Westminster, Abbey, and Upshur Stormwater Management Upgrades - Invitation to Bid

This is an Advertisement of Invitation to Bid and Contract Documents issued by the Town of Berlin, Department of Water Resources, in Worcester County, Maryland, for stormwater management upgrades. The project encompasses the furnishing of all labor, materials, equipment, and appurtenances necessary for the complete demolition, construction, and testing of stormwater management improvements located along Westminster Drive, Abbey Lane, and Upshur Lane in Berlin, Maryland. Sealed hard copy and electronic bids will be received until 1:30 p.m. EDT on August 26, 2026, at the Berlin Visitor Center, 13 S. Main Street, Berlin, Maryland 21811, with electronic submissions directed to mbohlen@berlinmd.gov, kdaub@berlinmd.gov, and info@berlinmd.gov. A non-mandatory pre-bid meeting has been scheduled for 2:00 p.m. on July 23, 2026, at the Berlin Police Station, 129 Decatur Street, Berlin, Maryland. The bid opening will occur at 2:00 p.m. on August 26, 2026, at the same police station location. Bid documents are available electronically on the Town of Berlin website at https://berlinmd.gov/government/request-for-proposals/. Hard copies are not available. The Notice of Award will be issued within thirty days of bid opening, and the contract will be effective upon execution by both parties. The contract does not specify a renewal option.

The successful bidder will be the lowest qualified, responsible, and responsive bidder as determined by the Town of Berlin. Bid security of five percent of the maximum bid price must accompany all submissions in the form of a certified or bank check or bid bond. Liquidated damages are set at one thousand dollars per day as specified in the Agreement. Performance and payment bonds are required as set forth in Article 6 of the Standard General Conditions. Contract time for substantial completion and final completion is to be indicated in the Bid Form and Agreement, with the contractor responsible for submitting an itemized construction schedule outlining activities from notice to proceed through project completion. All required permits must be obtained and paid for by the contractor. The contract incorporates the EJCDC C-700 Standard General Conditions of the Construction Contract (2018 Edition), and all inquiries shall be directed to Steven Lemasters, P.E., Project Manager at EA Engineering, Science, and Technology, Inc., PBC, telephone 410-641-5341, or kdaub@berlinmd.gov.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADVERTISEMENT OF INVITATION TO BID

WESTMINSTER, ABBEY, AND UPSHUR

STORMWATER MANAGEMENT UPGRADES

TOWN OF BERLIN, MARYLAND

Electronic and/or sealed hard copy proposals will be received by the Mayor and Council of Berlin, Worcester County, Maryland, at the Berlin Visitor Center located at 13 S. Main Street, Berlin, Maryland 21811 until 1:30 p.m., on 26 August 2026 for the WESTMINSTER, ABBEY, AND UPSHUR STORMWATER MANAGEMENT UPGRADES.

Electric submissions are to be sent to mbohlen@berlinmd.gov, kdaub@berlinmd.gov, and info@berlinmd.gov. Hard copies are to be submitted at the Berlin Visitor Center located at 13 S.

Main Street, Berlin, MD 21811. The bid opening will occur at 2:00pm on 26 August 2026 at the Berlin Police Station located at 129 Decatur Street, Berlin, MD 21811 where the proposals will be opened publicly and read aloud.

Potential bidders are encouraged to attend the non-mandatory Pre-Bid Meeting which will be held on 23 July 2026, at 2:00 p.m. at the Berlin Police Station located at 129 Decatur Street, Berlin, Maryland.

Bid documents are available on the Town of Berlin website https://berlinmd.gov/government/request-for-proposals/.

All inquiries shall be directed to Steven Lemasters, P.E., Project Manager, EA Engineering, Science, and Technology, Inc., PBC at 410-641-5341.

mailto:kdaub@berlinmd.gov mailto:info@berlinmd.gov https://berlinmd.gov/government/request-for-proposals/

This page intentionally left blank

Contract Documents and Construction Specifications

Town of Berlin

Westminster, Abbey, and Upshur Stormwater Management Upgrades

Prepared for

Department of Water Resources

10 William Street Berlin, Maryland 21811

Prepared by

EA Engineering, Science, and Technology, Inc., PBC 11200 Racetrack Road, Unit A101

(410) 641-5341

July 2026 EA Project No. 61470410

Contract Documents and Construction Specifications

Westminster, Abbey, and Upshur Stormwater Management Upgrades

Prepared for

Department of Water Resources

10 William Street

Prepared by

EA Engineering, Science, and Technology, Inc., PBC 11200 Racetrack Road, Unit A101

(410) 641-5341

July 2026 2024 EA Project No. 61470410

Table of Contents (page 1 of 2)

TABLE OF CONTENTS

SECTION A: INSTRUCTIONS TO BIDDERS

Advertisement for Bids Instructions to Bidders

SECTION B: GENERAL CONDITIONS OF THE CONTRACT

Standard General Conditions of the Construction Contract

SECTION C: SUPPLEMENTARY CONDITIONS

Supplementary Conditions

SECTION D: BONDS AND BID FORMS

Proposal Bond Performance Bond Payment Bond Bid Form Notice of Award Agreement Between Owner and Contractor Notice to Proceed Contractor’s Application for Payment Form Change Order Certificate of Substantial Completion

