USCGC HENRY BLAKE (WLM 563)
SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS
FY2019
Developed By: Jordan C Rank
(Rev-0, 21 February 2019)
USCGC HENRY BLAKE (WLM-175) UNPLANNED AVAILABILITY FY2019
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .................................................................................. v Consolidated List of Critical Inspection Items ............................................................................................. vi Principal Characteristics - TENDER .......................................................................................................... vii General Requirements WORK ITEM 1: Starboard Z-Drive, Propulsion Seals, Renew (Drydock) WORK ITEM 2: Fathometer Transducer, Renew WORK ITEM 3: Drydock WORK ITEM 4: Temporary Services, Provide - Cutter WORK ITEM 5: Sea Trial Performance, Support, Provide WORK ITEM 6: Towing Services, Provide iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 184-001, Rev-, CRP-V850 Transducer Adapter Ring Coast Guard Drawing 175 WLM 243-2, Rev F, Propulsion Shaft Arrangement Coast Guard Drawing 175 WLM 245-1, Rev A, Propeller Coast Guard Drawing 175 WLM 801-001, Rev A, Hull Lines Coast Guard Drawing 175 WLM 801-003, Rev A, Curves of Form Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Drawing
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual Coast Guard Commandant Instruction (COMDTINST) M16672.2D, Mar 1999, Navigation Rules, International-Inland Coast Guard Technical Publication (TP) 3653, Jul 2013; SWBS 245, Section A; Z-drive - Model 1350-H Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary
Services
OTHER REFERENCES
Commercial Item Description (CID) A-A-59323, Rev A, Cloths, Cleaning, Low-Lint Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert MIL-F-24402, May 1995, Filters (Hydraulic), Filter Elements (High Efficiency), and Filter Differential
Pressure Indicators, General Specification v (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
1 N Prop Shaft Seal NSN: 5330-20-009-3957 1 ea. 28,950.00 1 N **Seal Ring, MN
Bronze NSN: 5330-01-F15-4225 1 ea. 1,406.84
1 N **O-Ring NSN: 5331-21-912-4287 1 ea. 8,075.00 1 N **Lantern Ring NSN: 4320-21-912-4285 1 ea. 941.14 2 N ***Fathometer
Transducer, Shallow Water, 50-200 kHz
(Airmar Technology
SS505)
NSN: 5845-01-470-2500 1 ea. 343.63
3 Y *Transducer Cover Plate
N/A 2 ea. 50.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
1 Starboard Z-Drive, Propulsion Seals, Renew (Drydock) vii (Rev-0)
PRINCIPAL CHARACTERISTICS - TENDER
175' WLM, BUOY TENDER
PHYSICAL
Length overall 174' 8" Length between perpendiculars 155' 1" Depth 14' 8" Maximum beam 36' 0" Designed draft 8' 0" Mast height (above 8' waterline) 58' 8" Frame spacing 20" Full load displacement 855.15 Long Tons SW Light load displacement 719.78 Long Tons SW Minimum op condition displ 852.19 Long Tons SW
HULL
Hull material Steel
MACHINERY
Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM
Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio Shaft seal John Crane Type ND Shaft bearings Five pedestal mounted, Cooper split roller bearings Number of propellers 2 Number of blades 4 Diameter 57.1" Rudders None; Z-drive Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800
RPM
Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM
TANK CAPACITIES
Diesel oil capacity (100%) 16,385 gal Fresh water capacity (100%) 7,339 gal Lubricating oil (100%) 86 gal
1 (Rev-0)
00000_0618_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”
3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”
3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope."
3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
4 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
5 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
6 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
7 (Rev-0)
TIME
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading (mils)
Mean Reading (mils) IAW ASTM DD4417).
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-0)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
24500_JPH_0818_175
WORK ITEM 1: Starboard Z-Drive, Propulsion Seals, Renew (Drydock)
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the propeller shaft seals for a single designated Z-drive propulsion unit, in drydock. The designated unit is the Starboard.
