SATPC0042566 Tab 04 4 SOW..pdf
PDF 152 KB Posted
- Attached to
- MTS Pump Model Replacement 2026 Federal contract opportunity
- Solicitation number
- 80NSSC26942370Q
About this file
This is a Statement of Work template for the replacement of pump/motor modules at NASA Langley Research Center.
The project involves removing and replacing two degraded 30 GPM pump/motor assemblies from an MTS SilentFlo HPU Model 505.60 located in the Materials Research Lab, Building 1205, Room 229Mez. The existing HPU specifications include: Assembly number 100252401, Serial Number 10385558V01, Generation G2, 3-phase 460V 60Hz AC power, 20.7 Mpa (3000 psi) pressure rating, right-hand orientation, tuned hose silencing technique, and water cooling method. The work scope requires safe shutdown and Lockout/Tagout procedures, complete depressurization of high-pressure accumulators, isolation of the targeted 30 GPM bay, disconnection of electrical and fluid line connections, installation of certified replacement modules, torque verification to manufacturer specifications, water-cooling circuit reconnection, replacement of high-pressure and filtration elements, and low-pressure bleeding and motor rotation verification. All parts must be delivered to NASA Langley Research Center, Building 1206 (Receiving), 4 S. Marvin Street, Hampton, VA 23681.
The deliverables include two operational 30 GPM pump modules with verified operations, a final service report detailing pump performance data (case drain flow rates, pressure ripple data, and fluid cleanliness certification), and successful completion of a 2-hour performance verification test demonstrating zero fluid leaks and normal operating temperatures with sign-off from the Lab Manager or Head Testing Engineer. The period of performance is 90 days after receipt of order (ARO).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SATPC0042566 Tab 06 RDSS..pdf | ||
| SATPC0042566 Tab 07 Capability Statement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK TEMPLATE
1.0 Introduction/Background
• Background:A MTS 505.60 within the Durability Damage Tolerance and
Reliability Branch (DDTRB). need pump modules replaced due to oil tests that indicate need for replacement. NESC investigations, and research for multiple branches rely on this specified equipment.
• Project Title: MTS SilentFlo HPU 30 GPM Pump/Motor Module Replacements
• Pump Location: [Materials Research Lab, Building 1205, and Room 229Mez]
• Existing HPU details:
Model 505.60
Assembly number 100252401
Serial Number 10385558V01
Generation G2
Voltage (3 Phase) 60 Hz 460 V (AC)
Pressure 20.7 Mpa (3000 psi)
Orientation Right-Hand (Standard)
Silencing Technique Tuned Hose
Cooling Method Water
Accumulation None
High Pressure Filtration false
• Shipping Information:
Deliver all parts to the following shipping address:
NASA Langley Research Center Building 1206, (Receiving) 4 S. Marvin Street Hampton, VA 23681
2. Objective and Scope of Work
• Objective: Remove two degraded 30 GPM pump/motor assemblys from a multi-bay or MTS SilentFlo HPU and install a certified replacement module to restore optimal pump capacity.
• Scope:
o Safely shut down the MTS HPU and execute full mechanical and electrical Lockout/Tagout (LOTO) on primary power.
o Depressurize high-pressure accumulators and surge suppressors completely.
o Isolate the targeted 30 GPM bay using localized isolation valves to preserve main reservoir levels.
o Disconnect subassembly electrical connectors, interlock wiring, and run-on-demand (ROD) signal lines as required.
o Disconnect and cap suction, high-pressure, and case drain lines using ultra-clean plugs to prevent fluid contamination.
o Install the new replacement module.
o Torque all fluid line fittings and structural fasteners to manufacturer specifications.
o Reconnect water-cooling/heat-exchanger circuit lines and verify integrity as needed.
o Replace the high-pressure element and filtration elements.
o Clear LOTO, verify correct motor rotation, prime the pump housing, and perform low-pressure bleeding.
5. Deliverables
• Two operational 30 GPM pump modules with operations verified.
• Contractor must provide a final service report detailing pump operation.
Information can include case drain flow rates, pressure ripple data, and a certificate or test of fluid cleanliness.
• The system must pass a 2-hour performance verification test with zero fluid leaks and normal operating temperatures. Final approval requires sign-off from the Lab Manager or Head Testing Engineer.
6. Period of performance
• 90 days ARO