About this file

This is an Invitation to Bid (ITB 801G) issued by the Ohio Department of Transportation (ODOT) for a term contract specifically set aside for Minority Business Enterprise (MBE) certified vendors. The invitation is dated February 4, 2024, and is exclusively open to MBE bidders certified by the State of Ohio's Department of Administrative Services and Equal Opportunity Division.

The contract covers asphalt concrete, bituminous mixes, equipment rental, material hauling, and associated labor rates, with all materials and services to be provided according to the current ODOT Construction & Material Specification Book. The contract will be effective from the date of execution through February 28, 2026, and ODOT will make multiple awards to all responsive MBE-certified bidders. Vendors may submit unit bid pricing for multiple plant locations, with each location requiring a separate Excel pricing file. Bidders must have valid AWP Codes for submitted plants, and the contract includes detailed specifications for material quality, testing, and performance standards, with provisions for price adjustments based on material non-conformance.

View the file

Other files

File Type Posted
889Global-801G-26GerkenCustarPlt12.xlsx XLSX spreadsheet
889Global-801G-26GerkenOttawaPlt05.xlsx XLSX spreadsheet
889Global-801G-26GerkenWatervillePlt04.xlsx XLSX spreadsheet
889Global-801G-26KMIColumbiaStation530.xlsx XLSX spreadsheet
889Global-801G-26KMIGrandRiver514.xlsx XLSX spreadsheet
889Global-801G-26KoKosingCAMPlt5101.xlsx XLSX spreadsheet
889Global-801G-26NLSCambridgePlt4.xlsx XLSX spreadsheet
889Global-801G-26ShellyCoshoctonPlt66.xlsx XLSX spreadsheet
889Global-801G-26ShellyFairviewPlt44.xlsx XLSX spreadsheet
889Global-801G-26ShellyLucasvillePlt47.xlsx XLSX spreadsheet
889Global-801G-26ShellyNECantonPlt100.xlsx XLSX spreadsheet
889Global-801G-26ShellyNEmassilonPlt73.xlsx XLSX spreadsheet
889Global-801G-26ShellyReynoldsburgPlt94.xlsx XLSX spreadsheet
889Global-801G-26ShellySpringfieldPlt25.xlsx XLSX spreadsheet
889Global-801G-26SmallAsphPortable.xlsx XLSX spreadsheet
889Global-801G-26ValleyCincinnatiPlt19.xlsx XLSX spreadsheet
889Global-801G-26ValleyTroyPortable25.xlsx XLSX spreadsheet
MBMapleGroveQPR_Material_Specification.pdf PDF
889Global-801G-26GerkenWMillgrovPortable11.xlsx XLSX spreadsheet
889Global-801G-26HolmesPlt01.xlsx XLSX spreadsheet
889Global-801G-26KMICleveland522.xlsx XLSX spreadsheet
889Global-801G-26KMIColumbus509.xlsx XLSX spreadsheet
889Global-801G-26KMIGarfieldHGT519.xlsx XLSX spreadsheet
889Global-801G-26KMIMarengo526.xlsx XLSX spreadsheet
889Global-801G-26KMIMedina516.xlsx XLSX spreadsheet
889Global-801G-26KMITallmadge523.xlsx XLSX spreadsheet
889Global-801G-26M_BTiffanPlt.xlsx XLSX spreadsheet
889Global-801G-26MedinaSupply.xlsx XLSX spreadsheet
889Global-801G-26NLSCadizPlt3.xlsx XLSX spreadsheet
889Global-801G-26ShellyEFultonhamPlt99.xlsx XLSX spreadsheet
889Global-801G-26ShellyNEStreetsboroPlt72.xlsx XLSX spreadsheet
889Global-801G-26ShellyOstranderPlt24.xlsx XLSX spreadsheet
889Global-801G-26ShellyPortagePortable128.xlsx XLSX spreadsheet
889Global-801G-26ShellySciotoPlt129.xlsx XLSX spreadsheet
889Global-801G-26ShellyScottPortable89.xlsx XLSX spreadsheet
889Global-801G-26StonecoFindlayPlt114.xlsx XLSX spreadsheet
889Global-801G-26StonecoMaumeePlt100.xlsx XLSX spreadsheet
889Global-801G-26ValleyABAsphPlt1301.xlsx XLSX spreadsheet
889Global-801G-26ValleyClevelandPortable17.xlsx XLSX spreadsheet
889Global-801G-26ValleyMorrowPlt05.xlsx XLSX spreadsheet
889Global-801G-26ValleySharonvillePlt23.xlsx XLSX spreadsheet
889Global-801G-26ValleyWallsbroPhilipsburgPlt1402.xlsx XLSX spreadsheet
ValleySpecification__101G_Bid_for_UPM_Cold_Mix.pdf PDF
889Global-801G-26GerkenBlufftonPlt03.xlsx XLSX spreadsheet
889Global-801G-26GerkenPauldingPlt08.xlsx XLSX spreadsheet
889Global-801G-26GerkenSanduskyPlt10.xlsx XLSX spreadsheet
889Global-801G-26GerkenToledoPlt17.xlsx XLSX spreadsheet
889Global-801G-26KMIWooster517.xlsx XLSX spreadsheet
889Global-801G-26KoKosingKMI501.xlsx XLSX spreadsheet
889Global-801G-26NLSMartinFerryPlt05.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation 801G-26

