70Z08525QDL1048_SOW.pdf
PDF 313 KB Posted
- Solicitation number
- 70Z08525QDL1048
About this file
This document is a Statement of Work (SOW) for the programming and service of the thruster system on the USCGC ASPEN. The USCG SFLC has an immediate need for technical support to commission the DECS 250 Voltage Regulator and troubleshoot/repair the faulty thruster system on the USCGC ASPEN. The contractor must provide all labor, materials, and tools necessary to install and commission the DECS 250 Voltage Regulator, as well as troubleshoot and repair the thruster breaker tripping and power fluctuations. The contractor must perform an operational test and provide a trip report documenting all findings. The period of performance is not to exceed 14 calendar days, and the primary place of performance is at the USCGC ASPEN's homeport in Homer, AK. This procurement is being conducted using commercial item procedures under FAR Part 12 and FAR Part 13 as a sole source contract to BIS Automation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70Z08525QDL1048_NOI.pdf | ||
| 70Z08525QDL1048_WD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAST UPDATED: 08/28/2024 PAGE 1/3
STATEMENT OF WORK (SOW)
FOR
USCGC ASPEN Thruster System Programming and Service
CGC ASPEN is experiencing thruster breaker trips and upgrading to the DECS 250 Voltage Regulator for their bow and stern thrusters and has an immediate need for technical support for tasks outlined in this Statement of Work (SOW).
1.0 GENERAL
1.1 BACKGROUND
The 225’ WLB asset, USCGC ASPEN, is upgrading to the DECS 250 Voltage Regulator for their thruster system. Additionally, the cutter is experiencing thruster system malfunctions, which includes; thruster breakers tripping, power fluctuations, and bow thruster tripping offline and is in need of technical assistance.
1.2 SCOPE
The scope of this contract is defined by the efforts and tools required to support USCGC ASPEN (WLB 208). The Contractor shall provide all labor, materials, and tools necessary to install and commission the DECS 250 Voltage Regulator on hand at CGC Aspen.
1.3 OBJECTIVE
The goal is to successfully commission the DECS 250 Voltage Regulator and troubleshoot and repair the faulty thruster system.
1.4 APPLICABLE DOCUMENTS
1.4.1 Compliance Documents
The following documents provide specifications, standards, or guidelines that must be complied with in order to meet the requirements of this contract:
Technical Publication Hull, Mechanical, & Electrical 3556
BOW AND STERN THRUSTERS
2.0 SPECIFIC REQUIREMENTS/TASKS
Unless otherwise stated, this contract applies to on-site support for USCGC ASPEN (WLB 208) at 4688 HOMER SPIT RD HOMER AK 99603-8001.
2.1 DECS 250 Commissioning
The Contractor shall perform any inspections, evaluations, tests, and/or tuning, as deemed necessary, to determine the most effective Voltage Regulator settings for proper thruster operation.
2.1.1 Contractor shall utilize their own laptop with required up-to-date software and communications cable.
2.1.2 The Contractor shall install the DECS 250 IAW OEM and USCG requirements.
LAST UPDATED: 08/28/2024 PAGE 2/3
2.1.3 The Contractor shall make parameter changes within DECS-250 Automatic Voltage Regulator to allow Thruster System to operate to 100% drive speed reliably.
2.1.4 The Contractor shall verify and document proper settings in the DECS- 250 voltage regulator.
2.1.5 The contractor shall fully commission the DECS-250, to include; fine tuning of all system parameters both dockside and underway.
2.1.6 Conduct full thruster test IAW compliant documents.
2.1.7 The contractor shall ensure that he DECS-250 meets the requirements set forth in TCTO 225-WLB-TH2030.0
2.1.8 Contractor Shall provide hard and digital copy of finalized voltage regulator setpoints.
2.1.9 Contractor shall troubleshoot and repair thruster breaker tripping open
2.1.10 Contractor shall troubleshoot and repair thruster power fluctuations.
2.2 Test Thoroughly and Document
The Contractor shall ensure the system is fully functional by preforming a system operational test to be witnessed by Engineer Officer (EO) or the EO’s designated representative.
2.2.1 The Contractor shall provide a trip report documenting all findings no later than 48 hours after returning to the home office.
3.0 CONTRACTOR PERSONNEL
3.1 The Contractor shall provide qualified personnel to perform all requirements specified in this SOW.
4.0 OTHER APPLICABLE CONDITIONS
4.1 PERIOD OF PERFORMANCE
The period of performance for this contract shall not exceed 14 calendar days from the date of award.
4.2 PLACE OF PERFORMANCE
The primary place of performance will be at CGC ASPEN’S homeport 4688 HOMER SPIT RD HOMER AK 99603-8001 USA unless an alternate location is approved by the Coast Guard.
4.3 HOURS OF OPERATION
Contractor employees shall generally perform all work between the hours of 0730 and 1600 EST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW. Precise times may be negotiated with the cutter Engineer Officer (EO) as scheduling is subject to ship’s operations.
4.4 Daily Progress Reports
LAST UPDATED: 08/28/2024 PAGE 3/3
The Contractor shall hold a daily progress meeting with the Engineer Officer and/or Commanding Officer upon arrival at the asset each morning of the visit. This report shall include a summary of all Contractor work performed, an assessment of technical progress, schedule status, and discuss any hazardous work conditions or necessary precautions the crew need to be made aware of prior to commencing work.
4.5 General Report Requirements
The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Windows and Microsoft Office Applications).
5.0 GOVERNMENT FURNISHED RESOURCES
NA
6.0 CONTRACTOR FURNISHED PROPERTY
The Contractor shall furnish all materials, equipment, and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in Section 5.0.
7.0 GOVERNMENT ACCEPTANCE PERIOD
The EO will inspect deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the EO will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
8.0 DELIVERABLES
The Contractor shall provide a trip report IAW 2.2 of this SOW.