A04 0040515071 20201109 Statement of Work.pdf

PDF 619 KB Posted

Attached to
Exterior Cyclic Maintenance (Carpenrty/Painting)
Solicitation number
140P4321Q0002
Issued by

View the file

Other files

File Type Posted
Sol_140P4321Q0002_Amd_0001.pdf PDF
B03 140P4321Q0002 20200925 DB MA20200001 Mod 7.pdf PDF
Handout 8 CM16 20201007.pdf PDF
Sol_140P4321Q0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Cyclic Maintenance at Oversands Vehicle Program Office

CAPE COD NATIONAL SEASHORE

204 Race Point Road, Provincetown, MA

November 9, 2020

Scope This project is for exterior cyclic maintenance at the park’s Oversand Vehicle Program office, a National Register-eligible historic structure at Cape Cod National Seashore.

Work shall include:

repair of two barn doors, one fixed in place and one operable;

repair deteriorated sill and studs at gable end fixed barn door, assume 60 linear feet;

modify two FRP double-swing interior pass-through doors to include one half-lite window in each;

repair any damage to soffit, trim, fascia and rake boards, assume 20 linear feet;

replacement of nine (approximately) 35” x 60” non-historic double hung windows;

stain approximately 1600 square feet of roofing to match Coast Guard red color;

refinish approximately 180 square feet of trim, soffit and fascia;

repairs to frieze board, assume 24 inches;

replace approximately 530 square feet of shingle siding on southwest side;

strip, patch, prep and refinish approximately 1320 square feet of currently painted surfaces on the building.

Minimize disturbance to the site to the greatest extent possible unless directed otherwise.

Provide all labor, materials, tools, and equipment required to complete this work.

All work performed under this contract shall be done in accordance with applicable local, State, and Federal codes, bylaws and ordinances in effect at the time of this work.

Measurements Estimated dimensions and quantities are provided as a guide only. The contractor is responsible for verifying all measurements and dimensions. Take all measurements for quantities of materials and note existing conditions for the installation of new work. All ancillary work, cutting and /or removal of existing work necessary for the installation of new work shall be done as required as part of this contract.

Site Examination It is the responsibility of the contractor to examine the work site to confirm existing conditions and required quantities prior to submitting a proposal on this project. The contractor may arrange a site visit by contacting the Contracting Officer’s Representative (COR), John DeFoe, 508-957-0707, between 8:00 a.m. and 4:00 p.m. Monday through Friday or anytime at john_defoe@nps.gov.

It is strongly suggested that locations and dimensions be field verified by the contractor prior to submitting a quote.

mailto:john_defoe@nps.gov

Historic Nature of Work Site The contractor shall note the historical significance of the site upon which the work will be performed.

Because of the historic nature of this site, certain aspects of the work of this Contract will not be carried out with materials and/or methods commonplace in the modern construction industry. It shall be incumbent upon the contractor to furnish staff who can execute first-class workmanship in the materials and methods specified, and who will take any necessary precautions to protect the elements of this historic site not scheduled to receive work.

Utilities and Services Provide and maintain sanitary facilities for workers.

The contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. Notify Contracting Officer and utility companies of proposed locations and times for excavation. If damage occurs to an unknown utility, repair utility and immediately notify Contracting Officer.

Water Service: Depending on time of year, water from existing water system is normally available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. If water is not available, the contractor shall supply temporary potable water adequate to the needs of the contract at no additional cost to the contract for project use.

Electric Power Service: Electric power from existing system is normally available for use during construction without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs.

Arrange with utility company and government for time when service can be interrupted, if necessary, to make connections for temporary services. If electric power is not available, the contractor shall provide temporary power at no additional cost to the contract for project use.

No other utilities or services will be available at the project site. There is no land line telephone service at the project site.

Permits and Approvals The contractor is responsible for contacting Dig Safe (#811) or other approved utility marking entity for pre-marking of all underground utility locations within project area prior to any ground disturbance.

Prior to commencement of any on-site work, provide CO with copies of proof of pre-marking from utility marking entity.

Obtain all required permits for the performance of the work specified in Contract Documents at no additional cost to the contract.