ITB 801G – Asphalt Concrete, Bituminous Mixes, Equipment Rental, and Material Hauling 02 / 04 / 2024

REQUIREMENTS/SPECIFICATIONS

Minority Business Enterprise (MBE) Set-Aside Bidding Opportunity

Section 1: Intent

The purpose of this invitation to bid is to establish a term contract for Asphalt Concrete, other Bituminous Mixes, Labor rates, Material Hauling, and Equipment rental. All materials and services shall be provided in accordance with the current ODOT Construction & Material Specification Book (C&MS) at time of award.

This invitation to bid is set-aside exclusively for Minority Business Enterprise (MBE) bidders certified by the State of Ohio, Department of Administrative Services, and Equal Opportunity Division. Only bids from certified MBEs will be considered for award of this invitation to bid.

Section 2: Multiple Award

ODOT will accept all responsive bids submitted on or before the specified bid opening date and make an award to all responsive State of Ohio, MBE certified bidders pursuant to O.R.C. 5513.02.

Section 3: Plant Locations

Bidders may submit unit bid pricing for multiple plant locations.

Bidders should complete an Excel pricing page for EACH plant location bid.

A separate pricing (excel) file should be submitted for EACH plant location.

Any plants submitted with this bid must have a valid AWP Code at the time of the bid closing.

Section 4: Contract Duration

The effective duration of this contract shall be from the Date of Execution through February 28, 2026.

Section 5: Product Specifications

Specification references included in the Department’s Excel Pricing page are incorporated into this Contract by reference and can be located in the Ohio Department of Transportation current Construction and Materials Specification (C&MS) book and provisions of the current version of supplemental specification 800 (available electronically via the link below) at time of award:

https://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/2023-Online-Spec- Book.aspx

Materials provided must conform to their applicable current C&MS specification. Specification references have been provided on the Department’s Excel pricing page at time of award.

To access current Supplemental Specifications (800 series), please follow the link below:

http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/ProposalNotesSupplemen talSpecificationsandSupplements.aspx

All mixing operations and plants supplying material on this invitation must meet the applicable requirements contained in the current C&MS at time of award.

https://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/2023-Online-Spec-Book.aspx https://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/2023-Online-Spec-Book.aspx http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/ProposalNotesSupplementalSpecificationsandSupplements.aspx http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/ProposalNotesSupplementalSpecificationsandSupplements.aspx

All plant operation and equipment must meet the requirements of section 402 in the current C&MS book at time of award.

Vendor is responsible for ensuring current plant certification is in place when materials are requested.

The JMF (Job Mix Formula) will be provided by ODOT or the Contractor/Producer as directed below for a PO (Purchase Order). The Contractor/Producer will provide quality control as directed below:

The District Testing Engineer of the purchasing District will provide the JMF for any 301 as referenced in the current C&MS at time of award. Tolerances from the JMF of +/- 0.50% for PG binder and +/- 6.0% passing the No. 4 sieve will be used for acceptance. District sampling will be at the direction of, and using procedures provided, by the District Testing Engineer. A minimum of one sample per 500 tons is required. For orders less than 500 tons, one sample is required per purchase order.

The Contractor/Producer will provide the JMF for any 448 items. The JMF will be approved by current ODOT procedures. The current requirements of 403, 441 and 448 (quality control and acceptance testing included) will apply for purchase orders of over 3000 tons of 448 material. The Contractor/Producer will be given 48 hours notice from the District so he can prepare for QC testing.

