96565 NIFCO MECHANICAL B265.pdf

PDF 464 KB Posted

Attached to
NE|96565
Contract number
96565
Issued by
Nebraska

About this file

This is a State of Nebraska Purchase Order (PO #96565 X3) issued on August 4, 2026, by the Task Force for Building Renewal to Nifco Mechanical Systems Inc, a mechanical piping contractor located in Lincoln, Nebraska. The purchasing agency is the Nebraska State Building Division, with Gloria Eddins listed as the buyer. The order is directed to the First Nebraska Administrative Building located at 1526 K Street in Lincoln.

The contract covers replacement of storm drain piping at the First Nebraska Administrative Building's mezzanine level with a total order value of $12,920.00. The scope of work includes removal and disposal of approximately 90 feet of existing 6-inch cast iron storm drain piping and 25 feet of 4-inch cast iron storm drain piping, along with furnishing and installation of approximately 90 feet of 6-inch schedule 40 PVC DWV pipe and 25 feet of 4-inch schedule 40 PVC DWV pipe with fittings, connection to three existing 4-inch roof drains, installation of a 4-inch clean out, and 1-inch fiberglass pipe insulation. The proposal excludes sales tax, temporary utilities, concrete work, equipment protection, and painting. Materials are to be shipped FOB Destination, and the vendor is required to submit two copies of invoices and include a packing list with each shipment.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of Nebraska Purchase Order PURCHASE ORDER NUMBER 96565 X3

SHOW PURCHASE ORDER NUMBER ON ALL PAPERS AND PACKAGES INVOICE TO ADDRESS BELOW

PAGE ORDER DATE AS TASK FORCE FOR BLDG RENEWAL

1526 K ST STE 170

LINCOLN NE 68508-2741

1 OF 1 08/04/26

BUSINESS UNIT BUYER

6512B265 GLORIA EDDINS (AS)

VENDOR NUMBER: 500883 DESTINATION OF GOODS

AS TASK FORCE FOR BLDG RENEWAL

1526 K ST STE 170

LINCOLN NE 68508-2741

VENDOR ADDRESS:

NIFCO MECHANICAL SYSTEMS INC

500 BLUE HERON CT

LINCOLN NE 68522-1734

Unsatisfactory delivery schedule or service will be sufficient cause for cancellation of this order. Order is subject to cancellation if merchandise is not received by:

FREIGHT: FOB DESTINATION

DELIVERY INSTRUCTIONS:

INSTRUCTIONS TO VENDORS

* Packing list must be included in each shipment.

AGENCY SIGNATURE

R43500|NISA0002|NISA0002 20220623

* Two copies of invoice must be submitted in order that payment can be made - INVOICES

MUST INDICATE YOUR FEDERAL TAXPAYER IDENTIFICATION NUMBER.

* Materials ordered are subject to our inspection and approval. Defective material(s) not in compliance with specifications will be held pending resolution or returned subject to your risk and expense.

* Materials are to be shipped F.O.B. Destination.

Line Description Quantity Unit of

Measure Unit Price

Extended Price

1 FIRST NE ADMIN BUILDG 1526 12,920.0000 $ 1.0000 12,920.00

MEZZANINE DRAIN LINE REPLACE

Total Order 12,920.00

June 12, 2026

Nebraska state building Division

301 Centennial Mall

Lincoln, NE 68509

Attn: Cody Pollack

RE: 1526 K Street storm drain piping REVISED

Nifco Mechanical is pleased to submit our proposal for the above referenced project. We include the following includes and excludes.

Items Included:

• Remove and dispose of approximately 90’of existing 6” NH cast iron storm drain piping in North maintenance room

• Remove approximately 25’ of 4” cast iron storm drain in South maintenance room.

• Furnish and install approximately 90’ of 6” schedule 40 PVC DWV pipe and fittings.

• Furnish and install approximately 25’ of 4” schedule 40 PVC DWV pipe and fittings

• Connect to three existing 4” roof drains

• Furnish and install a 4” clean out in 6” horizontal piping.

• Furnish and install 1” fiberglass pipe insulation

Items Excluded:

• Anything not specifically listed in the inclusions above.

• Temporary Utilities or sanitary facilities

• Concrete cutting, removal or replacement

• Protection of owner equipment or furnishings.

• All painting, including piping.

General Conditions to this proposal:

• This proposal excludes sales tax for all materials and equipment.

• All agreements must be made in writing.

• This proposal expires in 30 days.

Base Price $ 12,920.00

If bond is required add 1% to base bid.

Respectfully submitted, Project Manager

Nifco Mechanical

File details come from the government source that posted it. Updated .