Submittals and Deliverables

Transmittal Form (CM-16). All submittals shall be transmitted using National Park Service form Transmittal Form (CM-16).

Submit safety plan that complies with OSHA standards within 3 business days after award.

Submit a safety management plan that addresses parking, vehicular circulation, pedestrian circulation, laydown, fall protection, moving of materials and equipment within 3 business days after award. A fall protection plan shall be posted or made available prior to start of elevated work or any other time it is required.

Propose location of laydown and stockpile area for NPS approval. Laydown and stockpile shall be confined to existing paved areas only.

Provide detailed proposed project schedule prior to commencing any work on site.

Product Data: provide manufacturers' literature on characteristics of materials, maintenance, parts list and warranties. Submit only pages which are pertinent. Mark each copy to identify pertinent products referenced to the specifications. Provide manufacturers’ literature, drawings, and technical data sufficient to fully define the material and to demonstrate full compliance with the contract specifications.

Manufacturer's Installation Instructions: Include special precautions from manufacturer.

Drawings: submit drawings as appropriate.

Materials: submit representative samples of all materials to be used in sizes adequate to define the purpose of the material and determine its suitability.

Manufacturer's certificate: certify that products meet or exceed specified requirements.

Perform the work of this contract.

Safety and Environmental Protection Requirement This building was constructed prior to 1978, therefore, work may disturb lead-based paint. It is not the government’s intention to abate lead paint under this contract. The contractor shall protect contractor’s personnel and the public during the performance of any work that may disturb lead-based paint. Waste materials meeting the criteria of hazardous waste shall be disposed of as such in a legal manner.

Maintain project area in a neat, orderly and safe condition at all times. All work areas shall be made secure and safe after hours, on weekends and holidays.

All debris and removed material are the property of the contractor and shall be recycled or legally disposed of in a manner that is consistent with local and state regulations. All waste, trash and debris generated as part of this project must be secured from wind and rodent action.

Take all necessary precautions to prevent fire during construction. Provide and maintain suitable fire protection equipment. Protection Equipment Required: Furnish a minimum of one UL Class 2A, 2-1/2 gallon water type stored pressure extinguisher, and one UL Class 10, Type I, 15 pound A:B:C carbon dioxide extinguisher at each work site.

No radios or smoking (including vaping) will be allowed on the job site. Confined space entry, fall protection and hardhat use will conform to safety rules and regulations.

The contractor’s on-site representative shall have an updated First Aid card. Fall protection plan shall be posted or made available prior to start of elevated work or any other time it is required.

The contractor is responsible for securing the site and the work of the contract. During the execution of this contract, the contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards. Provide barriers, temporary fencing, signage, etc. wherever work could cause injury to workers or visitors, and ensure that ladders, scaffolding and equipment are secured from public access during off-hours.

Provide and maintain environmental protection during the life of the Contract to control pollution or to correct conditions that develop during construction.

Equipment shall not be allowed to operate outside the limits of work or to disturb existing vegetation.

Construction equipment shall be kept in good repair, without leaks of hydraulic or lubricating fluids.

The contractor must visually inspect all equipment prior to commencing work every day and at the mid-point in the workday for leaks. If such leaks or drips do occur, they shall be cleaned up immediately.

Confine equipment maintenance to one location. Control runoff in this area to prevent contamination of soils and water. No equipment repair will be allowed on the site.

It is the contractor’s responsibility to ensure that any disturbance or damage done during the course of this project to the existing utilities, landscape, building or government materials, shall be repaired or restored to its original condition by the contractor at the contractor’s expense prior to completion of the job.

Work and Weather Limitations Regular work hours are between 7AM to 4PM Monday through Friday. Unless otherwise requested and approved in advance, no work shall take place after hours, on holidays or weekends. Requests must be made 48 hours in advance.

The contractor shall be responsible for storage of all materials and equipment; the Park must approve the contractor’s use of any space on the site in advance.

Proceed with project only when existing and forecasted weather conditions will permit work to be performed according to manufacturers' recommendations and warranty requirements. Ensure temperatures are over the minimum installation temperatures recommended by material manufacturers.