1.2 Government-furnished property.
NOTE
Z-drive designation - port or starboard, or both will be indicated in the “Schedule of Supplies and Services or SECTION B” portion of the solicitation.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
N Prop Shaft Seal NSN: 5330-20-009-3957 1 ea. 28,950.00 N **Seal Ring, MN Bronze NSN: 5330-01-F15-4225 1 ea. 1,406.84 N **O-Ring NSN: 5331-21-912-4287 1 ea. 8,075.00 N **Lantern Ring NSN: 4320-21-912-4285 1 ea. 941.14
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 243-2, Rev F, Propulsion Shaft Arrangement Coast Guard Drawing 175 WLM 245-1, Rev A, Propeller
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3653, Jul 2013; SWBS 245, Section A; Z-drive - Model
1350-H Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
13 (Rev-0)
OTHER REFERENCES
Commercial Item Description (CID) A-A-59323, Rev A, Cloths, Cleaning, Low-Lint MIL-F-24402, May 1995, Filters (Hydraulic), Filter Elements (High Efficiency), and Filter
Differential Pressure Indicators, General Specification
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraphs:
• 3.3 (Z-drive initial inspection).
3.1.2 Tech Rep. The Contractor shall provide the services of an OEM authorized/ licensed Tech Rep for the Ulstein model number 1350-H (now Rolls Royce) Z-drive propulsion unit Rolls Royce System to accomplish the following on site:
• Provide manufacturer's proprietary system/ equipment information, software, and tools.
• Assist with and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.
3.1.2.1 Ensure the Tech Rep is an OEM Certified Representative for the system/equipment stated above and demonstrated on their résumé.
3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
NOTE
Plastic bags may be used only when arrangement or configuration prevents the use of the other sealing methods specified above.
3.1.4 Interferences. The Contractor shall Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
• Insulation and/or lagging
• Hydraulic piping and hoses
• ASW piping
• Pneumatic piping
• Lighting wiring and fixtures
14 (Rev-0)
• Control panels
• Electrical boxes.
• Portable railing bolted to the grating surrounding the Z-drive.
• Shaft guards/covers
3.2 System draining. Before inspecting and changing out seals, the Contractor shall drain the lubrication, steering, and seal oils from the designated Z-drive propulsion unit in accordance with TP- 3653 and Coast Guard Drawing 175 WLM 245-001. Dispose all drain fluids in accordance with applicable Federal, state, and local environmental regulations.
3.2.1 The quantities of existing system oil to be drained and disposed of are:
• Lube and Seal Oil - 120 gallons.
• Steering Oil - 92 gallons.
3.2.2 Once the systems have been drained, open all system tanks and clean to dry bare metal removing all condensation residue using new low-lint cleaning cloths conforming to CID A-A-59323, Type II.
3.3 Z-drive initial inspection. The Contractor shall clean the external portion of each Z-drive propulsion unit to remove any marine growth, dirt grease and surface contaminants. Visually inspect the propeller and external portion of the Z-drive propulsion unit for any damage, cracks, leakage, and other defects.
Submit A CIR.
3.4 Propeller removal and inspection. The Contractor shall accomplish the following tasks for the Z-drive propulsion unit propeller:
3.4.1 Remove the propellers from their shaft in accordance with all referenced Coast Guard drawings and CG TP-3653, Tab 245A “6.2 Propeller Removal Procedure”.
3.4.2 Once each propeller has successfully been broken free, is restrained, and hydraulic hose removed, the propeller nut may be fully removed, cleaned, and inspected. The exposed threads on shaft’s end shall be protected from damage by use of suitable tape or wrap.
3.4.3 Protect the removed propeller from damage until it is re-installed.
3.4.4 Thoroughly clean the removed propeller and remove all marine growth and fouling.
3.4.5 Perform a visual inspection of the propeller’s surfaces for damage or irregularities. Record the results noting the size and location of any defects found, the surface condition of the blades, any evidence of corrosion or cavitation. Submit a CFR.
3.5 Z-drive flushing with clean hot oil. If water has contaminated the Z-drive’s lubricating oil system, the Contractor shall follow the CG Provided Expert’s instructions to mitigate the effects of this water contamination. As a minimum this effort shall include a (a) complete oil fill and drain (b) flushing (and subsequent draining) the internals with clean hot system fluid, in an attempt to mitigate the effects and presence of residual water contamination and (c) flushing shipboard lube oil system including piping to and from the MDE attached pump, standby pump, and L/O cooler. Dispose all flushing fluids in accordance with applicable Federal, state, and local environmental regulations. Submit CFR with recommended additional procedures.
