This is an Invitation to Bid (IFB) issued by the City of Danville, Virginia for asbestos abatement and demolition services across eight properties located at 635 Shelton Street, 647 Randolph Street, 319 Richmond Avenue, 933 Keister Street, 213 Vance Street, 214 Vance Street, 1407 Washington Street, and 1014 Washington Street. The City is soliciting bids for complete asbestos abatement and/or demolition work on each individual structure, with awards to be made to the lowest responsible grand total bid for all structures or to the contractor completing the work in the least amount of days, regardless of cost. A mandatory pre-bid walk-through is scheduled for October 1, 2026 at 9:00 AM, beginning at 635 Shelton Street and proceeding through all eight addresses in the specified order. Sealed bids are due on October 22, 2026 at 11:00 AM and must be submitted to Carol Henley, Purchasing Director, at the City of Danville Purchasing Department. The contractor shall begin work within 48 hours of receiving the Notice to Proceed and must complete all asbestos abatement and demolition within twenty calendar days plus the time required for proper notifications, with liquidated damages assessed at $250 per consecutive calendar day for delays.
Bidders must submit cost proposals for each individual structure, separately invoiced to enable property-specific liens, along with the number of days required to complete each project and the number of days needed to remove friable asbestos if present. The contractor is responsible for obtaining all permits, including asbestos abatement permits, demolition permits (fee of $102), and excavation permits for contracts under $50,000, which require a $20,000 bond. For contracts exceeding $50,000, a 5% bid bond with the proposal and 100% performance and payment bonds upon award are required. The contractor must comply with all federal, state, and local regulations, transport asbestos-containing materials to Virginia Department of Environmental Quality-approved disposal sites, and provide clearance letters and waste disposal records separated by property address. Upon completion, the contractor must perform lot restoration including fine grading, fill-in of disturbed areas, seeding with specified seed mixtures, lime and fertilizer application, straw mulching, and installation of erosion control measures. All documentation and waste records should be submitted to Seth R. Hawker, Property Maintenance Code Supervisor, at the City of Danville Inspections Division.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF DANVILLE ASBESTOS ABATEMENT AND
DEMOLITION PROJECTS
GROUP BID COVERSHEET
The attached write-up is part of a group bid. Listed below are all addresses included in the group bid. The addresses are also listed in order for the scheduled walk-thru.
NOTE: 1 below is a group bid and both bid forms need to be in one envelope when submitted to Purchasing.
BID # 26-27-016
The walk-thru will be in this order:
1. 635 Shelton St October 01, 2026 @ 9:00 AM
2. 647 Randolph St
3. 319 Richmond Ave
4. 933 Keister St
5. 213 Vance St
6. 214 Vance St
7. 1407 Washington St
8. 1014 Washington St
If you have any questions, please call me.
Seth R. Hawker Property Maintenance Code Supervisor hawkesr@danvilleva.gov
(434) 799-5260 ext. 2493
CITY OF DANVILLE ASBESTOS ABATEMENT AND
DEMOLITION PROJECTS
INVITATION TO BID: ASBESTOS ABATEMENT AND DEMOLITION
Demolition 26-27-016 (Project #131) Date: September 18, 2026
Address: 635 Shelton St, 647 Randolph St, 319 Richmond Ave, 933 Keister St, 213 Vance St, 214 Vance St, 1407 Washington St, 1014 Washington St
Walk-Thru Date: October 01, 2026 at 9:00 am (follow attached walk thru schedule) Bids due: October 22, 2026 at 11:00 am
ASBESTOS REPORT AND OR DESIGN SPECIFICATIONS
• BIDDING: Bids shall be made for each individual structure. Awards will be made to the lowest responsible grand total bid for all structures. Awards may also be determined by the contractor that completes the work in the least amount of days, regardless of costs.
The award will be made to the proposal conforming to the IFB and will be most advantageous to the City. Bid amounts must be provided for each structure and must be invoiced separately so that a lien may be placed on each property.