Security and Safety The contractor shall have unescorted access to the construction site. The contractor shall coordinate with the COR for access to all locations.

The Contracting Officer’s Representative (COR) or the COR’s alternate will not be required to be at the site location during all working hours.

Regulations

• Occupational Safety and Health Administration (OSHA)

• National Institute for Occupational Safety and Health (NIOSH)

• Massachusetts General Laws and Department of Environmental Protection regulations and statutes

• Town Board of Health Regulations

Materials Furnish, supply, and install all necessary materials to successfully complete the project requirements.

Unless explicitly indicated, new materials shall match those being replaced.

Dimensional and structural lumber Wood to match existing species, shape and dimensions. All material shall be the best of its respective kind, free from stain, rot, or other imperfections impairing strength or durability.

Wood for window, door, soffit, fascia and trim repair and structural repairs shall match existing in species, shape and dimensions.

Wall sheathing (if needed) Wood to match existing species, shape and dimensions. All material shall be the best of its respective kind, free from stain, rot, or other imperfections impairing strength or durability.

Flashing Sheet Flashing shall be ASTM A 361/A361M; 26 Gauge (0.45 mm) steel with minimum G115/Z350 galvanized coating, ASTM B 209; 0.025 (0.63mm) thick aluminum, mill finish.

Windows New windows shall be thermopane with exterior grilles to match existing in appearance, functionality, shape and dimensions. Windows shall be factory finished in a color to match trim used on side of building. Windows shall be the best of their respective kind and intended for use in extreme environments. As an advisory to the contract, Andersen Coastal 400 Series and Pella Hurricane Shield Series meet the requirements of these specifications.

Existing door modifications Modifications to FRP double-swing interior pass-through doors shall be fully compatible with existing doors and include the manufacturer’s glass kit to cut in half-lite windows, one window per door, size to be determined by COR. Existing doors are Senneca Chem-Pruf FRP doors; window and window retainer shall match the door in color and finish.

Siding Materials Rain screen shall be black nylon ventilated underlayment three-dimensional open mesh with a thickness of 0.277 inches (7.04 mm), weight of 9.7 lbs/roll and a fire Rating of A. As an advisory to the contract, Cedar Breather meets the requirements of this contract.

House-wrap siding underlayment for application over wall sheathing shall be nonwoven spun, water-resistant, extremely fine fused high-density polyethylene (HPDE) lightweight, breathable pliable fabric made to resist bulk water and air penetration, reduce mold and water damage, stop air movement through walls and allow moisture vapor to pass through. As an advisory to the contract, Dupont Tyvek meets the above-listed criteria.

Cedar siding shall be white cedar shingles manufactured by members of the Cedar Shake & Shingle Bureau graded in accordance with UBC Standards No. 15-3 and/or CSA 0118.1, blue label resquared and rebutted, 16” minimum, Premium Grade All Clear, no defects, Heartwood 100% edge grain random widths, minimum width shall be 4", thickness shall be nominal with a minus tolerance of 1/16" in 10% of the bundle.

Cedar clapboard siding for repairs, if needed, shall be kiln-dried plain bevel ½” X 6” clear vertical grain heartwood per NLGA paragraph 201a, Western Red Cedar, factory finished, color to match existing.

Wood Patching Materials Use patching products of a single manufacturer to ensure best performance.

Wood Consolidant: Ready-to-use product designed for hardening and sealing soft fibers of wood materials that have deteriorated due to weathering and exposure and designed specifically to enhance the bond of wood patching compound to existing wood. Subject to meeting the salient characteristics specified and COR approval, the following products are acceptable:

• Abatron, Inc.; Liquidwood;

• Advanced Repair Technology; Primatrate;

• Gougeon Brothers, Inc.; West System;

• Other products meeting the specified salient characteristics and as approved by the COR.

Epoxy for Wood Repair: 2-part epoxy-resin wood compound with a 10 to 15-minute cure at 70 deg F, in knife grade formulation and recommended by manufacturer for type of wood repair indicated.