15 (Rev-0)
3.5.1 For the purpose of bid the following quantities of fill, flush, drain fluid required for this effort (these quantities of oil are for flushing only and do not include final fill quantities):
• Lube and Seal Oil - 180 gallons flushing oil.
• Steering Oil - 138 gallons flushing oil.
3.6 Propeller shaft seal renewal. With the propellers removed and the systems drained the Contractor shall renew the propeller shaft seals in the presence of the Tech Rep, in accordance with CG TP-3653, Tab 245A . Remove and inspect the companion seal ring (4803). A new upgraded seal D8202363 is to be installed in place of the older generation seal currently installed. The seal is provided GFM and includes all necessary parts including new sleeve and fasteners. All piece number identification in paragraph refer to Drawing D8202369/ D8202431 “Lower Unit Assembly” and/or Drawing D8202432 “Prop & Nozzle Assembly” included in CG Tech Pub 3653.
3.6.1 Inspect the shaft sleeve (item 106). Resurface the seal sleeve if required in accordance with cited procedure and per the Tech Rep guidance. Remove and inspect the companion seal ring (4803). Inspect the anode block (Item 130), submit CFR if renewal is recommended.
3.6.2 Unbolt and remove the seal set (D8202363). Inspect the seal sleeve (Item 106) for scoring in accordance with referenced procedure and submit CFR. Reassemble propeller shaft seal components using the Government-furnished rebuild kit.
3.6.3 The Government-furnished Propeller Seal Kit contains the following components of Drawing D8202363 included in CG Tech Pub 3653: 108, 109, 110, 111, 112, 113, 114, 115, 116, 117, 118, 121, 122, 124,125, 126,127, 129.
NOTE
All piece number identifications of above paragraph refer to Drawing D8202363 “Prop Shaft Seal Set-Imperial) and/or Drawing D8202395 “Prop & Nozzle Assembly” included in CG Tech Pub 3653.
3.7 Contractor furnished parts. For all disturbed seals, and/or gaskets, and capscrews (that are not already being replaced with the listed GFP) the Contractor shall obtain and provide renewal parts.
3.8 Propeller reinstallation. The Contractor shall reinstall the propellers in accordance with Coast Guard TP-3653, Tab 245A “Propeller Installation Procedure”. Use new o-ring (4807) on propeller nut (4806).
Install new gasket (4802) between propeller and seal ring (4803).
3.8.1 Inspect all disturbed and/or removed bolts, studs and nuts for damage and suitability for re-use. Coat the threads with anti-seize compound.
3.8.2 Be aware that the Government reserves the right to furnish propellers and/or new seal rings (4803), for installation in-place of the parts removed.
3.8.3 Upon completion of propeller installation of each unit, perform final visual inspection of the propeller assembly and submit a CFR.
3.9 System fluids replenishment. The Contractor shall furnish new replacement oils conforming to the manufacturer's recommendations to the seal oil tank, the Z-drive units and to the steering hydraulic systems. Follow the procedures for renewing the Contractor-furnished oils and filters in accordance with
16 (Rev-0)
TP-3653. The replacement oil shall be filtered through a non-bypass type filter with a 10-micron filter element conforming to MIL-F-24402 during refilling.
3.9.1 The total amount of new oil required for this entire specification is as follows:
• Lube and Seal Oil 140 gallons. Approved oils are shown in “Approved Mineral Lubricants” table of TP-3653.
NOTE
Previously 120 gallons was advertised as correct quantity of Lube and Seal Oil. That was based on the TP 3653, but actual experience has shown the true amount is closer to the above stated 140 gallons.
• Steering Oil 92 gallons. Approved oils are shown in “Approved Mineral Lubricants” table of
TP-3653.
3.9.2 Ensure that the tanks shall be inspected and verified by the Coast Guard Inspector prior to closing.
3.9.3 Renew all tank cover gasket materials.
3.10 Calibration. The Contractor in conjunction with Coast Guard Inspector shall calibrate the actual versus the indicated azimuth position mechanical indicators throughout the entire azimuth range in accordance with TP-3653. Coordinate with the Coast Guard Inspector during calibration to allow for the electronic indicators in the MPCMS and MSCC systems to be also verified true and accurate.