Bidders shall complete and submit the attached Bid Proposal containing:
1. Complete asbestos abatement and/or demolition costs.
2. Number of days to complete each project if different than the proposed timeframe.
3. Number of days to remove friable asbestos, if present, for each project.
The proposed cost, and number of days to complete each project (if different than the proposed timeframe) will be considered in determining the lowest responsive and responsible bidder, in addition to all applicable evaluation criteria as listed in Danville City Code § 30-50.
Any Bid Proposal submitted in response to this Invitation to Bid constitutes an offer to contract incorporating all terms included in this Invitation. By submitting a Bid Proposal, each bidder agrees to execute a contract (an “Agreement”) incorporating all such terms if selected as the winning bidder (“the Contractor”). This Invitation may be modified by one or more Addenda, the terms of which are incorporated into this Invitation as if fully laid out herein.
These projects are subject to change in ownership and other legal issues at any time that could result in putting a project on hold temporarily or indefinitely.
BIDS ARE TO BE SEALED AND SUBMITTED BY MAIL OR HAND DELIVERY
Fill out the attached bid form and submit to:
Carol Henley, Purchasing Director, City of Danville Purchasing Department 427 Patton St. Room 304 Danville, VA 24541 434-799-6528 opt. 4
I. GENERAL REQUIREMENTS: Upon selection as the winning bidder, the Contractor agrees to the following:
1. The Contractor agrees to comply with the City of Danville’s “Standard Instructions and Requirements for Bids,” the terms of which are incorporated into this Invitation as if laid out fully herein.
2. The Contractor represents that the Contractor and any subcontractors hold all licenses and certifications required by any applicable law to perform the work specified in this Invitation. The City may void any contract with a Contractor who fails to hold a license or certification required by this Section.
3. The Contractor shall submit the required notifications to the Department of Labor and Industry (DOLI) and any other agency required to be notified upon receiving the Notice to Proceed.
4. The Contractor shall furnish all labor, equipment, supervision, and incidentals necessary to provide asbestos abatement and/or demolition for each authorized property.
5. The Contractor shall be responsible for obtaining an asbestos abatement permit, demolition permit, and any other required permit from the City of Danville Inspections Division. The asbestos permit fee is based on the cost of the job and the demolition permit is $102.00.
6. Excavation Permit Required for Contracts less than $50,000. The successful contractor shall use the utmost care to not damage the City right-of-way during the performance of the work or during the transportation of equipment, materials, debris, etc. to or from the project site. The successful contractor is required to obtain an Excavation Permit from the City of Danville Department of Public Works before Notice to Proceed is issued to the contractor if the value of the work is less than $50,000. Public Works will inspect the right-of-way for any damage caused by the contractor during all phases of the work. Items in the City right-of-way that will be inspected include, but are not limited to, streets, pavement markings, guardrails, driveway entrances, signs, mailboxes, curbs, gutters, sidewalks, shoulders, roadside ditches, vegetation, storm drain systems, sanitary sewer systems, and utilities. The permit fee will initially be waived conditioned upon satisfactory performance; however, the contractor must obtain a bond (or similar surety) in the amount of $20,000 before the Excavation Permit can be issued. If right-of-way damage is discovered, the contractor will be responsible for repair of any damage in the right-of-way to the satisfaction of the Department of Public Works, the conditional waiver of the permit fee will be revoked, and the permit holder shall be liable to pay a permit fee in an amount based on the discovered damage and, if the contractor fails to repair the identified damage to the satisfaction of the Department of Public Works, the City will correct the damage and the contractor shall be responsible for all associated costs not otherwise covered by the permit fee.
A copy of the contractor’s certificate of insurance, with the City of Danville named as an additional insured, shall also be kept on file with the permit.