The current small quantities guideline (Small Quantity Bituminous Concrete Testing and Acceptance) can be used, if applicable, for purchase orders over 3000 tons. For purchase orders under 3000 tons, only an approved JMF for 448 is required. District sampling will be at the direction of, and using procedures provided by, the District Testing Engineer. Sampling frequency will be at least every 750 tons.

Aggregate suppliers are required to be properly certified in accordance with Supplement 1069 (link below):

https://www.dot.state.oh.us/Divisions/ConstructionMgt/Specification%20Files/1069_0420

2018_for_2023.pdf

5.1 Asphalt mixtures may be produced using the warm mix asphalt method according to 402.09 except as restricted by specification.

5.2 Vendor Notes: This will allow the vendor to provide product specific information on any item(s) bid on the material pricing tab. Vendor will not use this section to include additional conditions to any of the materials being supplied.

5.3 Milling / Planing / Grinding

Shall be in accordance with current Construction and Material Specifications. Refer to the following

Item #’s and Supplemental Specifications.

• Pavement planing or cold milling (refer to Item # 254)

• Pavement diamond grinding (refer to Item # 257)

• Pavement micro-planing, Class B (refer to Supplemental Specification 897) o Equipment, Planing, Surface Patching, Surface Tolerances also under SS 897

Grindings (from Item #254 & 257) will be removed by the District unless otherwise agreed upon.

The vendor will be responsible for collecting all waste material from the work performed and properly disposing of the materials.

Gradation of Reclaimed Asphalt Concrete Pavement (RACP)

Shall be per Item # 703.18 A.

Sieve Size Total Percent Passing

11/2 inch (37.5mm) 100 3/4 inch (19.0mm) 80 to 100 3/8 inch (9.5mm) 60 to 90 No. 4 (4.75mm) 30 to 90 No. 30 (600µ) 3 to 20 https://www.dot.state.oh.us/Divisions/ConstructionMgt/Specification%20Files/1069_04202018_for_2023.pdf https://www.dot.state.oh.us/Divisions/ConstructionMgt/Specification%20Files/1069_04202018_for_2023.pdf

Section 6: Non-Conforming Materials and Price Adjustments.

The district shall save the sample (if applicable) and prepare a report for all materials that fail to meet the applicable requirements of specifications.

A copy of the test report, price adjustment, and documentation on the use of the material shall be sent by the District Highway Management Administrator to the Vendor within 14 calendar days of the test.

Written notice must be given to the Vendor, who may appeal the price adjustment within 10 calendar days of receipt of the test report and price adjustment.

If the Vendor appeals for the price adjustment, the appeal shall be sent by the Vendor to the District Highway Management Administrator. If the vendor and the district cannot resolve the dispute, the matter shall be forwarded to the Office of Contracts for final resolution.

Failure to file an appeal within the allotted time shall result in a waiver of the Vendor’s right to appeal the price adjustment.

After the Vendor’s appeal time has elapsed and no appeal has been submitted, the district shall process the payment for the material reflecting the use of material that has failed to meet the Department’s specifications.

A minimum non-conformance fee of $300.00 shall be applied to all deficient materials test reports, unless a higher appropriate deduction is established. If the total bid price for the quantity is less than $300.00, then the minimum non-conformance fee shall be the total bid price.

The district shall include the appropriate adjustment in the material price as follows:

6.1 Low Bitumen Content

If a sample of asphalt concrete or asphalt concrete base has a bitumen content below the specification limits, then the following formula applies:

A ($/CY) = [{BR - BA - L} x QT x PI] / [QV x 100] B ($/CY) = {BR - BA - L} x P x 0.233 Price Adjustment ($) = {A + B} x QV

Where: BR = required bitumen content (%) BA = actual bitumen content (%) L = allowable limits from design (%) = usually 0.5 % QT = effected quantity in tons QV = effected quantity in cubic yards PI = placing index for month material placed ($/ton) P = bid price or material price ($/CY)

6.2 High Bitumen Content

The District Highway Management Administrator may accept, without a price deduction or administrative fee, asphalt concrete base material produced with a high bitumen content, provided the Contractor immediately brought the subsequent production into the specification limits and continued to control the mix within reasonably close conformity to the specifications.

If the material continues to be produced outside the specification limits or inconsistent control of the material following the above allowance persists, then the DCE shall review the performance of the material to determine if the material can remain in place. If the material is allowed to remain in place, then the pay adjustment shall be 5 percent of the purchase price of the in-place material.

