A04-Scope_of_Work.pdf
PDF 47 KB Posted
- Attached to
- MI-PENDILLS CRK NFH-QRTRS PROJECTS
- Solicitation number
- 140F0222Q0008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WD.pdf | ||
| A06-PLANS___DETAILS_FOR_RES_1___2.pdf | ||
| Sol_140F0222Q0008.pdf | ||
| A06-SEWAGE_DISPOSAL_SYSTEM_PLANS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pendills Creek National Fish Hatchery Quarters Plumbing Replacement
Scope of Work
All work to be performed on quarters 18, 19, and 24 at Pendills Creek National Fish Hatchery.
Replace approximately 100 feet existing drain lines with ABS piping from wall outlet of each sink, toilet, and tub all the way to the septic tank. Connect to all existing vents.
Replace incoming water supply lines with pex piping, starting where the water line enters the crawl space of each house, including all water lines and valves to the stop valves(includes new stop valves) for each sink, toilet, tub, and hot water heater.
Work to include all excavation and demolition of existing plumbing, disposal of all demolition materials, and installation of new plumbing. All work performed must meet most recent Michigan plumbing code.
Install a whole house shut off valve as the water enters the crawl space. Install isolation shut off valves for each, hot and cold water, and each outdoor spigot.
Each house has one bathtub, one toilet, one bathroom sink, one kitchen sink, one utility sink, one hot water heater, one washer hookup, and two outdoor frost- free spigots
Contractor is responsible to repair any wall damage caused by this project and return damaged areas back to existing condition.
Contractor to verify piping dimensions and quantity of each material, have utilities marked prior to excavation and leave excavated sites graded to match existing.