Compound shall be designed for filling damaged wood materials that have deteriorated due to weathering and exposure. Compound shall be capable of filling deep holes and capable of spreading to feather-edge. Subject to meeting the salient characteristics specified and COR approval, the following products are acceptable:

• Abatron, Inc.; Liquidwood with WoodEpox;

• Advanced Repair Technology; Primatrate with Flex-Tec HV;

• Gougeon Brothers, Inc.; West System;

• Other products meeting the specified salient characteristics and as approved by the COR.

Wood Finishes Finishing products for use in the work shall be the standard best or top brands produced for each particular kind of material required herein. The label on the primer container should indicate that the coating is recommended for use as stain blocking primer for Western Red Cedar. Highest quality, standard brand, latex stain-blocking primer for red cedar and stain as recommended for exterior use.

Provide primers and other undercoat materials produced by same manufacturer as finish coats.

Acceptable manufacturers: 1. Sherwin Williams; 2. Benjamin Moore; 3. Valspar; or equal meeting the specified salient characteristics and as approved by the COR. Stain primers, sealers, and undercoats shall match be suitable for the substrate and compatible with the finish coat and each other. Finish coat color shall match existing.

All new trim material shall be factory pre-finished on all six sides of each board. All wood trim finishes shall be highest quality, standard brand, stain-blocking primer and solid color stain as recommended for exterior use with mold and mildew inhibitors, factory applied to all surfaces of new wood materials in a manner consistent with manufacturer’s recommendations and best practices of the industry. Color to match existing. One coat primer and two coats of finish coat to match existing in color.

Existing trim to remain shall be finished with highest quality, standard brand, solid color stain as recommended for exterior use with mold and mildew inhibitors in a manner consistent with manufacturer’s recommendations and best practices of the industry. Color to match existing.

Obtain the same products used in factory finish for treatment of all field cuts prior to installing cut material, in accordance with manufacturer’s recommendations.

Stain for roof shall match “Coast Guard” red, color to be approved by COR prior to installation.

Caulking for joints or gaps around doors, windows, or siding where water invasion may occur shall be non-shrink high-performance acrylic-latex, acrylic, acrylic-silicone, polyurethane, polysulfide or terpolymer rubber materials compatible with specified finishes, such as Benjamin Moore Elastomeric 465 01 Caulk, or an approved equivalent. Pure silicone and clear caulks do not work well on Western Red Cedar and shall not be used in that application.

Fasteners Fasteners shall be sized for intended purpose, according to best practices of the industry.

Fasteners for shingles shall be of a length sufficient to penetrate into the sheathing at least ¾”, stainless steel type 316 ring shank blunt tip nail with minimum 7/32" head. Likely length of fastener: 1 ½” to 1 ¾”” long.

Fasteners for clapboard siding shall be split-less stainless steel fasteners designed for siding installation with a thin shank and blunt point with either ring or spiral shank. Fastener length should be adequate to provide a secure penetration into solid wood.

Fasteners for structural repairs shall be hot-dipped galvanized, sizes and types to conform to best practices of the industry.

Stainless steel staples will only be allowed to install water-resistant barrier under siding. No other use of staples will be allowed.

Workmanship The contractor is responsible for appropriate quality control and workmanship shall be the best of their respective kinds and in full accordance with applicable codes.

Make sure all work is flush, square, level and has proper reveals per manufacturer’s specs. If not sure ask COR before starting.

When a manufacturer or a standard uses subjective words, e.g., “should, could, may”, etc., these words shall mean “shall, will, required”, etc. When the word “recommended” is used, it shall mean “required”. If there is a conflict between general and specific provisions, the specific shall govern.

The AAMA 2400-2 manual, the Exterior and Interior Wall Manual published by the Cedar Shake and Shingle Bureau, and all standards and recommendations referred to by the manufacturers shall be applicable.

Ensure that all work is free from dirt, damage or defects. Pick up extra materials within 2 days of job completion. Do not use windows for access or to pull cords, hoses or siding materials though. Do not cut through trim or siding while on the building to avoid damaging the underlayment. Do not nail cleats or wood blocks onto or in finished siding products. Appropriate manufacture cleats shall be used that slide up under shingles. Never splice trim or siding when full-length material will fit.

