About this file

Amendment 01 to revise the cut-off for questions to November 13, 2017.

View the file

Other files

File Type Posted
80KSC018R0003_Amendment_04final.pdf PDF
80KSC018R0003_Amendment_02.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

80KSC018R0003 ENGINE VERTICAL INSTALLER Section L HANDLING & ACCESS ML Instructions to Offerors

APPENDIX TO SECTION L – QUESTION AND COMMENT FORM

Questions or comments regarding this solicitation must be submitted via email to the Contracting Officer identified below.

Name: Timothy Freeland Email: Timothy.Freeland-1@nasa.gov

Questions shall be submitted on this form in MS Word or equivalent (no PDF or read only formats). Questions also may be submitted in the body of an e-mail message following this form’s format. Late questions or comments will be considered by the Government but may not be answered. Responses to questions will be issued as amendments to the solicitation. The cutoff date and time for receipt of questions November 13, 2017.

Offerors are cautioned that technical activity personnel are not authorized to answer solicitation questions or comments and that any responses from them may not accurately represent the Government’s official position.

PLEASE CITE THE REFERENCE NUMBER SUCH AS PAGE NUMBER OF THE RFP,

SPEC, DWGS, ETC, IF APPLICABLE.

1. REFERENCE:

QUESTION:

2. REFERENCE:

QUESTION:

Submitted by (name):____________________________________________________________ Company:______________________________________________________________ E-mail Address:_____________________________________________________________

topmostSubform[0]:
Page1[0]:
ContractIDCode[0]:
Page[0]: 1
Pages[0]: 2
AmendmentNo[0]: 001
EffectiveDate[0]: See Block 16C
ReqNumber[0]:
ProjectNo[0]:
IssuedBy[0]: NASA/Kennedy Space Center

Office of Procurement, OP-ES Timothy Freeland Kennedy Space Center, FL 32899

Code[0]:
AdministeredBy[0]:
Code[2]:
NameandAddress[0]:
Code[1]:
FacilityCode[0]:
CheckBox9[0]: 1
AmendmentNo[1]: 80KSC018R0003
Dated9B[0]: 10/24/2017
CheckBox10[0]: 0
ModificationNo[0]:
Dated10B[0]:
CheckBox11[0]: 1
Extended[0]: Off
NotExtended[0]: 1
Copies[0]:
AccountingData[0]:
CheckBox13A[0]: 0
A13[0]:
CheckBox13B[0]: 0
CheckBox13C[0]: 0
C13[0]:
CheckBox13D[0]: 0
D13[0]:
IsNot[0]: 0
Is[0]: 1
CopiesReturned[0]: 1
Description[0]: The purpose of this amendment is to revise the cut-off for receipt of questions included on page 35 of the subject solicitation.

The cut-off for receipt of questions on the "Question and Comment " form is hereby revised to read November 13, 2017.

A replacement page is attached to this amendment.

NameandTitleSigner[0]:
DateSigned[0]:
NameandTitleOfficer[0]: Timothy M. Freeland
DateSigned[1]: 11/01/2017
2017-11-01T11:06:20-0400
TIMOTHY FREELAND

File details come from the government source that posted it. Updated .