Once the contractor has completed the contracted work and any subsequent repair work, and has removed all equipment from the site, a final inspection will be performed. If no damage is found to the City right-of-way, and if any previously identified damage has been corrected to the satisfaction of the Department of Public Works, the Excavation Permit will be closed and the contractor’s Excavation Permit bond released. More information about the Excavation Permit can be found HERE. As part of the bidding process, the contractor should account for the costs to secure the bond required by this section.
7. The Contractor shall follow all local, state and federal laws for all asbestos abatement and/or demolition projects. The Contractor is responsible for all permits related to the project.
8. The Contractor shall transport all friable asbestos containing material (RACM) and non-friable asbestos-containing material (ACM) to a disposal site approved by the Virginia Department of Environmental Quality (DEQ).
9. The Contractor shall transport and dispose of any material containing contaminants regulated by federal, state, or local regulation in accordance with federal, state, and local regulations. (The landfill that services the Danville area is First Piedmont Industrial Landfill, 1224 Clarks Mill Road, Ringgold, VA 24586.)
II. REQUIRED FOR RELEASE OF PAYMENT: The Contractor shall cause all of the following conditions to be satisfied before release of payment:
1. The Contractor must provide a clearance letter from the environmental consultant that prepared the asbestos survey and/or performed the monitoring and submit it to the City of Danville Inspections Division. The letter must state the structure is clear for demolition.
http://www.danville-va.gov/605/Permit-Information
2. All waste disposal records must be separated by property address (address must be visible on ticket) and submitted to the City of Danville Inspections Division.
Waste tickets are required for all asbestos-containing waste and any other material containing contaminants regulated by federal, state, or local regulation that was disposed.
3. The contractor/owner is responsible for the disconnection of the sewage pipe prior to any demolition to prevent deleterious material from entering the public sewer main.
• The building sewer shall be capped in the yard outside of the building with an appropriately sized combination fitting of an approved material and cleanout brought to a minimum of 12 inches above grade. Capped at top and bottom with like material.
• Public Works shall be notified by phone (434)-799-5245 to schedule an inspection before the pipe is covered. Inspection must be prior to demolition and covering the pipe and fittings.
4. The attached Salvage Materials List must be filled out, signed, and submitted to the City of Danville Inspections Division. All materials that were salvaged must be included on this list.
5. Any damage to public improvements must be noted and submitted to the City of Danville Inspections Division.
6. All street and public sidewalk cleanup must be complete.
7. When an invoice is submitted, the City of Danville has at least 30 days to pay the invoice. Do not call and ask for payment until after the 30 days has passed and all other requirements have been met.
8. At a minimum, the following erosion and sediment controls are required to be utilized in accordance with the standards of the City of Danville Erosion and Sediment Control Ordinance: stone construction entrance at all points of egress;
silt fence installed at the lower side of all disturbed areas; temporary seeding on disturbed areas that are left dormant for more than 30 days; and permanent seeding on all disturbed areas within 7 days after final grade is achieved.
III. SCOPE OF WORK: The Contractor shall perform all of the following duties in compliance with the terms outlined in its submitted Bid Proposal and any other applicable terms:
1. ASBESTOS ABATEMENT:
a. The Contractor shall remove all asbestos-containing material according to the asbestos survey report and/or design specifications prepared for this project and in compliance with all EPA, OSHA, and DOLI regulations, and any other applicable law, using best practices. Recommendations are located in the survey report and/or design specifications prepared for this project.
b. The Contractor shall contact the environmental contractor that prepared the asbestos survey report to schedule a final clearance inspection. Contact information for the asbestos contractor is located on the survey reports. Asbestos must be removed on all buildings prior to contacting the testing agency.
c. The Contractor shall submit the required notifications to the Department of Labor and Industry (DOLI), and any other agency required to be notified, upon notice to proceed and is responsible for all associated costs.
d. The Contractor shall furnish all labor, equipment, supervision, and incidentals necessary to provide complete asbestos abatement for each authorized property.
e. The Contractor shall follow all state, federal, local codes and ordinances for all asbestos abatement projects. The Contractor is responsible for all permits related to the project being addressed.
f. The Contractor shall transport all friable asbestos containing material (RACM) and non-friable asbestos-containing material (ACM) to a disposal site approved by the Virginia Department of Environmental Quality (DEQ). (The landfill that services the Danville area is First Piedmont Industrial Landfill, 1224 Clarks Mill Road, Ringgold, VA 24586.)
g. If it is determined that a Contractor has disposed of asbestos containing material in a disposal location not permitted by the Commonwealth of Virginia, DEQ will be contacted to investigate the disposal site that was used.
h. If a project monitor is used, The Contractor shall be responsible for all costs associated with the use of the project monitor.
i. Any additional cleaning required after the final cleaning will be performed at the expense of the Contractor. Additional hours and sample costs required by the project monitor will be at the expense of the Contractor if the initial or subsequent final air samples fail.
j. The Contractor shall be responsible for any costs for additional clearance inspections if the initial clearance inspection fails. The Contractor is not responsible for the initial clearance inspection performed by the environmental contractor.
k. If a contract to perform work on multiple structures is awarded in accordance with this Invitation to Bid, to help save costs, the Contractor agrees that all asbestos work will be completed on each structure before requesting for a testing agency to make final inspection and before demolition work begins on any structure.
2. DEMOLITION:
a. The Inspections Office shall send a utility release form to have water, gas, electric, and any applicable utilities disconnected.
b. The contractor is responsible for the disconnection of the sewage pipe.
- The building sewer shall be capped in the yard outside of the building with an appropriately sized combination fitting of an approved material and cleanout brought to a minimum of 12 inches above grade. Capped at top and bottom with like material.
- Public Works shall be notified by phone (434)-799-5245 to schedule an inspection before the pipe is covered. Inspection must be prior to demolition and covering the pipe and fittings.
c. Prior to any work, the Contractor shall contact Miss Utility to locate any underground utilities that may be present in the demolition area.
d. The contractor shall provide to the Inspections Office a copy of the final asbestos clearance inspection prior to conducting any demolition work.
e. The Contractor shall remove all footings, basement walls, basement floors, tires, concrete slabs, asphalt, poles, posts, non-public sidewalks, stairs, etc.
f. The Contractor is required to use water for dust control during demolition.
g. All work performed shall be in accordance with the Virginia Uniform Statewide
Building Code and the instructions of the City's Contract Administrator or designee.
h. The Contractor shall completely remove all debris resulting from the demolition, including any contents left inside structure and any miscellaneous items on the premises. Any material containing contaminants regulated by federal, state, or local regulation must be disposed in accordance with federal, state, and local regulations.
i. The Contractor shall provide evidence of disposal, including the disposal location.
Manifests must be provided for disposal of all demolition materials including lead, asbestos, and any other hazardous materials.
j. The Contractor shall remove all accessory structures, drive ways, trees, parking lots, fences, fence posts, retaining walls, and any other items on the property, at the direction of the City’s Contract Administrator or designee.
k. The Contractor shall conduct septic tank and well abandonment, per Virginia Health Department (434-432-7232) regulations, on a case-by-case basis, at the direction of the City’s Contract Administrator or designee.
l. All curb-cut driveway entrances shall remain intact.
m. Any separation of private sidewalks, driveways, stairs, tires, retaining walls, slabs, or any other private materials from any public improvements shall be cleanly separated without damage to public improvements.
n. All public streets, gutters, and sidewalks shall be clean of debris, dirt and mud during and at the completion of each project.
