89503121QWA000149 - Amendment 01.pdf

PDF 188 KB Posted

Attached to
WAPA/DSW Cooling Tower 1 Replacement
Solicitation number
89503121QWA000149
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

89503121QWA000149

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PHOENIX AZ 85005-6457

DSW

PO BOX 6457

DESERT SOUTHWEST REGIONAL OFFICE

US DOE/WESTERN AREA POWER

WAPA (DSW)

06/01/20210001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/14/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

See Continuation Page for Amendment Details

Sol. 89503121QWA000149 Amendment 0001

The purpose of this amendment is to clarify the RFQ due date, how quotes are to be submitted, correct information in block 10, and answer Contractor submitted questions.

A. The date and time set for receipt of quotes is June 07, 2021 at 2:00 PM (Local AZ) time.

Please submit your quotes via email to dreed@wapa.gov prior to the due date and time.

B. Replace “Chiller” with “Cooling Tower” in block 10 of the solicitation. This requirement is for the acquisition and installation of a Cooling Tower in accordance with the Statement of Work.

C. Please see the answers to the following questions:

1. Will WAPA be bringing in its own chiller controls vendor to set up the controls interface with the new cooling tower?

Answer: No, this is a turn-key project, so the expectation is for the contractor to ensure interface, see paragraphs J and K under section 2 REQUIREMENTS.

2. Building code requires electrical disconnects on cooling towers but the existing towers do not have disconnects. Do we need one on the new cooling tower?

Answer: Yes, all current and applicable codes and standards will be followed. See paragraph e, Section 5 CONSIDERATIONS.

3. Attachment A, Scope of Work, page 4, paragraph 2.B.c. says the new cooling tower is to sit within the existing footprint for the cooling towers but page 7 includes a photo 1c of possible new location. What is the intent regarding location of the new cooling tower?

Answer: 1c is an alternative location that the tower can be located if the existing footprint does not meet the technical requirements of the new tower proposed by the low offeror.

D. All other conditions remain unchanged.

mailto:dreed@wapa.gov

File details come from the government source that posted it. Updated .