SECTION E: SPECIFICATIONS

DIVISION 1 – GENERAL REQUIREMENTS

SECTION 01 10 00 SUMMARY OF WORK

SECTION 01 20 00 MEASUREMENT AND PAYMENT

SECTION 01 33 00 SUBMITTALS

SECTION 01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS

DIVISION 2 – SITEWORK

SECTION 02 11 00 CLEARING AND GRUBBING

SECTION 02 25 00 TRENCH EXCAVATION, BACKFILL, AND COMPACTION

SECTION 02 41 16 DEMOLITION

SECTION 02 74 10 ASPHALT PAVING

SECTION 02 80 00 RESTORATION

DIVISION 3 – CONCRETE

SECTION 03 00 00 CONCRETE

Table of Contents (page 2 of 2)

SECTION 03 05 16 PRECAST CONCRETE STRUCTURES

SECTION 03 10 00 CONCRETE FORMS AND ACCESSORIES

SECTION 03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 31 – EARTHWORK

SECTION 31 05 15 EARTHWORK

SECTION 31 05 16 AGGREGATES

SECTION 31 25 00 EROSION AND SEDIMENT CONTROL

DIVISION 32 – EXTERIOR IMPROVEMENTS

SECTION 32 92 00 LAWNS AND GRASSES

DIVISION 33 – UTILITIES

SECTION 33 31 00 PIPING AND APPURTENANCES

SECTION F: DRAWINGS (Bound Separately)

G-001 TITLE SHEET

G-002 ABBREVIATIONS, NOTES, LEGEND, AND SITE DATA

C-101 EXISTING CONDITIONS AND DEMOLITION PLAN

C-102 PROPOSED SITE AND STORMWATER MANAGEMENT PLAN

C-103 PROPOSED PLANTING PLAN

C-201 PROFILES

C-202 PROFILES

C-501 DETAIL SHEET I

C-502 DETAIL SHEET II

C-503 DETAIL SHEET III

C-504 DETAIL SHEET IV

C-701 EROSION AND SEDIMENT CONTROL PLAN

C-702 EROSION AND SEDIMENT CONTROL NOTES

C-703 EROSION AND SEDIMENT CONTROL DETAILS

SECTION G: FIGURE 1 – PROPOSED STORM DRAIN PLAN BID ALTERNATE 1

Section A

Instructions to Bidders

Instructions to Bidders (page 1 of 8)

INSTRUCTIONS TO BIDDERS

1. DEFINED TERMS

Terms used in these Instructions to Bidders, which are defined in the Standard General Conditions of the Construction Contract, have the meanings assigned to them in the General Conditions. The term “Bidder” means one who submits a Bid directly to Owner, as distinct from a Sub-Bidder, who submits a Bid to a Bidder. The term “Successful Bidder” means the lowest, qualified, responsible and responsive Bidder to whom Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award. The term “Bidding Documents” includes the Advertisement of Invitation to Bid, Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). The “Owner” shall be defined as “Town of Berlin – Department of Water Resources”

2. COPIES OF BIDDING DOCUMENTS

A. Complete electronic sets of the Bidding Documents may be obtained from the Town of Berlin’s website at https://berlinmd.gov/government/request-for-proposals/. Hard copies of the bid documents are not available.

B. Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

C. Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use.

3. QUALIFICATIONS OF BIDDERS

To demonstrate qualifications to perform the Work, each Bidder must be prepared to submit within five (5) days of Owner’s request, written evidence, such as financial data, previous experience, present commitments, and other such data, as may be called for below (or in the Supplementary Conditions). Each Bid must contain evidence of the Bidder’s qualifications to do business in the state where the project is located or a covenant to obtain such qualification prior to award of the Contract.

4. EXAMINATION OF CONTRACT DOCUMENTS AND SITE

A. It is the responsibility of each Bidder before submitting a Bid, to (a) examine the Contract Documents thoroughly; (b) visit the site to become familiar with local conditions that may affect cost, progress, performance or furnishing of the Work; (c) consider federal, state, and local laws and regulations that may affect cost, progress, performance, or furnishing of the Work, (d) study and carefully correlate Bidder’s observations with the Contract Documents; and (e) notify Owner and Engineer of all conflicts, errors, or discrepancies in the Contract Documents.

https://berlinmd.gov/government/request-for-proposals/

Instructions to Bidders (page 2 of 8)

B. Reference is made to the Supplementary Conditions for identification of:

1. Those reports of explorations and tests of subsurface conditions at the site which have been utilized by Engineer in preparation of the Contract Documents. Bidder may rely upon the accuracy of the technical data contained in such reports, but not upon nontechnical data, interpretations, or opinions contained therein or for the completeness thereof for the purposes of bidding or construction.