6.3 Bitumen Content or 4.75 mm (No. 4) Sieve Outside Range

Limitation

If a sample of asphalt concrete or asphalt concrete base is outside the range limitation specified for bitumen content or the 4.75 mm (No. 4) sieve, then the following formula applies:

Price Adjustment = P x 0.05 Quantity to Apply Price Adjustment * = QV x F

Where: F = fraction out on range based on the number of tests outside the range limitation divided by the total tests performed

P = bid price or material price QV = effected quantity in cubic meters (cubic yards)

* Any remaining quantity shall have no deduction.

6.4 PG Binder

If a check sample of PG binder from a hot mix facility fails to meet the grade requirements and is proven to fail by at least two sample failures and a refinery sample taken at the same time is proven to pass the following formula applies:

Price Adjustment = P x A x Q Where: Q = quantity of PG binder affected P = material price, bid price A = total of applicable adjustment factors from chart

Adjustment factor for PG binder sample failure m-value failure 0.290 - 0.299 A = 0.05

0.280 - 0.289 A = 0.10

0.270 - 0.279 A = 0.20

0.269 or less A = 0.30

Original DSR (G*/sin delta) less than 1.00kPa A = 0.30 Any other PG properties A = 0.05

Section 7: Equipment

ODOT will direct the time and place of the use of the vendor’s equipment. The vendor’s operators and other employees will be under the direction and supervision of ODOT.

The vendor shall not park equipment on the right-of-way without the approval of the project supervisor. All staging areas in the right-of-way must be approved by the project supervisor.

7.1 Equipment Mobilization (F.O.B. Job site)

The initial mobilization and final mobilization are included in each pay item for each contract unless the price page provides a lump sum mobilization pay item.

On site mobilization, transporting by tractor and low boy will be included in the initial mobilization for site mobilizations of two (2) miles or less. On site mobilization, transporting by tractor and low boy, for site mobilizations exceeding two (2) miles will be a per hour cost based upon bid prices.

Moving equipment - self-propelled moving of equipment will be charged as operating time.

7.2 Traffic Control

ODOT may choose to provide traffic control or pay the vendor to do so per vendor bid items Miscellaneous Traffic Control Equipment (Paving Related), Flagger, Flagger with Pickup Truck, or Maintaining of Traffic.

7.3 Ohio EPA Division of Air Pollution Control Engineering Section Engineering Guide #57

Reasonably Available Control Measures (RACM), pursuant to OAC rule 3745-17- 08(B), for fugitive dust emissions are to be followed when performing:

1. Structural abrasive blasting

2. Surface cleaning of concrete and other highway surfaces

3. Concrete cutting

4. Asphalt cutting

5. Bridge deck preparation for resurfacing.

Refer to Section 14 for Guide #57.

Section 8: Payment

The “operating hourly rate” will be the rate that the vendor will be paid for the actual operating hours for each piece of equipment. At the completion of work at the end of each day, the vendor and the project supervisor will come to an agreement on the number of hours of work performed that are to be submitted for payment.

8.1 Asphalt Placement

Per ton payment shall be based on the project quantity not the daily production. Per ton bid rate will apply to projects where a pavement course is placed. Projects involving repairs only or the repair portion of any project shall use the hourly rates bid. (i.e., full or partial depth repairs) When ODOT trucking is used, payment will be based on the hourly rates bid.

8.2 Pavement Planning

Payment will be based on the Square-yard-inch milled for the project, not the daily accomplishment.

Payment for milling or pavement planning used to perform butt joints, full or partial depth repairs, or the like will be based on the hourly rate bid. When ODOT trucking is used, payment will be based on the hourly rates bid.

8.3 Asphalt Grinding/Planning

This work shall consist of cold-planning asphalt material from various locations as directed by ODOT.

The work covered by these notes consists of furnishing the equipment, operators and necessary support for removing asphaltic concrete pavement to a depth and cross section designated by the Ohio Department of Transportation. In addition, removal may include butt joints at various locations and/or portions of intersecting streets as directed by ODOT. Payment for this work will be paid at the unit price bid for the square yard, one inch thick (Square-yard-inch).

After grinding has been completed, the contractor will sweep the entire street or roadway to remove all loose material. Any equipment/labor required for trim work around manholes, valve boxes, etc.

will be paid for by the hourly rate bid. The street/roadway will be ready for asphalt placement after grinding is complete.