3.11 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the Z-drive systems to be in satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.
17 (Rev-0)
42410_0617_FLT
REC_42410_FLT_175 WLM (0715)
WORK ITEM 2: Fathometer Transducer, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the transducer(s).
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED COST
($/UNIT)
N ***Fathometer Transducer, Shallow Water, 50-200 kHz (Airmar Technology SS505)
NSN: 5845-01-518-6920 1 ea. 343.63
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 184-001, Rev-, CRP-V850 Transducer Adapter Ring
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert None.
3. REQUIREMENTS
3.1 General.
18 (Rev-0)
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.1 Transducer and lines. Protect all exposed ends of transmission lines, control lines, connectors, and cables from weather, moisture, and physical damage while they are disconnected from the transducer.
Take all necessary measures to protect transducer from damage during the performance of work specified herein. Inform the COR, in writing, of all damage, if any, that is incurred by the transducer.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Transducer renewal particulars. The Contractor shall accomplish the following tasks using Coast Guard Drawing 175 WLM 184-001 for guidance:
3.2.1 Transducer removal. Disconnect and remove the existing fathometer transducers. Retain the mounting hardware for reinstallation. Dispose of the removed transducers.
NOTE
Do not discard any hull ring adapter(s). They are to be reused with the new transducer(s).
3.2.2 New transducer installation. Install new Government-furnished transducer(s), in place of the removed. Reinstall each hull ring adapter and transducer in accordance with the applicable drawing listed in Section 2 (References) using new gaskets, mold release coating, and adhesive sealants. Apply mold release aerosol coating to both adaptor orifice and transducer to facilitate future removal of the transducer from the adaptor ring.
NOTE
A piece of neoprene or a washer may need to be placed at the bottom of the hull ring adaptor to facilitate transducer and bottom of hull ring flushness.
3.2.2.1 Using chocking compound as transducer bedding material, install transducer into hull ring adaptor. After the chocking compound has cured, paint the bottom half of the hull ring adaptor and transducer in accordance with drawing notes.
3.2.2.2 Renew the transducer head to hull ring gasket with new gasket conforming to HH-P-151, Class 4.
Using appropriate thickness gasket, place gasket on adaptor plate of transducer; apply ½” bead of marine adhesive on adaptor plate along the inside edge of the gasket. Install transducer flush with hull.
19 (Rev-0)
3.2.2.3 Reconnect each transducer cable to its terminal board in the adjacent connection box. Renew all stuffing tube packing and seals. Inspect the connection in the presence of the Coast Guard Inspector.
Submit a CFR. If cable renewal is authorized via approved Change Request, cut the transducer cable to length leaving 2-foot service loop in the cable. Ensure cables are installed in a manner to prevent any chaffing which may require new cable way clamps and stuffing tubes.
3.2.2.4 Following completion of transducer installation, fabricate a ¾” × 3” × ¼” aluminum label plate, engraved with ¼-inch high numbers stating the installation date. Affix a label plate, using suitable epoxy cement. Ensure that the label plate is visible and legible, without the need to move equipment or cables.
3.2.2.5 Thoroughly clean the transducer radiating surfaces with a strong solution of household detergent to remove any oil, dirt, and all other surface contaminants.
3.3 Transducer seal. If not waterborne, the Contractor shall inspect the transducer to ensure that its outer circumference is installed flush to the hull ring and the transducer cover plate forms a tight seal with the hull ring. Submit CFR.
3.4 Post installation tests. After completion of work, the Contractor shall accomplish the following tasks, in the presence of the Coast Guard Inspector:
3.4.1 Preliminary leak test. If not waterborne, inspect and perform a water hose test of all affected boundaries in accordance with SFLC Std Spec 0740, Appendix C. If waterborne, slowly back off the emergency cover plate bolts and allow seawater to flood the transducer well. No leakage allowed. Submit a CFR.
3.4.2 Not waterborne. Replace the hull ring set screws with new Monel fasteners, coating the threads with anti-seize compound. Recess the set screws ⅛” and cover with beeswax tallow.
