Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_00001.doc | DOC document | |
| 80AFRC17Q0004_-_T&Cs.docx | DOCX document | |
| Attachment__1_Quality_Documents.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ #80AFRC17Q0004
STATEMENT OF WORK
Landing Gear Overhaul
LANDING GEAR REMOVED FROM B747-SP N747NA S/N 21411
Date: 08/02/2017
National Aeronautics and Space Administration
Armstrong Flight Research Center
Edwards, California
RFQ No. 80AFRC17Q0004
Date June 26, 2017 Version #2
Table of Contents
1.0 Background
2.0 Objectives
3.0 Scope
4.0 Tasks
5.0 Deliverables
6.0 Government-Furnished Property (GFP)
7.0 Performance / Qualifications
8.0 Shipment requirements
9.0 Other Unique Requirements and Considerations
10.0 Place of performance
11.0 Period of performance
RFQ 80AFRC17Q0004 B747-SP Landing Gear Overhaul
Aug 2, 2017 Version #2
1.0 Background
The National Aeronautics and Space Administration (NASA) operates a Boeing 747SP aircraft as an airborne astronomical observatory under the Stratospheric Observatory for Infrared
Astronomy (SOFIA) Program. This aircraft N747NA S/N 21411 is operated by NASA
Armstrong Flight Research Center (AFRC) and is located at Palmdale, CA.
Removed Landing Gear Information:
Type Aircraft Boeing 747SP
Engine Type PW JT9D
Tail Number N747NA
Serial Number 21411
Total Hours 77,985
Total Cycles 10,561
Nose P/N 65B18202-9 S/N 26660
Left Hand (LH) Wing P/N 65B18201-23 S/N 11756
Right Hand (RH) Wing P/N 65B18201-24 S/N 10475
Left Hand (LH) Body P/N 65B18203-19 S/N 11753
Right Hand (RH) Body P/N 65B18203-20 S/N 11748
2.0 Objectives
Overhaul of a complete landing gear ship set for NASA’s B747SP, with all applicable airworthiness directives and service bulletins incorporated. Landing gear being overhauled has had 180 cycles over the last 12 years.
3.0 Scope
Provide a complete overhauled landing gear ship set for the NASA SOFIA Programs B747-SP aircraft. This includes:
2 ea. LH and RH Wing Main Landing Gear (MLG);
2 ea. LH and RH Body MLG;
1 ea. Nose Landing Gear (NLG)
All assemblies shall include all components that would enable an operator to install/change the landing gear as an all-inclusive Ready for Installation (RFI) assembly.
4.0 Requirements/ Tasks
4.1 Tasks
Overhaul and Build-up 747SP NLG Assembly –P/N 65B18202-9, S/N 26660
1. NLG component assembly - 65B18202-9
2. Shock strut assembly - 65B01459-8
3. Axel assembly –65B19923
4. Drag strut assembly – 65B01222
5. Upper tripod brace – 65B01225-1
6. Lower tripod brace – 65B05271-3
7. Torsion link assemblies – 65B05340 upper & 65B05342 lower
8. Tow fitting – 65B08800-1
9. Trunnion pins – 65B05106
10. Hydraulic installation – 65B01562-1
11. Electrical installation includes all conduits, hardware etc.
12. Wire harness – 65B40862
13. Hardware installation
14. Pivot link installation – 65B82745
15. Bullnose installation – 65B14240
16. Steering collar – 65B05250-30
17. Steering actuator support assemblies
18. Steering actuators – 65B01503
19. Steering summing mechanism - 65B81434-1
20. Steering metering valve – 65B01519
21. Downlock actuator – 1U1204-4
22. Oleo pressure switch – 6584059-2
23. Downlock bungee – 65B05398-8
24. Retract actuator – 65B01550
4.2 Tasks
Overhaul and Build-up 747SP Wing Landing Gear (WLG)
(LH) P/N 65B18201-23, 11756 (RH) P/N 65B18201-24 S/N 10475
1. Component assembly – 65B18201-23 & 24
2. Shock strut assembly –65BI8211-5 & -6
3. Torsion link assemblies – 65B18219
4. Side brace assembly – 65B18207-5 & 6
5. Drag brace assembly –65B18218-2
6. Jury strut upper and lower assemblies- 65B05338 and 65B05336
7. Truck beam assembly. –65B18223-1
8. Truck lock Installation– 65B01483-8
9. Hydraulic support – 65B80165
10. Hydraulic installation – 65B01561
11. Electrical harness – 65B40861
12. Attaching hardware
13. Down lock actuator – 69B80358
14. Down lock bungee- 65B08803
15. Fwd. trunnion bearing housing and fuse pin
16. Walking beam assembly – 65B01204-7
17. Brake rod assembly – 65B18225-3
18. Truck positioning actuators – 65B01539
19. Gear retract actuator – 65B01501-11
4.3 Tasks
Overhaul and Build-up 747SP Body Landing Gear (BLG)