All grindings become the property of the contractor.

ODOT. and the contractor will measure and record the number of square yards and the thickness (depth) of the ground area.

Minimum milling depth will be 1" for billing purposes.

The contractor will be paid at the unit price of one square yard one inch thick (Square-yard-inch)

8.3.1 Example:

Bid price= $5.00 per square-yard-inch Area milled= 3000 square yards Depth milled = 1-1/2" Square-yard-inches= 3000 x 1-1/2 = 4500 square-yard-inches Payment = 4500 x $5.00 = $22,500.00

Section 9: Crack Sealing, Hot Applied

This work shall consist of the preparation and application of hot applied crack sealant to transverse and longitudinal construction joints and cracks. Work shall be performed in accordance with the current C&MS book at the time of award.

Section 10: Prevailing Wages

Projects are subject to Ohio Prevailing Wage Laws, the contractor/vendor and all subcontractors are required to comply with all provisions of the Ohio Prevailing Wage Laws. See PROPSAL NOTE 060 linked below as if fully incorporated herein.

PN 060 – 04/20/2018 - PREVAILING WAGES ON STATE PROJECTS WITH NO FEDERAL AID

http://www.dot.state.oh.us/Divisions/ConstructionMgt/Pages/ProposalNotesSupplementalSpecificat ionsandSupplements.aspx

Truck drivers who are employed to deliver materials to the project site are exempt from prevailing wage except when the work performed is on the “site of work”. Site of Work includes the following:

• The physical place or places where the building or work called for in the contract will remain after the work is completed.

• Job headquarters, tool yards, batch plants, borrow pits, etc., provided they:

1. Are located adjacent or virtually adjacent (within a one-mile radius) to the site of the work described above.

**AND**

2. Are dedicated exclusively, or nearly so, to performance of the contract or project; 80% of the materials taken from the site must be used for the project.

Truck drivers who are Owner-operators are also exempt from prevailing wage. Owner-operators must have a purchase or bona fide lease agreement contract and demonstrate financial commitment, such as purchasing vehicle insurance, gasoline, etc. An Owner-operator includes a lessee of equipment, but there must exist a bona fide lease with evidence of independent contractor status. A lease calling for a share of revenues while being used, or short term in duration (3-5 years), will not qualify for Owner-operator status.

Section 11: Liquidated Damages for Load Limit Violations

By signing this bid, the bidder will be deemed to have stipulated as follows:

I. Any vehicle being used to haul materials under this contract shall be loaded so as not to exceed the maximum weight limitations contained in Ohio Revised Code Section 5577.04 and Specification 105.12.

II. Any vehicle determined to be overloaded shall be cause for the assessment of liquidated damages to the vendor. For the purpose of assessing liquidated damages under this contract, the following schedule of maximum gross vehicle weights will be used to determine the extent of "overload" to which damages will apply. This schedule will apply in all cases except where paragraphs (c) or (d) below apply;

Vehicle Type Gross Vehicle Weight A) Single Unit Trucks

1) 2-axle, with 1 rear axle 32,000 lbs.

2) 3-axle, with 2 rear axles 47,000 lbs.

3) 4-axle, with 3 rear axles 60,000 lbs.

B) Tractor-trailer combinations 80,000 lbs.

C) In the event that any vehicle can legally exceed the above maximums, then the liquidated damage clause will not be invoked if and only if a written determination of the maximum legal gross vehicle weight under O.R.C. 5577.04 for that vehicle has been issued by the ODOT Special Hauling Permit Section and is presented upon demand.

D) In the event that the gross vehicle weight of any vehicle exceeds the maximum legal gross vehicle weight under O.R.C. 5577.04 for that vehicle, then the liquidated damage clause will not be invoked if and only if a Special Hauling Permit stating the permitted gross vehicle weight for that vehicle has been issued by the ODOT Hauling Permit Section and is presented upon demand.

III. Schedule of Liquidated Damage for Vehicle Overloads

Overload (lbs) Liquidated Damages 0 - 2,000 $80.00 2,001 - 5,000 $100.00 plus $1.00 per 100 lbs. of overload 5,001 - 10,000 $130.00 plus $2.00 per 100 lbs. of overload 10,001+ $160.00 plus $3.00 per 100 lbs. of overload

IV. Drivers of all vehicles being used to haul materials on this invitation, shall be informed by the vendor that liquidated damages shall be charged for overloads.