Upon Notice to Proceed, the contractor shall make steady and uninterrupted progress toward the completion of the work of this contract.

Demolition The intent of the project is to preserve all existing building materials in situ wherever possible and salvageable, unless specifically indicated to be replaced.

Before beginning any demolition or deconstruction work, inspect and examine the site to determine the extent of the work. Take necessary precautions to avoid damage to existing items, including trees, to remain in place, to be reused, or to remain property of Government.

Provide waste-collection containers in sizes adequate to handle waste from construction operations.

Comply with requirements of agency(ies) with jurisdiction.

Unless otherwise indicated, disposal of removed materials shall be the contractor's responsibility. All debris and removed material are the property of the contractor and shall be recycled or legally disposed of in a manner that is consistent with local and state regulations.

Installation All work shall be done in conformance with the Secretary of the Interior Standards for the Treatment of Historic Properties.

Preserve all existing building materials in situ wherever possible using wood patching materials as described elsewhere in this document. Only as a last resort and only after approval by COR, replace damaged and rotted material with new sound material according to the best practices of the industry.

Finished repairs shall match existing in materials, size, configuration and appearance.

Remove and reinstall any wall mounted items as required to maintain a weather-tight wall.

Install trim and clapboard siding with smooth side out.

Store materials so they remain clean and dry. Provide a waterproof and weatherproof protective cover over all work areas after existing roofing material has been removed and before new roofing is installed, to prevent interior damage to the buildings.

Work shall be performed only during dry weather conditions. Except as otherwise specified, work shall be performed only on dry surfaces. Prior to leaving for the day, all areas open to weather shall be made water and weather-tight until the commencement of work the next workday.

Apply the same products used in factory finish on all field cuts prior to installing cut material, in accordance with manufacturer’s recommendations.

Structural and framing repairs (if needed) After approval by COR, carefully excise rotten sections of sill and framing members. Leave keys to receive repairs, Replace rotten wood with dutchmen repairs. Apply reinforcing gussets as needed and fasten all with appropriate fasteners. Remove rotten framing members, key in repairs where needed, reinforce as needed.

Siding Take note of and measure exposure on existing siding in order to replicate with new siding. Cedar siding exposure shall match existing.

For cedar shingle siding, follow the installation procedures described in the Cedar Shake & Shingle Bureau Wall Manual unless otherwise indicated herein. For clapboard siding, follow the installation procedures described in Western Red Cedar Lumber Association literature.

Remove existing shingle siding down to bare wood substrate.

Preserve all existing wall sheathing in situ wherever possible using wood patching materials as described elsewhere in this document. Only as a last resort and only after approval by COR, replace damaged and rotted material with new sound material according to the best practices of the industry. Finished repairs shall match existing in materials, size, configuration and appearance.

Coordinate installation of siding with installation of water resistive barrier, rain screen, flashing and other adjoining work to ensure proper sequencing. Review flashing procedure with COR prior to installing any flashing. Install flashings around doors and windows and all other wall penetrations to remain to prevent moisture from entering the wall spaces. Complete flashings as required during and at the conclusion of siding. Install drip edges and other flashing as recommended by the siding manufacturer. Install Z flashing at bottoms of walls and all wall penetrations in accordance with manufacturer’s guidance. Install flashing at wall/roof and siding/trim interface in accordance with best practices of the industry and manufacturer’s guidance.

Install water-resistive barrier with penetration and junction flashing in accordance with local building code requirements and manufacturers applicable recommendations.

Before installing siding, install flashings around doors and windows and all other wall penetrations to remain to prevent moisture from entering the wall spaces. Complete flashings as required during and at the conclusion of siding. Install drip edges, self-adhering flashing and other flashing as recommended by the siding manufacturer. Install Z flashing at bottoms of walls and all wall penetrations in accordance with manufacturer’s guidance. Install flashing at wall/roof interface in accordance with best practices of the industry and manufacturer’s guidance.