3.4.3 Waterborne. Not Applicable.
3. 5 Leak repairs. The Contractor shall observe each transducer for leaks during the vessel re-floating process (if drydocked) or emergency cover plate removal (if waterborne). Repair all leaks detected.
Submit a CFR.
3.6 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test and prove the transducer(s) to be in satisfactory operating condition. Submit a CFR.
4.1 Operation of equipment. Coast Guard personnel will operate all shipboard machinery and equipment.
20 (Rev-0)
86340_1118_FLT
REC_86340_FLT_175 WLM (ALL) (0818)
WORK ITEM 3: Drydock
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to drydock the vessel, undock the vessel, and perform various drydocking-related tasks.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
Y *Transducer Cover Plate N/A 2 ea. 50.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 801-001, Rev A, Hull Lines Coast Guard Drawing 175 WLM 801-003, Rev A, Curves of Form Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Drawing
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):
21 (Rev-0)
• None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Key personnel. The Contractor shall determine key personnel and require their presence during all drydocking phases as required by SFLC Standard Spec 8634.
3.3 Docking and undocking. The Contractor shall perform drydock and undock in accordance with SFLC Std Spec 8634, using Coast Guard Drawing 175 WLM 801-001, 175 WLM 801-003, and 175 WLM 801- 006 for guidance.
3.4 Cutter conditions. The Contractor shall use the Full Load Condition, values listed below all in inches, for purposes of performing Pre-Award calculations as described in Appendix A (Requirements for Calculations) of SFLC Std Spec 8634.
• Displacement (LT SW): 878.473
• VCG (FT ABL): 14.072
• LCG (FT aft FP): 87.469
• LCF (FT aft FP): 91.327
• Trim (FT by bow): 0.274
• MT1” (LT-FT/Inch): 136.75
3.4.1 Blocking. The Contractor shall facilitate docking the vessel in block position by arranging keel and side blocks and ensuring minimum block heights as shown on the vessel's docking plan.
TABLE 1 - BLOCKING
Pos.
BLOCK HEIGHT ABOVE DOCKING
FACILITY DECK
Steel Plate
Situation Awareness
Fin Stabilizers Additional
Min. Rudder Removal
Propeller Removal
Shaft Removal
2 48" NA NA NA Sonar.
Ensure clearance around sonar(s) at Frames 21-22 and Frames 51-52.
NA None
22 (Rev-0)
This vessel has a Z-drive propulsion system.
3.4.2 Cable, sling, or strap tension calculation. If the Contractor plans to use a vertical lift, crane, or travel/mobile lift to haul out the vessel, the Contractor shall submit the cable, sling, or strap tension calculation specified in Table A1 and paragraph A2.7.2.7 of SFLC Std Spec 8634 with the Pre-Award calculations, using the loading condition specified in paragraph 3.4.
3.5 Pre-award calculations. The Contractor shall provide to the KO a set of pre-award calculations, as described in SFLC Std Spec 8634 Appendix A.
3.5.1 The Contractor shall provide vertical side/bilge block offsets for any side blocks placed in a location where vertical offsets are not already defined by the docking plan.
3.5.2 The Contractor shall submit an alternate blocking arrangement, as part of the pre-award calculation submission, to compensate for any changes from the docking plan.
3.5.2.1 If the alternate blocking arrangement interferes with the normal periodicity of U/W hull plate inspection or 100% preservation of U/W body surfaces, the Contractor shall include a plan and summary of how inspection/preservation will occur, in accordance with the prescribed docking plan, by means of removing, shifting, repositioning blocks; or fleeting the vessel at no cost to the Government.
NOTE
1. The USCG has established several approved alternate docking plans for each vessel-class, to facilitate complete access to the entire U/W body structure, for periodic comprehensive inspection and/or 100% preservation.
This inspection and preservation pattern and periodicity is a configuration management concern that is a vital requirement of the contract. Intention to deviate from these plans (fewer blocks, block spacing, additional blocks, etc) shall be identified on pre-award calculations (Paragraph 3.5.2); an alternate docking plan and mitigation strategy shall be provided to maintain preservation and inspection configuration.