V. These provisions are strictly for the convenience of administering this regulation and shall not be construed to replace or waive any provision of the Ohio Revised Code pertaining to vehicle weight limitation.

Section 12: Sub-Vendors

Any use of sub-vendors will require written pre-approval from the Department. In addition, all sub-vendor invoices must be submitted to the Department with the vendor’s invoice. The Department will not pay any additional fees above those charged by the sub-vendor.

Section 13: Ohio EPA Division of Air Pollution Control Engineering Section Engineering Guide #57

Question:

What are the reasonably available control measures (RACM), pursuant to OAC rule 3745-17-

08(B), for fugitive dust emissions from the following operations at highway construction and maintenance projects:

1. Structural abrasive blasting,

2. Surface cleaning of concrete and other highway surfaces,

3. Concrete cutting,

4. Asphalt cutting, and

5. Bridge deck preparation for resurfacing.

Answer:

1) Structural Abrasive Blasting:

Structural abrasive blasting involves the removal of rust, scale, and old paint from metal surfaces on bridges prior to repainting. The following measures will be considered RACM for these operations.

An enclosure shall be erected to completely surround the blasting operation. This includes the area around and underneath the operation. The ground cannot be used as the bottom of the enclosure unless completely covered with plastic sheeting or a tarpaulin.

The enclosure shall be constructed of flexible material such as tarpaulins or containment screens which are specifically designed for this purpose, or of rigid materials such as plywood. All materials shall be maintained free of tears, cuts, or holes. However, flexible material used for the sides of the enclosure may be woven to contain a maximum of 15% holes and a minimum of 85% material. All seams shall be overlapped a minimum of 6" and fastened together at least at 12" intervals. The vertical sides of the enclosure shall extend completely up to the bottom of the deck on a steel beam bridge and up to at least the elevation of the blasting operation on a truss bridge.

Bulkheads shall be used between beams to enclose the blasting area.

All debris which has been collected by this operation or which has fallen to the ground shall be' collected and stored at the bridge site for testing, evaluation and disposal. Collection and storage services of an approved testing laboratory shall be obtained to evaluate a representative sample of the abrasive blasting debris (from each bridge) for the Toxic Characteristic Leaching Procedure

(TCLP) Test. Sampling shall be done within the first week of the abrasive blasting.

All sampling and testing shall be done in accordance with U.S. EPA Publication SW8 846. The test results of exceedances shall immediately be forwarded to the local air agency or Ohio EPA District

Office in whose jurisdiction the blasting project is taking place.

2) Surface Cleaning of Concrete and Other Highway Surfaces:

A) Smooth highway surfaces:

The surface cleaning operations on rough or smooth highway surfaces are performed to prepare the surface prior to the laying of asphalt or concrete or as general cleanup of the work area.

For smooth highway surfaces, the vacuum truck has been used in the highway construction industry for the past few years with great success because of the effective cleaning and the speed that the surface areas can be cleaned.

The vacuum truck uses a sweeping and vacuuming method of cleaning with a filter collector and an internal storage bin to hold the captured particulates. The filters in the vacuum have to be cleaned and maintained at frequent intervals. Also, the vacuum and sweeping equipment have to be in good repair for proper operation of the equipment.

Therefore, the use of a vacuum truck in good working order and with properly cleaned filters shall be the RACM for smooth highway surface cleaning.

B) Rough highway surfaces:

The cleaning of rough construction surfaces can be accomplished by different methods. In one method, a vacuum truck has a flexible vacuum hose attachment mounted on the rear of the truck.

This vacuum hose can be used for removal of surface dust from the rough surfaces and deep crevices. An alternative method would be to wet down the area and hand sweep the surface dust.

Either control method shall be used as the RACM for rough highway surface cleaning.

The use of the air lance (blowing of compressed air) should be used only after the vacuum truck and/or wetting has been used to clean the surface of a substantial amount of the surface dirt. If not used in this manner, an excessive amount of fugitive dust will be blown into the air.

For the general cleanup of the street or highway, a street sweeper has been used effectively. The street sweeper includes a water spray bar which wets down the street surface area and a sweeper/vacuum which removes the roadway dirt to a containment bin in the vehicle. Similar to the vacuum truck, the use of a street sweeper in good working order and with the water spray bar and sweeper/vacuum shall be considered the RACM for this general purpose cleanup.