2. Those drawings of physical conditions in or relating to existing surface and subsurface conditions (except Underground Facilities) which are at or contiguous to the site which have been utilized by Engineer in preparation of the Contract Documents. Bidder may rely upon the accuracy of the technical data contained in such drawings, but not upon the completeness thereof for the purposes of bidding or construction.

3. Copies of such reports and drawings will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the technical data contained therein, upon which Bidder is entitled to rely as provided in Paragraphs 4.B.1 and 4.B.2, are incorporated therein by reference. Such technical data have been identified and established in the Supplementary Conditions.

C. Information and data reflected in the Contract Documents, with respect to Underground Facilities at or contiguous to the site, is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities or others, and Owner does not assume responsibility for the accuracy or completeness thereof, unless it is expressly provided otherwise in the Supplementary Conditions.

D. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders on subsurface conditions, Underground Facilities, and other physical conditions, and possible changes in the Contract Documents due to differing conditions appear in Paragraphs 4.B and 4.C of the General Conditions.

E. Before submitting a Bid, each Bidder will, at Bidder’s own expense, make or obtain any additional examinations, investigations, explorations, tests, and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance, or furnishing of the Work and which Bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price, and other terms and conditions of the Contract Documents.

F. On request in advance, Owner will provide each Bidder access to the site to conduct such explorations and tests as each Bidder deems necessary for submission of a Bid. The bidder shall fill all holes, clean up, and restore the site to its former condition upon completion of such explorations.

G. The lands upon which the Work is to be performed, rights-of-way and easements for access thereto and other lands designated for use by the Contractor in performing the

Instructions to Bidders (page 3 of 8)

Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by Contractor.

H. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences, or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

5. INTERPRETATIONS AND ADDENDA

A. All questions about the meaning or intent of the Contract Document are to be directed to Engineer. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda, mailed or delivered to all parties, and recorded by Engineer as having received the Bidding Documents. Questions received less than ten (10) days prior to the date for opening Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

B. Addenda may also be issued to modify the Bidding Documents as deemed advisable by Owner or Engineer.

6. BID SECURITY

A. Each Bid must be accompanied by Bid security made payable to Owner in an amount of five (5) percent of the Bidder’s maximum Bid price and in the form of a certified or bank check or a Bid Bond, issued by a surety meeting the requirements of Paragraph 5.A of the General Conditions.

B. The Bid security of the Successful Bidder will be retained until such Bidder has executed the Agreement and furnished the required contract security, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Agreement and furnish the required contract security within ten (10) days after the Notice of Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of the seventh day after the Effective Date of the Agreement or the sixty-first day after the Bid opening, whereupon Bid security furnished by such Bidders will be returned. Bid security with Bids which are not competitive will be returned within seven (7) days after the Bid opening.

Instructions to Bidders (page 4 of 8)

7. CONTRACT TIME

The numbers of days within which, or the dates by which, the Work is to be substantially completed and also completed and ready for final payment (the Contract Time) are set forth in the Bid Form and the Agreement.

8. LIQUIDATED DAMAGES

Provisions for liquidated damages are $1,000 per day, as set forth in the Agreement.

9. SUBSTITUTE OR “OR-EQUAL” ITEMS

The Contract, if awarded, will be on the basis of materials and equipment described in the Drawings or specified in the Specifications without consideration of possible substitute or “or-equal” item. Substitute or “or-equal” materials or equipment may be furnished or used by Contractor if acceptable to Engineer; application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by Engineer is set forth in Article 7 of the General Conditions and may be supplemented in the General Requirements.

10. SUBCONTRACTORS, SUPPLIERS, AND OTHERS

If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, and other persons and organizations (including those who are to finish the principal items of material and equipment) to be submitted to Owner in advance of the specified date prior to the Effective Date of Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within seven (7) days after the Bid opening submit to Owner a list of all such Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, person, or organization if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, other person or organization, Owner may request the apparent Successful Bidder to submit an acceptable substitute prior to the Notice of Award, in which case that Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11. BID FORM

A. The Bid Form (Form of Proposal) is included with the Bidding Documents; additional copies may be obtained from Owner.

B. All blanks on the Bid Form must be completed in ink or typed. All blanks on the Bid Form must be completed; use N/A or a dashed line to indicate items that are not applicable.

Instructions to Bidders (page 5 of 8)

C. Bids by corporations must be executed in the corporate name by the president or a vice-president (or other corporate officer accompanied by evidence of authority to sign) and the corporate seal must be affixed and attested by the secretary or an assistant secretary.

The corporate address and state of incorporation must be shown below the signature.

D. Bids by partnerships must be executed in the partnership name and signed by a partner, whose title must appear under the signature and the official address of the partnership must be shown below the signature.