o. Protection of City Right-of-Way and Responsibility for Damage. The Contractor shall protect all adjacent properties and the City of Danville right-of-way, including but not limited to pavements, roadways, medians, sidewalks, curbs, gutters, landscaping, and all public and private utilities and appurtenances, whether shown on the plans or not. The Contractor shall be fully responsible for any damage to City right-of-way or public improvements caused by its operations, equipment, employees, or subcontractors. Any damage resulting from the Contractor’s work shall be repaired or replaced at the Contractor’s sole expense and in a manner acceptable to the City of Danville Public Works Department. All such repairs or replacements shall be completed promptly and to the same or better condition as existed prior to the start of work, as determined by the City. The Contractor’s required insurance coverage and performance bond shall be directly applicable to the correction, repair, or replacement of any damage to City property or right-of-way resulting from the Contractor’s work. In the event the Contractor fails or refuses to make timely or satisfactory repairs, the City may perform or cause to be performed the necessary corrective work and recover all associated costs from the Contractor, including by claim against the Contractor’s insurance and/or performance bond. No separate payment will be made for the protection, repair, or replacement of City right-of-way, public improvements, or adjacent properties. All costs associated with such protection and restoration shall be considered incidental to the work and included in the Contractor’s bid. For contracts less than $50,000, an Excavation Permit shall be issued (see Item #6 under General Requirements).
p. The Contractor shall remove the metal UNSAFE STRUCTURE signs and return them to the City of Danville Inspections Division without damage.
3. LOT RESTORATION: The Contractor shall agree to perform lot restoration to the following requirements upon completion of asbestos abatement and/or demolition work:
a. The Contractor shall call the Inspections Division for the lot to be inspected before any seed or straw is distributed.
b. The Contractor shall fine grade the property to re-establish the grade and slope of the property to match the adjacent properties and remove all mounds, low areas, large rocks, roots, or ruts caused by equipment tracks or tires using a Soil Pulverizer or like equipment designed to loosen, pulverize, and level packed or encrusted soils in preparation for seeding. Areas that are not accessible with such equipment must be raked out by hand to prepare the soil for seeding. The lot and all disturbed areas associated with the demolition shall be left in a maintainable condition using a residential mower
c. The Contractor shall fill-in any areas disturbed by demolition including basements, accessory structures, driveways, sidewalks, stairs, retaining walls, fence posts and any other items included in the project with properly compacted clean fill dirt.
d. A correctly restored lot shall match the grade of the adjacent properties and be fine graded. The lot shall be left so it may be maintained using a residential mower.
e. Contractor shall stabilize all disturbed areas by seeding and mulching so as to reestablish vegetative ground cover for all disturbed areas. Seeding will be required on all denuded or disturbed areas not paved in this project and shall be installed in accordance with Standard & Specification 3.32 in the Virginia E&S Handbook.
f. Lime and Fertilizer. Lime and fertilizer needs should be determined by soil tests which may be performed by the Cooperative Extension Service Soil Testing Laboratory at VPI & SU or by any other reputable commercial laboratory. Where no test is performed, the following soil amendments will be required:
i. Lime. 3 tons/acre of pulverized agricultural limestone (140 lb.
/1,000 sf.)
ii. Fertilizer. 1,000 lb. /acre of 10-20-10 blend plus 300 lb. /acre of 38-0-0
g. Seed. Lots must be permanently seeded in such a manner as to establish permanent vegetative cover. A 50%-50% seed mixture of 8-10 pounds per acre of inoculated white clover (Trifolium repens) and 8-10 pounds per acre of an annual ryegrass (Lolium perenne) shall be used to establish permanent vegetative cover.
Seeds bearing a “Certified Seed” label from the Virginia Crop Improvement Association, or a similar agency from another state, must be used when possible.
h. Straw. All seeded areas shall be mulched in accordance with Standard & Specification 3.35 in the Virginia Erosion and Sediment Control Handbook.
i. 70-90lbs of straw per 1000sq/ft. of disturbed area
i. Contractor shall install appropriate perimeter erosion control measures, where necessary and as determined by the Contract Administrator, to prevent site runoff damage to adjoining properties or to the public right-of-way in accordance with the Virginia Erosion & Sediment Control Handbook.