3) Concrete Cutting:

Concrete cutting operations performed at highway projects use diamond or abrasive discs for hand-cutting operations and a Vermeer grinder wheel mounted on a construction vehicle for large cutting or trenching operations.

Operating experience has shown that a high-speed diamond disc must use water as a lubricant, while an abrasive disc can be used in dry cutting. However, the abrasive disc using water results in easier cuts. The Vermeer grinder wheel can be used in dry or wet cuts. A dry cut on the

Vermeer grinder wheel is also hard on the cutting teeth.

The use of water as a coolant lubricant for the cutter and as a means to keep down the emission of fugitive dust from the cutting operation is not only effective, but also very reasonable in cost.

Water is readily available from nearby city water line fire hydrants and also from water tank trucks that are commonly used on highway construction projects. A water storage tank also is usually available on the Vermeer grinder vehicle.

Therefore, the use of water in sufficient quantities to wet the cutter, the immediate surrounding work area, and the fugitive dust immediately emanating from the cut shall be considered as the

RACM for concrete cutting. As an optional control method, a hood or shroud surrounding the work area which contains the emission of fugitive dust may also be considered as the RACM for concrete cutting. In this case, the surface dust created by the concrete cutting should be promptly cleaned from the surface as outlined in item 2.

4) Asphalt Cutting:

Wet sawing, as used in concrete cutting, has proven effective in the cutting of asphalt as well as in the suppression of dust. The use of wet sawing shall be considered the RACM for asphalt cutting.

A vacuum/filter dust control option is currently being examined by the Ohio Contractors

Association. Should OEPA determine this option to be an effective dust suppression technique, it will be included in this Engineering Guide.

5) Bridge Deck Preparation for Resurfacing:

The first phase, milling or scarification, involves grinding down the upper layers of the concrete surface. The wastes, or millings, are then removed. The second phase of the rehab involves the major breaking out (jack hammering) and minor breaking out of the areas of delamination.

(Delamination is a term used for the concrete that has, through deterioration, lost contact with the metal reinforcement rods (rebar) in the bridge road bed.) After the major breaking out of the delaminated areas, the waste materials are removed. Major breaking out is followed by minor, breaking out. Minor breaking out involves smaller areas of delamination, is usually done manually, and generates less waste material. After minor breaking out, the waste materials are cleaned up.

The final phase in the preparation for resurfacing is the bridge deck and rebar cleaning. The purpose of the cleaning is to remove all grit and debris from the deck, and any scale from the rebar.

A) Deck milling or scarification:

The vacuum truck has been shown to be an effective means of cleaning milled surfaces. Therefore, the use of a vacuum truck in good working order and with properly cleaned filters shall be the

RACM for the milling or scarification process.

B) Major and minor breaking out of delaminated areas:

The cleaning of delaminated areas can be accomplished with the use of a vacuum truck. The flexible hose attachment on the rear of the truck can be used to clean up large pieces of debris, and the belly sweeping and vacuuming can be used to clean the deck surface. Therefore, the use of a vacuum truck in good working order and with properly cleaned filters shall be the RACM for major and minor breaking out of delaminated areas.

C) Final deck cleaning in preparation for resurfacing:

Originally, OEPA had recommended that the RACM for this process should be total enclosure with tarps. However, various contractors, as well as ODOT, have criticized this method of control, citing the cost-effectiveness as a problem. The use of tarps can vastly raise the cost of an operation due to the increased man-hours, as well as lengthen the time in which traffic lanes are closed.

In a 1994 letter to Tom Kalman of OEPA, Don Conaway of ODOT had proposed the use of

"dustless" abrasives as an alternative to total enclosure. The letter suggested these abrasives could be used effectively without causing a significant amount of dust. On October 18, 1995, ODOT demonstrated for RAPCA the use of these abrasives on a Clark County bridge. RAPCA found that the "dustless" abrasives actually caused excessive amounts of dust (in violation of the 20% opacity limit set in OAC 3745-17-07 (B)) and, therefore, determined that before this demonstration, OEPA had also recommended that high pressure water blasting be used to clean the exposed rebar.

ODOT denied the feasibility of this process, claiming that the water did not clean effectively. When asked about the use of water with abrasives, ODOT stated that the water would cause corrosion on the metal, which would then interfere with the concrete bond. After the demonstration, RAPCA asked ODOT for technical data supporting these claims.

In response, ODOT discovered that some research had shown that a slight corrosion left by moisture on a clean bar had actually improved the concrete to metal bond. ODOT has since decided to change their contractor specifications to include water blasting supplemented by abrasives. Allowing the contractors to use this process will enable them to achieve compliance with the applicable air pollution control regulations.