E. All names must be typed or printed below the signature.

F. The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of which must be filled in on the Bid Form).

G. The address and telephone number for communications regarding the Bid must be shown.

H. The name, address, and telephone number of the laboratory to perform testing must be provided on the Bid Form.

12. SUBMISSION OF BIDS

Bids shall be submitted before 1:30 p.m. (EDT) on 26 August 2026. Electronic and hard copy submissions are both acceptable. Electric submissions are to be sent to mbohlen@berlinmd.gov, kdaub@berlinmd.gov, and info@berlinmd.gov. Hard copies are to be submitted at the Berlin Visitor Center located at 13 S. Main Street, Berlin, MD 21811 shall be enclosed in an opaque, sealed envelope, marked with the Project title, and name and address of the Bidder and accompanied by the Bid security and other related documents. If the Bid is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope. The notation “BID ENCLOSED: TOWN OF BERLIN – WESTMINSTER, ABBEY, AND UPSHUR STORMWATER MANAGEMENT UPGRADES” on the face of it.

13. MODIFICATION AND WITHDRAWAL OF BIDS

Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids.

14. OPENING OF BIDS

The bid opening will occur at 2:00pm on 26 August 2026 at the Berlin Police Station located at 129 Decatur Street, Berlin, MD 21811.

An abstract of the amounts of the base Bids and major alternates will be made available to Bidders after the opening of Bids.

mailto:kdaub@berlinmd.gov mailto:info@berlinmd.gov

Instructions to Bidders (page 6 of 8)

15. BIDS TO REMAIN SUBJECT TO ACCEPTANCE

All bids will remain subject to acceptance for sixty (60) days after the day of the Bid opening, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to that date.

16. AWARD OF CONTRACT

A. Owner reserves the right to reject any and all Bids, to waive any and all informalities not involving price, time, or changes in the Work and to negotiate Contract terms with the Successful Bidder, and the right to disregard all nonconforming, nonresponsive, unbalanced or conditional Bids. Also, Owner reserves the right to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive, or the Bidder is unqualified or of doubtful financial ability, or fails to meet any other pertinent standard or criteria established by Owner. Discrepancies in the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

B. In evaluating Bids, Owner will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other date, as may be requested in the Bid Form or prior to the Notice of Award.

C. Owner may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Supplementary Conditions. Owner also may consider the operating costs, maintenance requirements, performance data, and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award.

D. Owner may conduct such investigations, as Owner deems necessary, to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to Owner’s satisfaction within the prescribed time.

E. If the Contract is to be awarded, it will be awarded to the lowest Bidder whose evaluation by Owner indicates that the award will be in the best interests of the Project.

F. If the Contract is to be awarded, Owner will give the Successful Bidder a Notice of Award within thirty (30) days after the day of the Bid opening.

17. CONTRACT SECURITY

Article 6.01 of the General Conditions and the Supplementary Conditions set forth Owner’s requirements as to performance and payment Bonds. When the Successful Bidder delivers the

Instructions to Bidders (page 7 of 8) executed Agreement to Owner, it must be accompanied by the required performance and payment Bonds.

18. SIGNING OF AGREEMENT

When Owner gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement with other written Contract Documents attached. Within five (5) days thereafter, Contractor shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner with the required Bonds. Within five (5) days thereafter, Owner shall deliver one fully signed counterpart to Contractor. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification.

19. PREBID CONFERENCE

A prebid conference will be held at 11:00 a.m. (EDT) on 23 July 2026 at the Berlin Police Station located at 129 Decatur Street, Berlin, MD 21811. Representatives of the Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. The engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference.

20. PERMITS

All required permits shall be obtained and paid for by Contractor and are hereby made a part of this contract.

21. RETAINAGE

Provisions concerning retainage are set forth in the AGREEMENT.

22. AWARD OF BIDS/ALTERNATES

The successful Bidder, for purpose of contract award, shall be the conforming responsible Bidder offering the low unit price bid for the Base Bid Items. After the successful Bidder has been determined by this method, Owner reserves the right to select alternates out of the listed sequence and to make award for only those items so selected and to accept any or all of the balance of the alternates within sixty (60) days of award of the Contract.

23. CONTACT SCHEDULE

All Bidders are required to submit an itemized construction schedule outlining activities from the notice to proceed through project completion. In addition to the completed Bid Form and Bonds, and required bid documents, the Town reserves the right to evaluate the qualified bids based on the construction schedule.

Instructions to Bidders (page 8 of 8)

24. INSTRUCTIONS TO BIDDERS – INDEX

Page

1. DEFINED TERMS

2. COPIES OF BIDDING DOCUMENTS

3. QUALIFICATIONS OF BIDDERS

4. EXAMINATION OF CONTRACT DOCUMENTS AND SITE

5. INTERPRETATIONS AND ADDENDA

6. BID SECURITY

7. CONTRACT TIME

8. LIQUIDATED DAMAGES

9. SUBSTITUTE OR “OR-EQUAL” ITEMS

10. SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11. BID FORM

12. SUBMISSION OF BIDS

13. MODIFICATION AND WITHDRAWAL OF BIDS

14. OPENING OF BIDS

15. BIDS TO REMAIN SUBJECT TO ACCEPTANCE

16. AWARD OF CONTRACT

17. CONTRACT SECURITY

18. SIGNING OF AGREEMENT

19. PREBID CONFERENCE

20. PERMITS

21. RETAINAGE

22. AWARD OF BIDS/ALTERNATES

23. CONTACT SCHEDULE

24. INSTRUCTIONS TO BIDDERS – Index

Section B

General Conditions of the Contract

EJCDC® C-700, Standard General Conditions of the Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

This document has important legal consequences; consultation with an attorney is encouraged with respect to its use or modification. This document should be adapted to the particular circumstances of the contemplated Project and the controlling Laws and Regulations.