IV. TIMEFRAME FOR COMPLETION; LIQUIDATED DAMAGES:
1. The Contractor shall begin asbestos abatement process and/or demolition within 48 hours of receipt of the Notice to Proceed. The Notice to Proceed will include a final date of completion determined by adding twenty (20) days for proper notifications and by the average number of days from past demolitions.
2. The City of Danville may deduct liquidated damages in the amount of two hundred fifty dollars ($250.00) for each consecutive calendar day the asbestos abatement and/or demolition goes beyond the stated date of completion. Consecutive calendar days will include weekends and holidays. The City will consider time delays for projects halted by the City, weather, natural disasters, declared emergencies, and other events outside of the control of the Contractor.
V. EQUIPMENT: The Contractor shall maintain all equipment in compliance with all federal, state and local regulations.
VI. BONDS:
1. Upon the award of any public construction contract exceeding fifty thousand dollars ($50,000) to a prime contractor, such Contractor shall furnish to the City a 5% bid bond with its Bid Proposal and a 100% performance bond and a 100% payment bond if awarded the contract.
2. Each bond required by this section shall be executed by one or more surety companies selected by the Contractor that is legally authorized to do business in the Commonwealth. Bonds required by this section shall be made payable to the City and shall be filed with the City of Danville Inspections Division. In lieu of a performance or payment bond required by this section, a contractor may furnish a certified check or cash escrow in the face amount required for the bond, such check to be returned or destroyed at the conclusion of the retainage period or when final asbestos removal is certified by inspections department.
VII. SALVAGE: The Contractor shall be permitted to salvage building materials from demolition projects under the following conditions:
1. Salvaging material may not cause any delay of project completion.
2. Only materials approved by DEQ may be salvaged. The DEQ Regional
Enforcement Representative may be contacted as follows:
Regional Enforcement Representative Department of Environmental Quality 3019 Peters Creek Road Roanoke, VA 24019
(540) 562-6700 (540 562-6725 (fax)
3. The Contractor must submit a list of items that are being salvaged and the location these items are to be taken. (See attached “Salvage Materials List.”)
4. Salvaged items must be sold offsite.
5. The salvage material list and any landfill records will be submitted to DEQ for review by the Regional Enforcement Representative.
6. The City makes no representation or guarantee regarding the availability of any anticipated salvageable property or materials. In submitting a bid, the Contractor assumes all risk of loss resulting from the unavailability of any anticipated salvageable property or materials.
7. The City makes no representation as to the ownership of any property or material collected by the Contractor for salvage under this section. The Contractor assumes all risk of liability in conducting any salvage activities.
VIII. BILLING: The Contractor agrees to bill for services as follows:
1. If structures are grouped together for bid, invoices must be separated by property.
This itemized invoice is for the purpose of repayment and lien that will be filed with the court.
2. Any invoice shall be itemized showing:
a. The cost for the demolition, removal of the structure, and fill dirt for that structure.
b. The cost for all other tasks included in the bid, for example (removal of driveways, sidewalks, retaining walls, fences, etc.)
IX. MODIFICATION: The Parties agree that the Agreement entered into pursuant to this Invitation may be modified by mutual agreement to the fullest extent permitted by the Virginia Public Procurement Act, the Danville City Code, and any other applicable law.
Modifications may, but need not, take the form of additional Addenda to this Invitation.
X. INDEMNITY. The Contractor agrees as follows:
1. General indemnity. To the fullest extent permissible by law the Contractor shall indemnify and hold harmless the City, its agents, officers, and employees, from any and all liability from all claims for damages, loss, injury, or death to any third party, or the property of any third party, arising from any occurrence relating to performance of the Contractor’s duties.
