This is a State of Nebraska Purchase Order (PO #96565 X3) issued on August 4, 2026, by the Task Force for Building Renewal to Nifco Mechanical Systems Inc, a mechanical piping contractor located in Lincoln, Nebraska. The purchasing agency is the Nebraska State Building Division, with Gloria Eddins listed as the buyer. The order is directed to the First Nebraska Administrative Building located at 1526 K Street in Lincoln.
The contract covers replacement of storm drain piping at the First Nebraska Administrative Building's mezzanine level with a total order value of $12,920.00. The scope of work includes removal and disposal of approximately 90 feet of existing 6-inch cast iron storm drain piping and 25 feet of 4-inch cast iron storm drain piping, along with furnishing and installation of approximately 90 feet of 6-inch schedule 40 PVC DWV pipe and 25 feet of 4-inch schedule 40 PVC DWV pipe with fittings, connection to three existing 4-inch roof drains, installation of a 4-inch clean out, and 1-inch fiberglass pipe insulation. The proposal excludes sales tax, temporary utilities, concrete work, equipment protection, and painting. Materials are to be shipped FOB Destination, and the vendor is required to submit two copies of invoices and include a packing list with each shipment.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Nebraska Purchase Order PURCHASE ORDER NUMBER 96565 X3
SHOW PURCHASE ORDER NUMBER ON ALL PAPERS AND PACKAGES INVOICE TO ADDRESS BELOW
PAGE ORDER DATE AS TASK FORCE FOR BLDG RENEWAL
1526 K ST STE 170
LINCOLN NE 68508-2741
1 OF 1 08/04/26
BUSINESS UNIT BUYER
6512B265 GLORIA EDDINS (AS)
VENDOR NUMBER: 500883 DESTINATION OF GOODS
AS TASK FORCE FOR BLDG RENEWAL
1526 K ST STE 170
LINCOLN NE 68508-2741
VENDOR ADDRESS:
NIFCO MECHANICAL SYSTEMS INC
500 BLUE HERON CT
LINCOLN NE 68522-1734
Unsatisfactory delivery schedule or service will be sufficient cause for cancellation of this order. Order is subject to cancellation if merchandise is not received by:
FREIGHT: FOB DESTINATION
DELIVERY INSTRUCTIONS:
INSTRUCTIONS TO VENDORS
* Packing list must be included in each shipment.
AGENCY SIGNATURE
R43500|NISA0002|NISA0002 20220623
* Two copies of invoice must be submitted in order that payment can be made - INVOICES
MUST INDICATE YOUR FEDERAL TAXPAYER IDENTIFICATION NUMBER.
* Materials ordered are subject to our inspection and approval. Defective material(s) not in compliance with specifications will be held pending resolution or returned subject to your risk and expense.
* Materials are to be shipped F.O.B. Destination.
Line Description Quantity Unit of
Measure Unit Price
Extended Price
1 FIRST NE ADMIN BUILDG 1526 12,920.0000 $ 1.0000 12,920.00
MEZZANINE DRAIN LINE REPLACE
Total Order 12,920.00
June 12, 2026
Nebraska state building Division
301 Centennial Mall
Lincoln, NE 68509
Attn: Cody Pollack
RE: 1526 K Street storm drain piping REVISED
Nifco Mechanical is pleased to submit our proposal for the above referenced project. We include the following includes and excludes.
Items Included:
• Remove and dispose of approximately 90’of existing 6” NH cast iron storm drain piping in North maintenance room
• Remove approximately 25’ of 4” cast iron storm drain in South maintenance room.
• Furnish and install approximately 90’ of 6” schedule 40 PVC DWV pipe and fittings.
• Furnish and install approximately 25’ of 4” schedule 40 PVC DWV pipe and fittings
• Connect to three existing 4” roof drains
• Furnish and install a 4” clean out in 6” horizontal piping.
• Furnish and install 1” fiberglass pipe insulation
Items Excluded:
• Anything not specifically listed in the inclusions above.
• Temporary Utilities or sanitary facilities
• Concrete cutting, removal or replacement
• Protection of owner equipment or furnishings.
• All painting, including piping.
General Conditions to this proposal:
• This proposal excludes sales tax for all materials and equipment.
• All agreements must be made in writing.
• This proposal expires in 30 days.
Base Price $ 12,920.00
If bond is required add 1% to base bid.
Respectfully submitted, Project Manager