Install shingle siding with exposure to match existing as recommended by the Cedar Shake & Shingle Bureau. Use two fasteners per shingle ¾” in from each edge and 1” above the butt line of the overlapping shingle, use 3 nails on shingles wider than 6”. Leave a keyway of at least 1/8” between shingles –shingles shall not touch. Joints of successive courses must be offset by at least 1 ½”.

Fasteners must penetrate underlayment at least ½”.

Window, sill/threshold, door, soffit, fascia, clapboard siding, trim and cornerboard repairs Verify actual extent of deteriorated wood at each location. Preserve all existing components in situ wherever possible. Only as a last resort and only after approval by COR, replace damaged and rotted material with new sound material according to the best practices of the industry. Finished repairs shall match existing in materials, size, configuration and appearance.

If deterioration is less than 1/8 inch deep, no repair is necessary. Fill area with wood patching material.

If deterioration is deeper than 1/8-inch, but less than half the depth of the member and/or less than 33-percent of the existing member is compromised/deteriorated, make epoxy repairs as recommended by epoxy manufacturer and as follows:

• Remove either with dry scraping or solvent-based chemical strippers all non-adhered, “alligatored” or heavily built-up paint down to sound paint and/or bare wood;

• Remove all paint, down to wood substrate, in the immediate vicinity of each repair;

• Ensure member to be repaired is clean and dry;

• Mix and use epoxy components in accordance with manufacturer’s instructions; for respective applications as consolidants, adhesives, and fillers. Add bulking agents (micro-balloons), in volumes not exceeding manufacturer's recommendations, to increase post-cure workability;

• After cure, dress repair to final shape, blending surface of repair to surface of original material without apparent joint.

Where deterioration is deeper than half the member and/or exceeds 33-percent of the existing member is compromised/deteriorated, provide Dutchman repairs or partial or full replace of existing member as approved by the COR, and as follows:

• Provide Dutchman repairs where wood is structurally compromised. Wood repairs will not be made for aesthetic purposes. Dutchman repairs shall provide continuous smooth surfaces matching planes and profiles of wood members being repaired. Dutchman shall match wood being repaired in species and cut. Grain pattern of Dutchman shall match grain pattern of wood into which it is inserted.

• Neatly cut out existing opening as required to provide a prismatic void. Create voids that will provide mechanical attachments as in dovetails to the greatest extent possible. The amount of wood removed should be minimized but the amount should include all deteriorated wood and extend just beyond damaged wood into sound substrate to prevent the spread of any fungus. Cut away area shall provide ample glue surface.

• Cut Dutchman to exactly fit void, with exposed portion matching original profile of woodwork and just slightly proud of original surface. Orient grain of Dutchman parallel to grain of element being patched.

• Where deterioration or loss at end of component requires Dutchman repair, use a diagonal scarf joint for end-to-end joint between Dutchman and remaining portion of component.

• Clean glue surfaces with acetone or denatured alcohol. Insert Dutchman using specified adhesive and clamp in place until glue is set. Where clamping is not feasible, use small brads; remove brads and fill holes after adhesive has set.

• Plane or scrape Dutchman to provide smooth continuous surface coplanar with adjacent wood.

Do not damage or alter profile or finish of adjacent wood.

• After cure, dress repair to final shape, blending surface of repair to surface of original material without apparent joint.

If depth of deterioration is greater than half the thickness of the member or exceeds 33-percent of the entire member and the deterioration cannot be repaired utilizing a Dutchman or epoxy methods, the entire member shall be replaced:

• Carefully remove fasteners at deteriorated member.

• Remove deteriorated member, taking care not to damage adjacent members.

• Remove adhesive residue and fasteners from adjacent members.

• Fabricate new members to match existing size, thickness, shape, and length. Wood shall be same species with configurations, profiles, dimensions and joinery exactly matching those of the existing elements. Machine and surface all new replacement wood elements to provide smooth even surfaces without saw marks or plane marks. Wood with surface irregularities, including but not limited to scratches, saw marks, and plane knife marks, visible after finish has been applied will be rejected and shall be replaced with properly finished wood elements at no additional cost.

• Replacement members shall be set square. Profiles and exterior surfaces shall be flush with adjacent surfaces.