2. Environmental indemnity. To the fullest extent permissible by law, the Contractor agrees to indemnify and hold harmless the City from any and all loss, liability, or expense (including attorneys’ fees or expenses) arising out of any environmental liability relating to the performance of the Contractor’s duties. “Environmental liability” shall include without limitation any claim, demand, obligation, cause of action, accusation, allegation, order, violation, damage, injury, judgment, penalty, fine, cost of enforcement, cost of remedial action, or any other cost or expense whatsoever, resulting from the violation or alleged violation of any environmental law which relates to the performance of the Contractor’s duties. “Environmental law” includes, without limitation, any federal, state, or local law, regulation, or order related to environmental matters, including, without limitation, matters related to air pollution or water pollution, noise control, or the handling, discharge, disposal, or recovery of any hazardous or toxic substances or materials, including, without limitation, asbestos and lead.
XI. WAIVER OF LIABILITY: To the fullest extent permissible by law, the City will not be responsible for any damage, injury, or loss to the Contractor, its employees, agents, or subcontractors, resulting from any cause whatsoever.
XII. DISCRIMINATION: In any contract for services of more than $10,000, the Contractor agrees as follows:
1. The Contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex or national origin, except where religion, sex or national origin is a bona fide occupational qualification reasonably necessary to the normal operation of the Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.
2. The Contractor will state they are an equal opportunity employer in all solicitations or advertisements for employees placed by or on behalf of the Contractor.
3. Notices, advertisements, and solicitations placed in accordance with applicable federal laws, rules, and regulations are sufficient to meet the requirements of this section.
4. A Contractor subject to this section shall include the provisions set out in Subsections 1-3 of this Section in every subcontract or purchase order of over ten thousand dollars ($10,000.00), such that the same provisions will be binding upon each subcontractor or vendor.
XIII. DRUG-FREE WORKPLACE: In any contract for services of more than $10,000, the Contractor shall agree as follows:
1. The Contractor shall provide a drug-free workplace for its employees.
2. The Contractor shall post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor’s workplace, and specifying the actions taken against employees for violations of such provision.
3. The Contractor shall state in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a drug-free workplace.
4. The Contractor must include the provisions set out Subsections 1-3 of this Section in any subcontract or purchase order of over $10,000, such that the same provisions will be binding upon each subcontractor or vendor.
XIV. IMMIGRATION. The Contractor agrees that in performing any obligation under any contract formed pursuant to this Invitation, the Contractor shall not knowingly employ an unauthorized alien, as that term is defined in the federal Immigration Reform and Control Act of 1986.
XV. AUTHORIZATION TO CONDUCT BUSINESS IN VIRGINIA. The following provisions shall apply to any bidder submitting a Bid Proposal and any Contractor to which a contract is awarded:
1. Any Contractor organized as a stock or nonstock corporation, limited liability company, business trust, or limited partnership, or that is registered as a limited liability partnership, must be authorized to transact business in the Commonwealth of Virginia as a domestic or foreign business entity, if such entity is so required by Title 13.1 or Title 50 of the Virginia Code, or is otherwise required to do so by law.
2. Any Contractor described in Subsection 1 of this Subsection which is required to be authorized to transact business in the Commonwealth of Virginia by Title 13.1 or Title 50 of the Virginia Code must include in the attached Bid Proposal the identification number issued to it by the State Corporation Commission.
3. Any Contractor described in Subsection 1 of this Subsection which is not required to be authorized to transact business in the Commonwealth of Virginia by Title 13.1 or Title 50 of the Virginia Code shall include in the attached Bid Proposal a statement describing why such Contractor is not required to be so authorized.
4. No contract may be awarded to any bidder not in compliance with the requirements of Subsection 1-3 of this Section, unless a waiver of this requirement is granted by the City Manager of the City of Danville, Virginia.
5. Any Contractor required to seek authorization to transact business in the Commonwealth of Virginia by Title 13.1 or Title 50 shall not allow its existence to lapse, allow its certificate of authority or registration to be cancelled or revoked, at any time during the term of a contract entered into pursuant to this Invitation.
