8-Change Order Form.pdf.pdf

PDF 201 KB Posted

Attached to
Cape Seal Pavement Preservation
Solicitation number
IFB-26-00111
Issued by
Hillsborough County, Florida

About this file

This is a Change Order Form from Hillsborough County, Florida, used to authorize modifications to existing construction contracts. The form provides a structured template for documenting changes to the scope of work, cost, and schedule of county contracts. It accommodates various types of changes including time extensions, extra work, credits, or other modifications. The form requires identification of the original contract details, including the contract number, bid number, contractor name, project number, and CPA number. It includes sections for describing the change, documenting cost impacts, and specifying reasons for the modification. The document tracks the original contract sum, cumulative impact of previous change orders, the new contract sum resulting from the current change order, and any adjustments to the final completion milestone.

The Change Order Form requires approvals from multiple county departments and officials, including the County Attorney (for legal sufficiency), the Department Fiscal Director, the Procurement department, and the Board of County Commissioners (BOCC). The contractor must provide authorized signatures and, if applicable, corporate acknowledgment through notarization. The form includes a separate section for surety consent, requiring the bonding company to acknowledge changes to the contract amount and/or completion date and confirm that performance and payment bonds are adjusted accordingly. The contractor waives claims for additional time extensions or monetary compensation beyond what is specified in the change order. The form was last revised on January 29, 2025, and applies to the Cape Seal Pavement Preservation project estimated at $2,010,823.90, which involves pavement treatment at four designated locations throughout Hillsborough County.

View the file

Other files

File Type Posted
12-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 09.docx DOCX document
24-Agreement - Construction - Stand Alone.docx.docx DOCX document
23-Performance Bond 07.02.25.doc DOC document
13-Attachment B - Emulsion Specifications.pdf PDF
3-Application for Payment.pdf.pdf PDF
20-Attachment C - Supplemental Specifications.pdf PDF
21-Bid Bond.doc.doc DOC document
16-Attachment G - Exhibit 4 Project-Map.pdf PDF
4-Consent of Surety-Change Order.pdf.pdf PDF
9-Insurance Certificate.doc.doc DOC document
7-Consent of Surety to Final Payment.pdf.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
19-Attachment D - Exhibit 1 Project-Map.pdf PDF
14-Attachment H - Insurance Requirements.pdf PDF
5-Contractors Affidavit for Payment of Debts and Claims.pdf.pdf PDF
2-Allowance Authorization Release Form.pdf.pdf PDF
10-Substitute W9 Form.pdf.pdf PDF
18-Attachment F - Exhibit 3 Project Map.pdf PDF
22-Payment Bond 07.02.25.doc DOC document
15-Attachment A - Sign Specifications.pdf PDF
25-IFB-26-00111 Contract Terms and Conditions.pdf PDF
17-Attachment E - Exhibit 2 Project-Map.pdf PDF
6-Subcontractors Statement of Satisfaction.pdf.pdf PDF
11-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 01.29.2025

HILLSBOROUGH COUNTY

CHANGE ORDER FORM

CONTRACT: CHANGE ORDER NO.:

BID NO:

CONTRACTOR: PROJECT NO:

CPA NO:

TIME CHANGE EXTRA WORK CREDIT OTHER

The Contractor is hereby authorized and directed to make the following changes and modifications to the aforesaid Contract in accordance with all requirements applicable thereto.

DESCRIPTION OF CHANGE:

COST

IMPACT

FINAL

COMPLETION

DAYS

REASON FOR CHANGE:

The original Contract Sum (TOTAL GMP) was . . . . . . . . . . . . $____________ Net change by previous Change Orders . . . . . . . . . . . . . . . . $____________ The Contract Sum prior to this Change Order was . . . . . . . . . . . . . $____________ The Contract Sum will be by this Change Order. . . . . . $ ____________ (increased, decreased or unchanged) The new Contract Sum including this Change Order will be . . . . . . . . . . $ ____________

The Final Completion Milestone prior to this Change Order was .

The time for Final Completion Milestone will be ______________ by __________( )days.

(extended, reduced or unchanged) The Final Milestone for this change order therefore is therefore

The Contractor waives any and all claims to additional time extension and/or additional monetary compensation resulting from these changes and all cost associated with the change order as herein addressed.

Excepting those terms and provisions conflicting with this Change Order which are hereby changed to conform hereto, the aforesaid Contract as amended by all previous change orders hereto is otherwise reaffirmed in its entirety.

IN WITNESS WHEREOF, this Change Order No. _______ to __________________________________ has been executed by the parties hereto or their duly authorized representatives.

ATTEST: VICTOR D. CRIST COUNTY: HILLSBOROUGH COUNTY FLORIDA

Clerk of Circuit Court

BY: BY:

Deputy Clerk Chair, Board of County Commissioners

BOCC Document Number Date of BOCC approval

ATTEST: CONTRACTOR:

BY:

Witness Authorized Signature (SEAL)

TITLE:

DATE:

BOCC Staff Approval Date

Department Fiscal Department Director Procurement County Attorney:

Approved as to Form and Legal Sufficiency

(ACKNOWLEDGMENT OF CONTRACTOR, IF A CORPORATION)

STATE OF )

COUNTY OF )

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this day of , 20 , by ______________________ (Name of person) as____________________________ for ___________________________________________________.

(ie. Officer, attorney in fact) (Name of party on behalf of whom instrument was executed.)

(Signature of Notary Public)

(Print, Type, or Stamp Name of Notary Public)

Personally Known OR Produced Identification

Type of Identification Produced ______________________

(ACKNOWLEDGMENT OF CONTRACTOR, IF A PARTNERSHIP OR INDIVIDUAL)

STATE OF )

COUNTY OF )

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this day of , 20 , by .

(Name of person acknowledging)

(Signature of Notary Public)

(Print, Type, or Stamp Name of Notary Public)

Personally Known OR Produced Identification

Type of Identification Produced ______________________

CONSENT OF SURETY TO CHANGE ORDER

CONTRACT TITLE:

CONTRACTOR (PRINCIPAL):

SURETY:

AGENT:

The SURETY does hereby acknowledge and agree to Change Order No. to the above referenced contract with Hillsborough County, the contract amount (increasing/decreasing) by $ , and/or extending the completion date by ( ) calendar days. The SURETY further acknowledges that the performance bond and/or payment bond furnished under the aforementioned contract is accordingly changed to reflect the change in contract amount, and/or time included in Change Order No. .

This Consent is dated this day of , 20 .

SURETY:

BY: (SEAL)

Authorized Signature

-OR-

BY: (SEAL)

As Attorney in Fact (Attach Power of Attorney)

Printed Name

STATE OF FLORIDA

COUNTY OF HILLSBOROUGH

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this ___ day of ____________, 20___, __________________________ by (Name of person) ________________________ for _________________________________________________.

(ie. Officer, attorney in fact) (Name of party on behalf of whom instrument was executed.)

(Signature of Notary Public) (Print, Type, or Stamp Name of Notary Public)

Personally Know OR Produced Identification

Type of Identification Produced __________________

File details come from the government source that posted it. Updated .