Summary Attachment H: HOC Financial Support Services; Monthly Report Part 1
Month & Year:
| Task | Task Description | Number of Transmittals | Number of Lines |
| 1 | Vendor Transmittal Processing | | |
| 2 | General HOC Transmittal Processing | | |
| 3 | Tax Transmittal Processing | | |
| Totals | | |
| HOC | Transmittal Type | Unit | Number Received | Number Recommended for Approval or Rejection | Number Recommended for Rejection by SSC | Number Rejected by HUD staff | Number Where HUD Staff Did Not Agree with SSC Recommendation | Contractor Comments Regarding each transmittal on which HUD did not agree with contractors recommendation |
| AHOC | SAM | Transmittal | | | | | | |
| SFS | Transmittal | | | | | | |
| SMC | Transmittal | | | | | | |
| SFF | Transmittal | | | | | | |
| | Lines | | | | | | |
| SFT | Transmittal | | | | | | |
| | Lines | | | | | | |
| DHOC | SAM | Transmittal |
| SFS | Transmittal |
| SMC | Transmittal |
| SFF | Transmittal |
| | Lines |
| SFT | Transmittal |
| | Lines |
| PHOC | SAM | Transmittal |
| SFS | Transmittal |
| SMC | Transmittal |
| SFF | Transmittal |
| | Lines |
| SFT | Transmittal |
| | Lines |
| SAHOC | SAM | Transmittal |
| SFS | Transmittal |
| SMC | Transmittal |
| SFF | Transmittal |
| | Lines |
| SFT | Transmittal |
| | Lines |
Vendor Transmittal
| | | Monthly Billing By HOC | | | |
| HUD Received Date / Contract area | Contractor Received Date | Contractor | Transmittal Number | Transmittal Total | Date recommended for rejection | Date Completed - PR |
| 3-A | | | | | |
Final Count 0 $0.00
Final Count Total 0 $0.00
General HOC Count by date
| HUD Received Date | Contractor Received Date | Transmittal Number | Transmittal Total | # line items | Reject Count | Date Rejected/PR | Date Updated to PR Status | Comments |
| 11/28/17 | 11/28/17 | SFF8A1800058 | $2,368.57 | 5 | 5 | 12/01/17 | 12/01/17 | |
| 11/28/17 | 11/28/17 | SFF8A1800059 | $5,065.00 | 36 | | | 12/01/17 | |
| 11/30/17 | 11/30/17 | SFF4A1800018 | $17,500.00 | 50 | | | 12/04/17 | |
| 11/30/17 | 11/30/17 | SFF4A1800019 | $5,250.00 | 15 | | | 12/01/17 | |
| HOC Area | Transmittal Count | Line Count |
| 3A | 12 | 295 |
| 4A | 12 | 266 |
| 5A | 3 | 125 |
| 6A | 11 | 215 |
| 7A | 12 | 183 |
| 8A | 21 | 435 |
| HA | 20 | 104 |
| Total | 91 | 1623 |
| HOC Area | Line Count |
| 3A | 252 |
| 4A | 190 |
| 5A | 270 |
| 6A | 331 |
| 7A | 140 |
| 8A | 528 |
| HA | 50 |
| Total | 1761 |
Taxes
| HUD Received Date | SSC Received Date | Transmittal Number | Transmittal Total | # line items | Recommend for Rejection Count | Date Updated to PR Status | Comments |
| 11/30/17 | 11/30/17 | SFT4A1800076 | $1,299.65 | 1 | 1 | 12/01/17 | |
| 11/30/17 | 11/30/17 | SFT6A1800022 | $719.16 | 2 | | 12/04/17 | |
| 11/30/17 | 11/30/17 | SFT6A1800023 | $506.54 | 1 | | 12/04/17 | |
| 11/30/17 | 11/30/17 | SFT6A1800024 | $389.20 | 2 | | 12/04/17 | |
| TOTALS | | | $2,914.55 | 6 | 1 | | |
| Contract Area | Transmittal Count | Line Count | | | | | |
| 3A | 1 | 2 | | | | | |
| 4A | 1 | 1 | | | | | |
| 5A | 63 | 104 | | | | | |
| 6A | 70 | 145 | | | | | |
| 7A | 1 | 1 | | | | | |
| 8A | 0 | 0 | | | | | |
| Total | 136 | 253 | | | | | |