6. The City may void any contract with a Contractor which is in violation of any part of this Section.
XVI. RELATIONSHIP OF PARTIES: No part of the Agreement between the City and the Contractor shall be construed so as to create a relationship of agency, employment, joint venture, or partnership. Neither party may exercise authority to create any obligation, debt, or liability on behalf of the other party, nor represent to any other entity that the party enjoys such authority. Neither party shall be responsible for any obligation, debt, or liability created in violation of this Agreement.
XVII. THIRD-PARTY BENEFICIARIES: No part of the Agreement shall be intended, nor shall it be deemed, to confer any right or remedy upon any person not a party to this Agreement.
XVIII. NON-WAIVER: No waiver of any provision of the Agreement shall be deemed a continuing or further waiver of the same provision, or a waiver of any other provision.
XIX. AUTHORITY TO CONTRACT: Only the City Manager of the City of Danville, independently or through the Director of Purchasing as his designee, has authority to obligate the City for the order or purchase of any services or supplies, except that the Director of Purchasing may be assisted by assigned buyers in the execution of these duties. Any contract, debt, liability, or other obligation created in violation of this provision is void and unenforceable against the City.
XX. SEVERABILITY: If any provision of the Agreement shall be held invalid or unenforceable by a court, the invalidity or unenforceability of such provision shall not affect any other provision of that Agreement, and the Agreement shall be construed as if the invalid or unenforceable clause was not contained therein. Should the enforceability of any provision of the Agreement be called into question, such provision shall be construed as the mutual agreement of the Parties to the fullest extent permitted by law.
XXI. CONFLICT OF TERMS: Should there arise any error, discrepancy, or conflict between or among any provision of this Invitation, the Agreement, or any other governing document, such terms and documents will be given precedence in the following order:
1. The Agreement;
2. Any Modifications, Amendments, or Supplementary Conditions to the Agreement;
3. This Invitation to Bid and Bid Proposal;
4. Any Addenda to the Invitation to Bid or Bid Proposal; and
5. The City of Danville Standard Requirements & Instructions for Bidding.
XXII. HEADINGS: The descriptive headings herein are inserted for convenience only and do not constitute a part of this Agreement.
XXIII. COUNTERPARTS: Any Agreement entered into pursuant to this Invitation may be executed in one (1) or more counterparts, each of which shall be deemed an original but all of which together shall constitute one and the same Agreement.
XXIV. CONSTRUCTION: The Parties agree that this agreement shall be construed according to the laws of the Commonwealth of Virginia.
PROPERTY INFORMATION:
You can access property information and maps from the City of Danville website:
https://experience.arcgis.com/experience/31951e30986b44a1aa066c3b2f636a1f/pa ge/Map
Submit all required documents, invoices, and waste records to:
Seth R. Hawker, PMO City of Danville Inspections Division P.O. Box 3300 Danville, VA 24543 Fax: (434) 797-8919 Phone: (434) 799-5260 ext. 2493 Email: hawkesr@danvilleva.gov
| BIDS ARE TO BE SEALED AND SUBMITTED BY MAIL OR HAND DELIVERY |
| 4. The attached Salvage Materials List must be filled out, signed, and submitted to the City of Danville Inspections Division. All materials that were salvaged must be included on this list. |
| 5. Any damage to public improvements must be noted and submitted to the City of Danville Inspections Division. |
| 6. All street and public sidewalk cleanup must be complete. |
| 1. ASBESTOS ABATEMENT: |
| 2. DEMOLITION: |
| 3. LOT RESTORATION: The Contractor shall agree to perform lot restoration to the following requirements upon completion of asbestos abatement and/or demolition work: |
| IV. TIMEFRAME FOR COMPLETION; LIQUIDATED DAMAGES: |
| V. EQUIPMENT: The Contractor shall maintain all equipment in compliance with all federal, state and local regulations. |
| VIII. BILLING: The Contractor agrees to bill for services as follows: |