As a result of these communications with ODOT, the following measures will be considered the RACM for this cleaning operation:

Sandblasting followed by air lancing has been shown to effectively remove scale and corrosion from rebar and is capable of thoroughly cleaning all areas of the deck. RACM for this method shall be total enclosure of the bridge deck. The bridge deck enclosure shall meet the performance specifications outlined under structural abrasive blasting.

Alternatively, high pressure water blasting or water blasting supplemented by abrasives

(including sand) will also effectively clean the bridge deck and exposed rebar. These methods do not produce excessive fugitive dust, provided a sufficient amount of water is utilized when abrasives are employed. Therefore, the use of high-pressure water blasting or water blasting supplemented by abrasives shall be the RACM for final deck cleaning.

Equivalent alternative control methods may be used in all cases, where appropriate. The equivalency of alternative control methods for fugitive dust shall be evaluated by the local air agency or District Office of the Ohio EPA upon appropriate consultation with the Division of Air

Pollution Control. A determination of equivalency for RACM should be made in writing.

It should be noted that OAC rule 3745-17-07 (B) (1) is applicable to the fugitive dust generated by the above-mentioned highway construction and maintenance projects. This paragraph establishes an allowable visible emission limitation of 20% opacity, as a 3-minute average. Any RACM employed must be capable of meeting this visible emission limitation.

This Engineering Guide was used for training purposes during the joint winter conferences in

January and March of 1995 between OEPA, ODOT, and the Ohio Contractors Association.

December 9, 1992, revised April 3, 1996

Section 14: Off-Season Hauling (Between December 16 and March 31)

The intent of this section is to obtain loaded and unloaded (dead head) per mile pricing for various sizes of trucks to haul road salt or grits from a salt stockpile, salt mine, or aggregate plant location to ODOT locations around Ohio. This section may also be applied for the transportation of road salt from one ODOT facility (stockpile) to another ODOT facility (stockpile).

Along with its bid for the above per mile rates, a vendor should also submit a price per hour for wait time that shall be used to compensate the vendor for time spent in queue at a stockpile, salt mine, or ODOT location waiting to be loaded.

ODOT acknowledges that this section is being bid by the vendor on an “as available” basis and shall not hold the vendor responsible if unavailable to perform requested trucking services due to the unavailability of trucks and/or trucking hours.

Section 15: Blanket Purchase Orders

The Department may establish blanket purchase orders for a particular Vendor to pre-authorize funding for the products and/or services included in this Contract. The exact amount to be purchased is unknown and should not be construed by a Vendor as a commitment to purchase.

Blanket Purchase Orders should be kept on file by the Vendor and made available for use by the

Department. Department personnel will reference specific purchase orders when placing orders for products and/or services. These blanket purchase orders may be modified (including cancellation) at any time by the Department.

Vendors must submit their Bid Responses electronically in OhioBuys before the published deadline date & time, Columbus, Ohio local time on the Proposal due date.

Vendors will not be able to submit Bid Responses, or unsolicited Proposal amendments after the deadline.

Vendors must allow adequate time for uploading a Bid Response prior to the due date and time. ODOT recommends that vendors submit Bid Responses as early as possible.

If a second round is issued for any reason, vendors must resubmit their bid if they had already submitted in a previous round, as the previously submitted Bid Responses do NOT carry over to the new round.

The Signature process takes place after the award now. The email will come from documents@esign.ohio.gov and will go to the signatory that was identified in the bid submission. The subject line will be the bid # Signature Request, (example: 101G-25 Signature Request).

No contract can be issued to your company until we receive your signature to complete the process. And you must have an OAKS Payor ID before a contract can be issued. To obtain that, you will need to go into https://ohiopays.ohio.gov.

mailto:documents@esign.ohio.gov https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fohiopays.ohio.gov%2F&data=05%7C02%7CTodd.VanKirk%40dot.ohio.gov%7C1ac0731aa3fa4f066d5408dc7b4d0c36%7C50f8fcc494d84f0784eb36ed57c7c8a2%7C0%7C0%7C638520818049379076%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C0%7C%7C%7C&sdata=v8I%2Ba6H4M2smMVdNcvpoDrB2Dqsn4%2FJvMONLWyfwoxE%3D&reserved=0

File details come from the government source that posted it. Updated .