STANDARD GENERAL CONDITIONS

OF THE CONSTRUCTION CONTRACT

Prepared By

Endorsed By

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Copyright© 2018

National Society of Professional Engineers

1420 King Street, Alexandria, VA 22314-2794

(703) 684-2882 www.nspe.org

American Council of Engineering Companies

1015 15th Street N.W., Washington, DC 20005

(202) 347-7474 www.acec.org

American Society of Civil Engineers

1801 Alexander Bell Drive, Reston, VA 20191-4400

(800) 548-2723 www.asce.org

The copyright for this EJCDC document is owned jointly by the three sponsoring organizations listed above. The National Society of Professional Engineers is the Copyright Administrator for the EJCDC documents; please direct all inquiries regarding EJCDC copyrights to NSPE.

NOTE: EJCDC publications may be purchased at www.ejcdc.org, or from any of the sponsoring organizations above.

http://www.nspe.org/ http://www.acec.org/ http://www.asce.org/ http://www.ejcdc.org/

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Guidelines Page 1 of 2

GUIDELINES FOR USE OF EJCDC® C-700,

STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT

1.0 PURPOSE AND INTENDED USE OF THE DOCUMENT

EJCDC® C-700, Standard General Conditions of the Construction Contract (2018), is the foundation document for the EJCDC Construction Series. The General Conditions define the basic rights, responsibilities, risk allocations, and contractual relationship of the Owner and Contractor, and establish how the Contract is to be administered.

2.0 OTHER DOCUMENTS

EJCDC documents are intended to be used as a system and changes in one EJCDC document may require a corresponding change in other documents. Other EJCDC documents may also serve as a reference to provide insight or guidance for the preparation of this document.

These General Conditions have been prepared for use with either EJCDC® C-520, Agreement Between Owner and Contractor for Construction Contract (Stipulated Price), or EJCDC® C-525, Agreement Between Owner and Contractor for Construction Contract (Cost-Plus-Fee) (2018 Editions). The provisions of the General Conditions and the Agreement are interrelated, and a change in one may necessitate a change in the other.

To prepare supplementary conditions that are coordinated with the General Conditions, use EJCDC® C-800, Supplementary Conditions of the Construction Contract (2018).

The full EJCDC Construction series of documents is discussed in the EJCDC® C-001, Commentary on the 2018 EJCDC Construction Documents (2018).

3.0 ORGANIZATION OF INFORMATION

All parties involved in a construction project benefit significantly from a standardized approach in the location of subject matter throughout the documents. Experience confirms the danger of addressing the same subject matter in more than one location; doing so frequently leads to confusion and unanticipated legal consequences. Careful attention should be given to the guidance provided in EJCDC® N-122/AIA® A521, Uniform Location of Subject Matter (2012 Edition) when preparing documents.

EJCDC® N-122/AIA® A521 is available at no charge from the EJCDC website, www.ejcdc.org, and from the websites of EJCDC’s sponsoring organizations.

If CSI MasterFormat™ is used for organizing the Project Manual, consult CSI MasterFormat™ for the appropriate document number (e.g., under 00 11 00, Advertisements and Invitations), and accordingly number the document and its pages.

4.0 EDITING THIS DOCUMENT

Remove these Guidelines for Use. Some users may also prefer to remove the two cover pages.

Although it is permissible to revise the Standard EJCDC Text of C-700 (the content beginning at page 1 and continuing to the end), it is common practice to leave the Standard EJCDC Text of C-700 intact and unaltered, with modifications and supplementation of C-700’s provisions set forth in EJCDC® C-800, Supplementary Conditions of the Construction Contract (2018). If the Standard Text itself is revised, the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Guidelines Page 2 of 2 user must comply with the terms of the License Agreement, Paragraph 4.0, Document-Specific Provisions, concerning the tracking or highlighting of revisions. The following is a summary of the relevant License Agreement provisions:

1. The term “Standard EJCDC Text” for C-700 refers to all text prepared by EJCDC in the main body of the document. Document covers, logos, footers, instructions, or copyright notices are not Standard EJCDC Text for this purpose.

2. During the drafting or negotiating process for C-700, it is important that the two contracting parties are both aware of any changes that have been made to the Standard EJCDC Text. Thus, if a draft or version of C-700 purports to be or appears to be an EJCDC document, the user must plainly show all changes to the Standard EJCDC Text, using “Track Changes” (redline/strikeout), highlighting, or other means of clearly indicating additions and deletions.

3. If C-700 has been revised or altered and is subsequently presented to third parties (such as potential bidders, grant agencies, lenders, or sureties) as an EJCDC document, then the changes to the Standard EJCDC Text must be shown, or the third parties must receive access to a version that shows the changes.

4. Once the document is ready to be finalized (and if applicable executed by the contracting parties), it is no longer necessary to continue to show changes to the Standard EJCDC Text. The user may produce a final version of the document in a format in which all changes are accepted, and the document at that point does not need to include any “Track Changes,” redline/strikeout, highlighting, or other indication of additions and deletions to the Standard EJCDC Text.

5.0 LICENSE AGREEMENT

This document is subject to the terms and conditions of the License Agreement, 2018 EJCDC® Construction Series Documents. A copy of the License Agreement was furnished at the time of purchase of this document, and is available for review at www.ejcdc.org and the websites of EJCDC’s sponsoring organizations.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 1 of 5

STANDARD GENERAL CONDITIONS

OF THE CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1—Definitions and Terminology

1.01 Defined Terms

1.02 Terminology

Article 2—Preliminary Matters

2.01 Delivery of Performance and Payment Bonds; Evidence of Insurance

2.02 Copies of Documents

2.03 Before Starting Construction

2.04 Preconstruction Conference; Designation of Authorized Representatives

2.05 Acceptance of Schedules

2.06 Electronic Transmittals

Article 3—Contract Documents: Intent, Requirements, Reuse

3.01 Intent

3.02 Reference Standards

3.03 Reporting and Resolving Discrepancies

3.04 Requirements of the Contract Documents

3.05 Reuse of Documents

Article 4—Commencement and Progress of the Work

4.01 Commencement of Contract Times; Notice to Proceed

4.02 Starting the Work

4.03 Reference Points

4.04 Progress Schedule

4.05 Delays in Contractor’s Progress

Article 5—Site; Subsurface and Physical Conditions; Hazardous Environmental Conditions

5.01 Availability of Lands

5.02 Use of Site and Other Areas

5.03 Subsurface and Physical Conditions

5.04 Differing Subsurface or Physical Conditions

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 2 of 5

5.05 Underground Facilities

5.06 Hazardous Environmental Conditions at Site

Article 6—Bonds and Insurance

6.01 Performance, Payment, and Other Bonds

6.02 Insurance—General Provisions

6.03 Contractor’s Insurance

6.04 Builder’s Risk and Other Property Insurance

6.05 Property Losses; Subrogation

6.06 Receipt and Application of Property Insurance Proceeds

Article 7—Contractor’s Responsibilities

7.01 Contractor’s Means and Methods of Construction

7.02 Supervision and Superintendence

7.03 Labor; Working Hours

7.04 Services, Materials, and Equipment

7.05 “Or Equals”

7.06 Substitutes

7.07 Concerning Subcontractors and Suppliers

7.08 Patent Fees and Royalties

7.09 Permits

7.10 Taxes

7.11 Laws and Regulations

7.12 Record Documents

7.13 Safety and Protection

7.14 Hazard Communication Programs

7.15 Emergencies

7.16 Submittals

7.17 Contractor’s General Warranty and Guarantee

7.18 Indemnification

7.19 Delegation of Professional Design Services

Article 8—Other Work at the Site

8.01 Other Work

8.02 Coordination

8.03 Legal Relationships

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 3 of 5

Article 9—Owner’s Responsibilities

9.01 Communications to Contractor

9.02 Replacement of Engineer

9.03 Furnish Data

9.04 Pay When Due

9.05 Lands and Easements; Reports, Tests, and Drawings

9.06 Insurance

9.07 Change Orders

9.08 Inspections, Tests, and Approvals

9.09 Limitations on Owner’s Responsibilities

9.10 Undisclosed Hazardous Environmental Condition

9.11 Evidence of Financial Arrangements

9.12 Safety Programs

Article 10—Engineer’s Status During Construction

10.01 Owner’s Representative

10.02 Visits to Site

10.03 Resident Project Representative

10.04 Engineer’s Authority

10.05 Determinations for Unit Price Work

10.06 Decisions on Requirements of Contract Documents and Acceptability of Work

10.07 Limitations on Engineer’s Authority and Responsibilities

10.08 Compliance with Safety Program

Article 11—Changes to the Contract

11.01 Amending and Supplementing the Contract

11.02 Change Orders

11.03 Work Change Directives

11.04 Field Orders

11.05 Owner-Authorized Changes in the Work

11.06 Unauthorized Changes in the Work

11.07 Change of Contract Price

11.08 Change of Contract Times

11.09 Change Proposals

11.10 Notification to Surety

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 4 of 5

Article 12—Claims

12.01 Claims

Article 13—Cost of the Work; Allowances; Unit Price Work

13.01 Cost of the Work

13.02 Allowances

13.03 Unit Price Work

Article 14—Tests and Inspections; Correction, Removal, or Acceptance of Defective Work

14.01 Access to Work

14.02 Tests, Inspections, and Approvals

14.03 Defective Work

14.04 Acceptance of Defective Work

14.05 Uncovering Work

14.06 Owner May Stop the Work

14.07 Owner May Correct Defective Work

Article 15—Payments to Contractor; Set-Offs; Completion; Correction Period

15.01 Progress Payments

15.02 Contractor’s Warranty of Title

15.03 Substantial Completion

15.04 Partial Use or Occupancy

15.05 Final Inspection

15.06 Final Payment

15.07 Waiver of Claims

15.08 Correction Period

Article 16—Suspension of Work and Termination

16.01 Owner May Suspend Work

16.02 Owner May Terminate for Cause

16.03 Owner May Terminate for Convenience

16.04 Contractor May Stop Work or Terminate

Article 17—Final Resolution of Disputes

17.01 Methods and Procedures

Article 18—Miscellaneous

18.01 Giving Notice

18.02 Computation of Times

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 5 of 5

18.03 Cumulative Remedies

18.04 Limitation of Damages

18.05 No Waiver

18.06 Survival of Obligations

18.07 Controlling Law

18.08 Assignment of Contract

18.09 Successors and Assigns

18.10 Headings

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

STANDARD GENERAL CONDITIONS

OF THE CONSTRUCTION CONTRACT

ARTICLE 1—DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

A. Wherever used in the Bidding Requirements or Contract Documents, a term printed with initial capital letters, including the term’s singular and plural forms, will have the meaning indicated in the definitions below. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents.

2. Agreement—The written instrument, executed by Owner and Contractor, that sets forth the Contract Price and Contract Times, identifies the parties and the Engineer, and designates the specific items that are Contract Documents.

3. Application for Payment—The document prepared by Contractor, in a form acceptable to Engineer, to request progress or final payments, and which is to be accompanied by such supporting documentation as is required by the Contract Documents.

4. Bid—The offer of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

5. Bidder—An individual or entity that submits a Bid to Owner.

6. Bidding Documents—The Bidding Requirements, the proposed Contract Documents, and all Addenda.

7. Bidding Requirements—The Advertisement or invitation to bid, Instructions to Bidders, Bid Bond or other Bid security, if any, the Bid Form, and the Bid with any attachments.

8. Change Order—A document which is signed by Contractor and Owner and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, or other revision to the Contract, issued on or after the Effective Date of the Contract.

9. Change Proposal—A written request by Contractor, duly submitted in compliance with the procedural requirements set forth herein, seeking an adjustment in Contract Price or Contract Times; contesting an initial decision by Engineer concerning the requirements of the Contract Documents or the acceptability of Work under the Contract Documents;

challenging a set-off against payments due; or seeking other relief with respect to the terms of the Contract.

10. Claim

a. A demand or assertion by Owner directly to Contractor, duly submitted in compliance with the procedural requirements set forth herein, seeking an adjustment of Contract Price or Contract Times; contesting an initial decision by Engineer concerning the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

requirements of the Contract Documents or the acceptability of Work under the Contract Documents; contesting Engineer’s decision regarding a Change Proposal;

seeking resolution of a contractual issue that Engineer has declined to address; or seeking other relief with respect to the terms of the Contract.

b. A demand or assertion by Contractor directly to Owner, duly submitted in compliance with the procedural requirements set forth herein, contesting Engineer’s decision regarding a Change Proposal, or seeking resolution of a contractual issue that Engineer has declined to address.

c. A demand or assertion by Owner or Contractor, duly submitted in compliance with the procedural requirements set forth herein, made pursuant to Paragraph 12.01.A.4, concerning disputes arising after Engineer has issued a recommendation of final payment.

d. A demand for money or services by a third party is not a Claim.

11. Constituent of Concern—Asbestos, petroleum, radioactive materials, polychlorinated biphenyls (PCBs), lead-based paint (as defined by the HUD/EPA standard), hazardous waste, and any substance, product, waste, or other material of any nature whatsoever that is or becomes listed, regulated, or addressed pursuant to Laws and Regulations regulating, relating to, or imposing liability or standards of conduct concerning, any hazardous, toxic, or dangerous waste, substance, or material.

12. Contract—The entire and integrated written contract between Owner and Contractor concerning the Work.

13. Contract Documents—Those items so designated in the Agreement, and which together comprise the Contract.

14. Contract Price—The money that Owner has agreed to pay Contractor for completion of the Work in accordance with the Contract Documents.

15. Contract Times—The number of days or the dates by which Contractor shall: (a) achieve Milestones, if any; (b) achieve Substantial Completion; and (c) complete the Work.

16. Contractor—The individual or entity with which Owner has contracted for performance of the Work.

17. Cost of the Work—See Paragraph 13.01 for definition.

18. Drawings—The part of the Contract that graphically shows the scope, extent, and character of the Work to be performed by Contractor.

19. Effective Date of the Contract—The date, indicated in the Agreement, on which the Contract becomes effective.

20. Electronic Document—Any Project-related correspondence, attachments to correspondence, data, documents, drawings, information, or graphics, including but not limited to Shop Drawings and other Submittals, that are in an electronic or digital format.

21. Electronic Means—Electronic mail (email), upload/download from a secure Project website, or other communications methods that allow: (a) the transmission or communication of Electronic Documents; (b) the documentation of transmissions, including sending and receipt; (c) printing of the transmitted Electronic Document by the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

recipient; (d) the storage and archiving of the Electronic Document by sender and recipient; and (e) the use by recipient of the Electronic Document for purposes permitted by this Contract. Electronic Means does not include the use of text messaging, or of Facebook, Twitter, Instagram, or similar social media services for transmission of Electronic Documents.

22. Engineer—The individual or entity named as such in the Agreement.

23. Field Order—A written order issued by Engineer which requires minor changes in the Work but does not change the Contract Price or the Contract Times.

24. Hazardous Environmental Condition—The presence at the Site of Constituents of Concern in such quantities or circumstances that may present a danger to persons or property exposed thereto.

a. The presence at the Site of materials that are necessary for the execution of the Work, or that are to be incorporated into the Work, and that are controlled and contained pursuant to industry practices, Laws and Regulations, and the requirements of the Contract, is not a Hazardous Environmental Condition.

b. The presence of Constituents of Concern that are to be removed or remediated as part of the Work is not a Hazardous Environmental Condition.

c. The presence of Constituents of Concern as part of the routine, anticipated, and obvious working conditions at the Site, is not a Hazardous Environmental Condition.

25. Laws and Regulations; Laws or Regulations—Any and all applicable laws, statutes, rules, regulations, ordinances, codes, and binding decrees, resolutions, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

26. Liens—Charges, security interests, or encumbrances upon Contract-related funds, real property, or personal property.

27. Milestone—A principal event in the performance of the Work that the Contract requires Contractor to achieve by an intermediate completion date, or by a time prior to Substantial Completion of all the Work.

28. Notice of Award—The written notice by Owner to a Bidder of Owner’s acceptance of the Bid.

29. Notice to Proceed—A written notice by Owner to Contractor fixing the date on which the Contract Times will commence to run and on which Contractor shall start to perform the Work.

30. Owner—The individual or entity with which Contractor has contracted regarding the Work, and which has agreed to pay Contractor for the performance of the Work, pursuant to the terms of the Contract.

31. Progress Schedule—A schedule, prepared and maintained by Contractor, describing the sequence and duration of the activities comprising Contractor’s plan to accomplish the Work within the Contract Times.

32. Project—The total undertaking to be accomplished for Owner by engineers, contractors, and others, including planning, study, design, construction, testing, commissioning, and start-up, and of which the Work to be performed under the Contract Documents is a part.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

33. Resident Project Representative—The authorized representative of Engineer assigned to assist Engineer at the Site. As used herein, the term Resident Project Representative (RPR) includes any assistants or field staff of Resident Project Representative.

34. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and that establish the standards by which such portion of the Work will be judged.

35. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements for Engineer’s review of the submittals.

36. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor’s Applications for Payment.

37. Shop Drawings—All drawings, diagrams, illustrations, schedules, and other data or information that are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. Shop Drawings, whether approved or not, are not Drawings and are not Contract Documents.

38. Site—Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the Work is to be performed, including rights-of-way and easements, and such other lands or areas furnished by Owner which are designated for the use of Contractor.

39. Specifications—The part of the Contract that consists of written requirements for materials, equipment, systems, standards, and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable to the Work.

40. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work.

41. Submittal—A written or graphic document, prepared by or for Contractor, which the Contract Documents require Contractor to submit to Engineer, or that is indicated as a Submittal in the Schedule of Submittals accepted by Engineer. Submittals may include Shop Drawings and Samples; schedules; product data; Owner-delegated designs;

sustainable design information; information on special procedures; testing plans; results of tests and evaluations, source quality-control testing and inspections, and field or Site quality-control testing and inspections; warranties and certifications; Suppliers’ instructions and reports; records of delivery of spare parts and tools; operations and maintenance data; Project photographic documentation; record documents; and other such documents required by the Contract Documents. Submittals, whether or not approved or accepted by Engineer, are not Contract Documents. Change Proposals, Change Orders, Claims, notices, Applications for Payment, and requests for interpretation or clarification are not Submittals.

42. Substantial Completion—The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended.

The terms “substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion of such Work.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

43. Successful Bidder—The Bidder to which the Owner makes an award of contract.

44. Supplementary Conditions—The part of the Contract that amends or supplements these General Conditions.

45. Supplier—A manufacturer, fabricator, supplier, distributor, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or a Subcontractor.

46. Technical Data

a. Those items expressly identified as Technical Data in the Supplementary Conditions, with respect to either (1) existing subsurface conditions at or adjacent to the Site, or existing physical conditions at or adjacent to the Site including existing surface or subsurface structures (except Underground Facilities) or (2) Hazardous Environmental Conditions at the Site.

b. If no such express identifications of Technical Data have been made with respect to conditions at the Site, then Technical Data is defined, with respect to conditions at the Site under Paragraphs 5.03, 5.04, and 5.06, as the data contained in boring logs, recorded measurements of subsurface water levels, assessments of the condition of subsurface facilities, laboratory test results, and other factual, objective information regarding conditions at the Site that are set forth in any geotechnical, environmental, or other Site or facilities conditions report prepared for the Project and made available to Contractor.

c. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical…