exterior.

END OF SECTION 015000

SECTION 017000 - EXECUTION AND CLOSEOUT REQUIREMENTS

1.1 EXECUTION REQUIREMENTS

A. Permits: Proof of the requirements for any Permits that may have been required for the Project shall be submitted to the Contracting Officer.

B. Manufacturer's Installation Instructions: Obtain and maintain on-site manufacturer's written recommendations and instructions for installation of products and equipment.

1.2 CLOSEOUT SUBMITTALS

A. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

B. Certified List of Incomplete Items: Final submittal at Final Completion.

C. PDF Electronic File: Assemble manual into a composite electronically indexed file. Submit on digital media.

D. Record Digital Data Files: Submit data file and one (1) set(s) of plots.

E. Record Product Data: Submit one paper copy annotated PDF electronic files and directories of each submittal.

1.3 SUBSTANTIAL COMPLETION PROCEDURES

A. Prepare a list of items to be completed and corrected (punch…