AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE

DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

Terri N Tutt, Contracting Officer

Quoter Question MCC Response

Is there any flexibility regarding the start date or due date of the deliverable for task 1a? We have two key personnel on leave in February, so would be requesting a revised due date for the end of March/mid-April.

Yes, in this particular requirement, as long as the full team is ready to mobilize within 90 days of award, this will not be a disqualifying factor.

The RFQ states that ‘if MCC requires ongoing support for more than one phase of project development, a single project may have more than one country-level due diligence engagement’ (p.15). We understand this as meaning that a single Compact engagement would not cover multiple phases of a program but that it could still cover multiple sectors included in the Compact. Is that correct?

In general, the goal of both MCC and the eventual awardee should be that of focused, specific engagements in the Compact/Threshold Development process. In general, that will mean narrowing to a single sector, but it is not impossible that a country team may request to explore opportunities in more than one of the sectors in consideration.

Is it possible to include in the team an expert who already has contracts with MCC or its contractors?

Yes, as long as there is no Conflict of Interest.

Is there a cost ceiling or estimated range for the budget? Section B (page 6) references “unrestricted NAICS Code 541611 Size Standard $15 million” while on the forecast this opportunity was listed as a range of $150,000 - 699,999.

The MCC business forecast is estimated information, however, the governments is aware costs may exceed this estimate. The size standards are for the most part expressed in either millions of dollars (those preceded by “$”) or number of employees (those without the “$”). A size standard is the largest that a concern can be and still qualify as a small business for Federal Government programs. For the most part, size standards are the average annual receipts or the average employment of a firm.

Per L.3.2 (page 48), at least one of the past performance references should be from the proposed Team Lead or subcontractor. Does this mean that a project performed by the proposed Team Leader, but not by the prime or sub contractor, may be submitted?

Corrected: If proposing a contractor teaming arrangements (CTA) or subcontractor, at least one of the past performance projects performed by the CTA or subcontractor.

In some places the RFP refers to Morocco and/or Sierra Leone, and in other places it refers to francophone West Africa. Could MCC please confirm the anticipated countries or region(s) in which the work will be conducted? How many countries are envisioned?

The number of country due diligence engagements under Task 2 is already specified in the RFQ.

Morocco and Sierra Leone are ongoing RBF projects which may be analyzed under Tasks 3-5, but will almost certainly not be countries where Task 2 due diligence engagements will be launched. While not a foregone conclusion, the number of Francophone West African countries in MCC's portfolio is the reason for references to French language proficiency and experience in the region.

What is the size limit of the submission file? No, however the submission needs to not exceed the limit to submit an electronic file.

Are we able to bring in partners/subs for this opportunity? Yes.

9 Is MCC expected to have fully loaded labor rate for subcontractor personnel? Yes, if they re being proposed for a key or non key position.

Is markup allowed on the subcontracting budget line item? Can we include our negotiated indirect rates and fee in the subcontractor cost?

Price Quote should be in accordance with your accouting pratices as noted in your audited financial statements or your approved NICRA. Documentation of such rates shall be included with your submission.

Solicitation 95332419Q0020

95332419Q0020 Amendment 0001.pdf
Sheet1
Text52:
Text54: 1
Check Box91: Yes
Check Box92: Off
Check Box95: Yes
Check Box96: Off
Check Box97: Off
Check Box98: Off
Check Box99: Off
Check Box100: Off
Check Box101: Off
CUST_PROJ_CODE:
NO_OF_COPIES:
TOTAL_NO_OF_PAGES: 2
Text1: AMENDMENT CONTROL NUMBER :
AMENDMENT_DESCRIPTION: The purpose of this amendment is to provide responses to questions received.
Text134: SUMMARY OF CHANGES :
SOL_DOCUMENT_NUMBER: 95332419Q0020
OPEN_BIDDING_DATE: 12/11/2018
Text2: Same As Issuing Office
SOL_OPEN_BID_DATE: 2018-11-30T12:20:45.000-07:00
AMD_ISSUING_OFFICE_LADDR:
AMD_ISSUING_OFFICE_LOCCODE:
CLOSE_DATE_EXTEND_FLAG: N
HDR_DOCUMENT_NUMBER: 95332419Q00200001