Rev. 1/6/14
JUSTIFICATION FOR SOLE SOURCE PROCUREMENT (OPEN
MARKET OR GSA) UNDER $150,000
Sole source acquisitions may be used on a limited basis and only when the Contracting Officer’s Representative (COR)/Program Official has provided sufficient justification and the Contracting Officer has determined that the circumstances warrant such action. The content for a justification must contain detailed facts and rationale to justify the sole source acquisition. Soliciting from a single source must be done in accordance with FAR 13.106-1(b) or 8.405-6. At a minimum, the following information must be included:
Identification of Program Office, Contracting Activity, and Proposed Requirement, Justification and Program Office Certification:
A. Program Office:
DHCPP/ Viral Special Pathogens Branch
Tara Sealy 1600 Clifton Road NE MS G-14 Centers for Disease Control and Prevention Atlanta, GA 30333
B. Contracting Activity:
Centers for Disease Control and Prevention Procurement and Grants Office Acquisition Branch 2
C. Identification of Requirement:
1. Nature of Action to be Approved by Contracting Officer:
a. Sole source acquisition of: Biotek Instruments Inc maintenance agreement
b. Procurement Request (PR) Number (if available):
2. Proposed Vendor and Estimated Procurement Amount (if available):
a. Proposed Vendor: Life Technologies Corporation
b. Estimated Procurement Amount: $8082.00 (base year plus option years)
3. Is the requirement on GSA Schedule? ☐ Yes ☒ No
If yes, provide schedule number:
D. Justification:
kpy3 Typewritten Text xxxxxxx kpy3 Typewritten Text xxxxxxxx kpy3 Typewritten Text xxxxxxxxxxxxxxxx kpy3 Typewritten Text xxxxxxxx
1. The justification for this non-competitive action is:
☒ In accordance with FAR 13.106-1(b)(1), “only one source [is] reasonably available” which states that, “For purchases not exceeding the simplified acquisition threshold. (i) Contracting officers may solicit from one source if the contracting officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization). (ii) Where a single source is identified to provide a portion of a purchase because that portion of the purchase specifies a particular brand-name item, the documentation in paragraph (b)(1)(i) of this section only applies to the portion of the purchase requiring brand-name item. The documentation should state it is covering only the portion of the acquisition which is brand- name.”
☐ Urgency
☐ Exclusive licensing agreements/Proprietary data
☐ Brand name required
☐ Industrial mobilization
☒ Other (e.g., compatibility, space issues, continuity, compatibility, etc.)
☐ In accordance with FAR 8.405-6 “Limiting Sources” which states that, “the only circumstances that may justify the action are – (A) An urgent and compelling need exists, and following the procedures would result in unacceptable delays; (B) Only one source is capable of providing the supplies or services required at the level of quality required because the supplies or services are unique or highly specialized; or (C) In the interest of economy and efficiency, the new work is a logical follow-up to an original Federal Supply Schedule order provided that the original order was placed in accordance with the applicable Federal Supply Schedule ordering procedures. The original BPA must not have been previously issued under sole-source or limited-sources procedures.”
☐ Urgency
☐ Only One Source
☐ Logical Follow Up
2. Other facts supporting sole source procurement:
a. What can this product/service do that other products/services cannot do?
We cannot use any other vendor to service this machine. It is a Biotek machine and ONLY Biotek have the specific parts, applicable software updates, and trained technicians with the appropriate product knowledge specific for this machine to service this piece of equipment. Also, Biotek does not authorize any third-party to service its’ machines as this would void the warranty.
b. What other products/services were considered and why did they not meet the need?
No other products/services were considered due to voiding the warranty.
3. Program Office efforts to seek potential offerors:
No other products/services were considered due to voiding the warranty.
E. Program Office Certification:
I have reviewed this sole source justification and certify the justification is true and accurate to the best of my knowledge and adequate to support other than full and open competition.
Center/Institute/Office COR/Program Official Name/Title: William Lonergan, COR I
Center/Institute/Office COR/Program Official Signature:
Certification Date: Click here to enter a date.
F. Contracting Office Certification:
I have fully relied on the information provided herein and hereby certify that this justification is accurate and complete to the best of my knowledge and belief:
Contracting Officer Name: Click here to enter text.
Contracting Officer Signature:
Certification Date: Click here to enter a date.
| Certification Date: Click here to enter a date. |
| Contracting Officer Name: Click here to enter text. |
| Certification Date: Click here to enter a date. |
| Yes: Off | |
| In accordance with FAR 84056 Limiting Sources which states that the only: Off | |
| Only One Source: Off | |
| 2018-04-12T16:05:56-0400 | |
| William Lonergan -S |
| undefined: | |
| 2018-06-19T18:35:00-0400 | |
| William Brannen -S |