2. Pre-award calculations may be deemed unsatisfactory - and may adversely affect contract award if they are submitted with the following detrimental factors:
a. No methods have been proposed that meet the requirements for the specified docking plan.
b. Proposed block shifting or fleeting risk-mitigating plan may result in delays in period of performance.
c. Proposed alternate docking plan violates USCG configuration management policies."
3.6 Unplanned availability: Underwater body cleaning-removal of marine growth. Conduct the work in this paragraph in lieu of the work described in SFLC Std Spec 8634 paragraphs 3.5.4.1 and 3.5.4.2.
Within four hours after the vessel has been docked, the Contractor shall start cleaning the entire underwater hull from the upper edge of the boot top down, including sea chest gratings, sea chest interiors, fairwaters, rope guards, rudder, shaft strut, z-drive, thruster tunnel, and zinc anodes, as
23 (Rev-0) applicable. The Contractor shall remove all marine growth, fouling, salt, and dirt from the underwater hull by High Pressure Fresh Water Wash, using a minimum pressure at the nozzle of 3,500 psi and maximum pressure of 7,000 psi. Complete the hull cleaning before marine growth hardens. Removal of gratings is not required.
WARNING
Do not use chemical additives in the freshwater wash. Take extreme care to avoid damaging or removing existing intact underwater body coating.
3.7 Fuel offloading. The Contractor shall be aware that fuel offloading is not mandatory to drydock the vessel.
3.8 Fleeting. Not required.
4.1 Arrival conditions. The COR will advise the Contractor of the actual tank and draft readings when the vessel arrives, and will discuss with the Contractor any liquid loading changes necessary.
24 (Rev-0)
86350_0617_FLT
REC_86350_FLT_175 WLM (ALL) (0813)
WORK ITEM 4: Temporary Services, Provide - Cutter
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to provide temporary services to the Cutter, during the performance of this availability.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against
25 (Rev-0) contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Temporary service particulars. The Contractor shall provide the below listed temporary services, in accordance with SFLC Std Spec 8635.
TABLE 1 - SERVICE SELECTION
*SUB-
PARAGRAPH TITLE Y/N
3.3.1 Office space N
3.3.2 Telephone and internet access N
3.3.3 Parking Y
3.3.4 Duty section berthing: N
3.3.5 Electrical power (including all requirements in associated sub-paragraphs) Y
3.3.6 Hull grounding straps (not applicable when cutter is waterborne) Y
3.3.7 Compressed air (including all requirements in associated sub-paragraphs) N
3.3.8 Hazardous material/hazardous waste disposal (see Tables 2 and 3 below) N
3.3.9 Heavy lift equipment: N
3.3.10 Water supply
3.3.10.1 Potable water: 250 gallons per day, at 60 psig. Y
3.3.10.2 Hot-circulating water N
3.3.10.3 Cooling water N
3.3.10.4 Firemain system (including all requirements in associated sub-paragraphs) Y
3.3.11 Steam (including all requirements in associated sub-paragraphs) N
3.3.12 Refuse disposal Y
3.3.13 Sewage and grey water disposal (including all requirements in associated sub-paragraphs) Y
3.3.14 Storage – General (including all requirements in associated sub-paragraphs):
3.3.14 Dry stores. N
3.3.14 Paint and flammable stores. N
3.3.14 Refrigerated stores. N
3.3.15 Small boat storage (including all requirements in associated sub-paragraphs) N *Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 8635.
TABLE 2 - HAZARDOUS WASTE DISPOSAL – LIQUIDS (GALLONS)
PAINT THINNERS ENGINE COOLANT BILGE WATER
xx xx xx
TABLE 3 - HAZARDOUS WASTE DISPOSAL – SOLIDS
OILY
FILTERS
OILY RAGS
(LBS)
EMPTY 1-GAL
CONTAINER*
EMPTY 5-GAL
CONTAINER*
EMPTY 55-GAL
CONTAINER*
xx xx xx xx xx *Previously housed hazardous materials.
26 (Rev-0)
3.2 Extended temporary services. If the performance period of the contract is extended by the KO, the contractor shall continue to provide all temporary services as specified herein for the extension period.
This section is not applicable to this work item.
27 (Rev-0)
86850_0917_FLT
WORK ITEM 5: Sea Trial…