For clapboard repairs, if needed, install clapboards with exposure to match existing and as recommended by the Western Red Cedar Lumber Association. Joints shall be feathered or square butted to match existing. Each succeeding course shall overlap the upper edge of the previous one by a minimum of 1 inch. The bottom of the board that is placed across the top of windows shall coincide with the window cap.

Finished repairs shall match existing in materials, size, configuration and appearance.

Barn doors Repair deteriorated sill and studs at gable end fixed barn door.

The contractor shall assess the condition of the barn doors to determine if repairs are necessary. Repair materials shall have the same dimensions and salient characteristics and shall function in the same manner as existing, with existing hardware to remain to the greatest extent possible. If repairs are necessary, follow procedures described above.

Lubricate sliding mechanisms on operational door with lithium grease to result in effort-free movement.

Windows Follow best practices regarding removal and replacement of windows. Remove existing windows in a manner to avoid damage to existing materials to remain. Repair any damaged surrounding material.

Install windows, complete with all flashings and locking hardware.

FRP double-swing interior pass-through doors Using the door manufacturer’s glass kit and following manufacturer’s recommendations, cut in and install new half-lite windows, one window per door.

Exterior finishes No exterior finishing shall be undertaken if air or surface temperature is below 50 degrees Fahrenheit or immediately following rain or until frost, dew or condensation has evaporated.

Remove damaged or deteriorated paint to the next sound layer using the gentlest method possible (e.g., hand scraping and hand sanding) prior to any necessary repairs and repainting.

All surfaces specified to be finished shall be wiped down with a dry cloth and be dry and cleaned free of all dirt, grit, grease, mold, mildew, foreign substances and all loose, peeling, blistering, chalking or scaling paint. Set all exposed nail heads. Sand to remove roughness, lose edges, slivers and splinters.

Clean and remove all dust as recommended by paint manufacturer.

Pressure wash all surfaces.

Apply primer and stain, each coat of stain shall be evenly worked out and allowed to dry according to the manufacturer’s recommendations before subsequent coats are applied. Apply number of coats necessary to achieve uniform coverage and appearance, two coats minimum, to match existing color.

Each coat of finish shall be evenly worked out and allowed to dry according to the manufacturer’s recommendations before subsequent coats are applied. Final finish shall have uniform finish, color, and appearance.

Roof treatment Prepare roof to receive stain in accordance with manufacturer of the finishing products to be used.

Apply two coats of stain, each coat shall be evenly worked out and allowed to dry according to the manufacturer’s recommendations before subsequent coats are applied. Apply number of coats necessary to achieve uniform coverage and appearance, two coats minimum. Final finish shall have uniform finish, color, and appearance.

Caulking All joints or gaps around doors, windows, baseboards or siding where water invasion may occur shall be filled with Benjamin Moore Elastomeric 465 01 Caulk, or an approved equivalent, not to be applied until primer coating is applied and allowed to dry a minimum of 24 hours.

Storage of Equipment and Materials The contractor shall be responsible for storage of all materials and equipment; the Park COR and / or Project Inspector must approve the contractor’s use of any space on the site in advance.

Upon completion of the work of this contract, the storage area shall be left broom clean by the contractor.

Clean-Up After completion of the work, construction debris, excess material and equipment shall be removed from the site and legally disposed. Use a magnet of sufficient strength to ensure no metal is left behind. Upon completion of the work of this contract, work areas shall be left broom clean by the contractor.

Period of Performance Pre-construction Meeting – Will be held once all the contract required documents, that are identified as being required to be submitted by the contractor prior to the Pre-constuction meeting being conducted, are either accepted/approved by the Government.

Notice to Proceed – Will be provided to the contractor after the Pre-construction Meeting.

Material Submittals – Due within 48 hours (or 2 business days) of Notice to Proceed.

Proposed completed work with all documentation submittals – 75 days after date on the Notice to Proceed.

Sketch Plan – not to scale

Repair fixed door, sills and studs

Install windows in interior double swing doors

Replace cedar siding on SW side

Repair and lubricate sliding door

Replace all windows

Map of Project Location

Project Location

Project Location