(LH) P/N 65B18203-19, S/N 0628, 11753 (RH) P/N 65B18203-20 S/N 11748
1. Component assembly – 65B18203-19 & 20
2. Shock strut assembly – 65B18231-19 & 20
3. Trunnion assembly – 65B19918
4. Up-lock Installation 65B01291-12
5. Truck beam assembly –65818223-1
6. Hydraulic installation– 65B01563
7. Hydraulic installation support – 65B80164
8. Electrical harness installation – 65B40863-27 & 28
9. Attaching hardware
10. Steering mechanism – 65B05160 –1 & 2
11. Drag strut assembly –65B01209
12. Jury strut assembly upper and lower – 65B05370 & 65B05374
13. Side brace assembly – 65B18234-1
14. Bungee assembly – 65B08802
15. Torsion link assemblies - 65B18237-1
16. Downlock actuators – 69B80358
17. Steering actuators – 1U1171-5
18. Brake rod assembly – 65B18225-3
19. Truck positioning actuators – 65B01504.
20. Gear retract actuators – 65B01502
Note: Wheels Tires and Brakes are not included in the build-up
BLG Life Limited Parts must extend to the next overhaul with time remaining; NASA currently has a required life cycle of 12 years after Landing Gear installation.
4.4 Tasks
Ensure compliance with the below FAA / OEM and Historical Documents:
1. Previously complied airworthiness directives and service bulletins
2. Service Bulletins and Service Letters to be incorporated during overhaul Oleo pressure switch shut off valve installation– SB-747-27-2283
3. Previous Overhaul Documents
4. Landing Gear Previously Installed Aircraft Summary Data Sheet.
4.5 Ensure compliance with overhaul documents
1. Boeing component maintenance manuals for B747 NLG, WLG and BLG
2. Vendor overhaul and repair station manuals
3. Boeing approved expanded repair limits
4. Boeing standard practices and processes as they apply to the landing gear overhaul.
5. Compliance with all Applicable Federal Aviation Administration (FAA) airworthiness directives
6. Compliance with all applicable Original Equipment Manufacturer (OEM) service bulletins
4.6 Time between Overhauls / Life Limited Components
1. NASA requires the landing gear to be overhauled every twelve years
2. Life limited Landing Gear components are tracked as an assembly
3. Vendor to provide life limited Time Since New (TSN) and or Cycles Since New
(CSN) information
4. Landing Gear life limited parts installed must extend to the next scheduled overhaul after installation.
4.7 General Build-up
1. Shock strut fluid to be Castrolaero 40 or equivalent
2. Grease to meet Boeing Manufacture Specification (BMS) 3-33
3. Scraper / seal configuration compatible Mil-H-5606
5.0 Deliverables
5.1 Overhauled RFI main and nose landing gear ship set, for B-747SP
2ea. wing landing gear
2ea. body landing gear
1ea. nose landing gear
5.2 Landing gear shall be delivered certified for type CG2 with a maximum taxi gross weight of 703K
5.3 Data Package
1. Life Limited Parts (LLP) List
2. FAA 8130 for each major assembly
3. List of all airworthiness directives embodied
4. List of all service bulletins embodied
5. List of all service letters embodied
6. Submittals to Boeing with Boeing response (if applicable)
7. 3 year warranty from delivery
5.4 Provide access for NASA to perform periodic facility, process and quality
Inspections.
6.0 Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI)
6.1 B747-SP landing gear assemblies and major components
1. Nose P/N 65B18202-9 S/N 26660
2. LH Wing P/N 65B18201-23 S/N 11756
3. RH Wing P/N 65B18201-24 S/N 10475
4. LH Body P/N 65B18203-19 S/N 11753
5. RH Body P/N 65B18203-20 S/N 11748
6.2 Major components
1. Drag strut assemblies
2. Steering actuators
3. Gear retract actuators
7.0 Performance / Qualifications
Contractor shall provide evidence of the following:
1. Prime must be an FAA Part 145 Repair station with appropriate rating to perform overhaul of Heavy Landing Gear implemented a Quality Management System (QMS) that is compliant to the requirements of International Aerospace Quality Standard
AS9100.
2. Be certified mechanics.
3. Qualification to perform all aspects of this work scope
4. Currency with the changes to OEM overhaul manual and federal regulations
5. Capability to render of rendering services in analysis of landing gear technical problems
6. At least 10 years of experience in 747SP landing gear overhauls
8.0 Shipment requirements
Please refer to the "Attachment #2 Quality Documents" for specific shipping requirements:
1. Pre-Ship Review (PSR)
2. Shipping
3. Hardware Handling, Cleaning and Packaging
4. Data Delivery Package
9.0 Other Unique Requirements and Considerations
Please refer to the "Attachment #2 Quality Documents" for specific NASA Quality
Requirements:
Procurement Quality Requirements
NASA Performance / Qualifications
Government Source Inspection
Nonconformance Reporting
Contractor Quality Assurance Plan/Manual
10.0 Place of Performance
The contract will be performed at the contractor location.
11.0 Period of Performance
The period of performance shall complete the overhaul 150 Days from receipt of order.