Contract Summary

This is an AIA Document A101-2017 Standard Form of Agreement Between Owner and Contractor on a stipulated sum basis, executed on April 15, 2026, between the Board of Trustees of the Nebraska State Colleges d.b.a. Wayne State College (Owner) and Murray Roofing, LLC (Contractor). The project is the Studio Arts Building Roof Replacement located at Wayne State College, 1111 Main Street, Wayne, Nebraska 68787. The architect is Jackson-Jackson & Associates, Inc. The contract is governed by Nebraska law and incorporates AIA Document A201-2017 General Conditions of the Contract for Construction.

The contract sum is $170,000.00 for complete roof replacement work, including removal of existing deteriorated 2x6 wood blocking at $8.00 per linear foot. Work commencement is no sooner than Monday, May 11, 2026, with substantial completion required by Friday, July 24, 2026, and final completion by Friday, July 31, 2026. Progress payments are made monthly based on architect certification, subject to 10% retainage until substantial completion. The contractor must provide performance and payment bonds equal to 100% of the contract amount, commercial general liability insurance with $1,000,000 per occurrence limits, and property insurance covering the project value. Final payment is due within 30 days of the architect's final certificate, in accordance with the Nebraska Prompt Payment Act. The contract includes supplementary conditions dated March 20, 2026, and references comprehensive specifications and drawing documents detailing demolition, roofing systems, and architectural requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .