SATPC0037636 Tab 10 Questions and Answers.pdf

PDF 69 KB Posted

Attached to
De-Binding and Sintering Furnace for Ceramic Additive Manufacturing
Solicitation number
80NSSC25895828Q
Issued by

About this file

This is a Questions and Answers document regarding NASA Shared Services Center's solicitation (80NSSC25895828Q) for De-Binding and Sintering Furnaces for Ceramic Additive Manufacturing. The document contains technical clarifications about the furnace requirements, including delivery timing (beginning of June 2025), material processing details (ceramic AM greenware only, no organics), and operational parameters.

Key technical specifications discussed include: exhaust system requirements (back-mounted exhaust acceptable, with exhaust into high bay room through water bucket filtration), temperature requirements (sintering at 1720°C for 90 minutes maximum, debinding at 615°F for 120 minutes), and equipment compatibility with a laser-based 3D printer (specific model restricted by NSSC). The exchange appears focused on gathering information to properly quote and configure the furnace systems for NASA's specific ceramic additive manufacturing application.

View the file

Other files

File Type Posted
SATPC0037636 Tab 10 RFQ Open Market.pdf PDF
SATPC0037636 Tab 10 SOW_Redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Is there a specific date your customer needs the furnace delivered by?

Beginning of June 2025

Can your customer please share the es�mated amount or organics that will be placed in the furnace?

No organics only ceramic AM greenware

If possible, can your customer please share what 3D printer they have?

According to the NSSC, no. I believe I can say it is a laser based 3d printer

We would like to inquire about the contract ID - 80NSSC25895828Q for the DE binding and Sintering furnaces. We would like to beter understand the off gases coming from your material. We need to understand your exhaust system expecta�ons for this project.

The unit will be housed in a high bay. Exhaust into the room is allowable per our environmental hygienist. We will run the exhaust tube through a water bucket in order to catch any solids that might come through.

We have a couple of op�ons with exhaust out of the top or out of the back of our furnace. We can quote the project and refine this ques�on later.

Out of the back I do need to know the amount of �me your project needs to see the temperatures required in both furnaces? 30 min @ 1700 C.

The exact schedule is sensi�ve however the most extreme is 1720C for 90 minutes in the sintering and 120 min at 615F for debinding. There are mul�ple plateaus and holds, those are the most extreme.

File details come from the government source that posted it. Updated .