CGC_CLAMP_(WLIC_75D)_SPECIFICATIONS.pdf
PDF 908 KB Posted
- Attached to
- DOCKSIDE REPAIRS FOR THE CGC CLAMP
- Solicitation number
- 70Z085-19-Q-P4527700_
About this file
SPECIFICATIONS/WORKSTATEMENT
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CGC_CLAMP_SECTION_B.xls | XLS spreadsheet | |
| CGC_CLAMP_-_OMBUDSMAN.doc | DOC document | |
| CGC_CLAMP_-_Attachment_-Request_for_Clarification.doc | DOC document | |
| CGC_CLAMP_70Z085-19-Q-P45027700.docx | DOCX document | |
| CGC_CLAMP_-__PAST_PERFORMANCE_INFORMATION_FORM.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC CLAMP (WLIC 75306)
USCG 68B BARGE (68016)
SPECIFICATION FOR MINI DOCKSIDE REPAIRS
FY2019
Developed By: Jordan Rank
(Rev-1, 18 December 2018)
USCGC CLAMP (WLIC-75D) DOCKSIDE AVAILABILITY FY2019
ii (Rev-1)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics - Tender ............................................................................................................. viii Principal Characteristics - Barge .................................................................................................................. ix General Requirements WORK ITEM 1: Sewage Holding Tank(s), Clean and Inspect - Tender WORK ITEM 2: Grey Water Piping, Clean And Flush WORK ITEM 3: Sewage Piping, Clean And Flush WORK ITEM 4: Boiler and Piping, Renew WORK ITEM 5: Tanks (Potable Water), Preserve “100%” - Tender WORK ITEM 6: Tanks (Potable Water), Preserve “100%” - Barge iii (Rev-1)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
12/18/2018 1 23 3.2 Removed “in Table 1” added “by the Coast Guard
Inspector”
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-1)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 68 CGB-1101-1, Sheet 1, Rev - , Structural Sections and Details
Coast Guard Drawing 68-CGB-2901-2, Sheet 2, Rev, Tank Capacity Tables
Coast Guard Drawing 75 WLIC 123-2, Rev-, Sewage Tank
Coast Guard Drawing 75 WLIC 593-3, Rev, A, Diagram Sewage Treatment & Discharge System
Coast Guard Drawing 75 WLIC 593-4, Rev, B, Arrgt Sewage Treatment & Discharge System
Coast Guard Drawing 75B-WAGL 3802-1, Rev -, Heating System Mods
Coast Guard Drawing 75D WAGL 4804-1 F.W. Piping & Flushing Sys
Coast Guard Drawing 75D WAGL 4804-2 Fresh WTR & Waste Piping Plan
Coast Guard Drawing 75D WAGL 4804-3 Fresh WTR & Waste Piping Sects
Coast Guard Drawing 75D-WAGL 3801-1, Rev B, Vent Heating & A/C (75306-75307)
Coast Guard Drawing 75D-WAGL 3901-1, Rev A, Insulation & Sheathing Sched (75306-75307)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2014, General
Requirements
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6310, 2014, Requirements for
Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Preserve Ship
Structures
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary
Hull Accesses
Coast Guard Technical Publication (TP) 1882, Manufacturer's Instruction Book-SWBS Group(s) 233-551
OTHER REFERENCES
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning v (Rev-1)
American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System
Components - Health Effects
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities vi (Rev-1)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
This section is not applicable to this package.
vii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
This section is not applicable to this package.
viii (Rev-1)
PRINCIPAL CHARACTERISTICS - TENDER
75' WLIC (D-CLASS), TENDER
PHYSICAL
Length overall 75' 0"
Depth 7' 7-3/4"
Maximum beam 22' 0"
Height of highest projection 32' 0"
Full load draft 4' 4 11/16" LCF Draft
Full load displacement 148.49 Long Tons Fresh Water
Shore tie voltage requirements 440 VAC / 3 Phase
Frame spacing 1' 6"
HULL
Hull material Steel
MACHINERY
Number of propellers 2
Number of blades 4
Diameter of propeller 48"
Pitch 40" fixed
RPM 400
Shaft Diameter 4.5”
TANK CAPACITIES
Fuel tanks
Fresh water tanks
Lube oil ix (Rev-1)
PRINCIPAL CHARACTERISTICS - BARGE
68' CGB (B-CLASS: 68016 -68020), BARGE
PHYSICAL
Length overall 68' 6-1/2"
Depth 7' 0"
Maximum beam 28' 0"
Full load draft 3' 0"
Full load displacement 117 Long Tons
Shore tie voltage requirements 440 VAC / 3 Phase
Frame spacing 1' 0"
1 (Rev-1)
00000_0618_FLT
REC_00000_FLT_Commercial Project @ CG Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-1)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC
Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is conditionally exempt small quantity generator.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public
3 (Rev-1) notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For
Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor shall be aware of the following:
3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint
Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”
3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of
4 (Rev-1)
SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”
3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay
(RRL) wire rope or Dyform-18, rotation resistant wire rope."
3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-1)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
6 (Rev-1)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
7 (Rev-1)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
8 (Rev-1)
TIME
9 (Rev-1)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading
(mils)
Mean Reading (mils) IAW ASTM DD4417).
10 (Rev-1)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-1)
12 (Rev-1)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic
Pull-Off (Type I/Banana) Gauge Is
Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
13 (Rev-1)
59302_ESD _1017_FLT
REC_59301_FLT_75 WLIC (‘D’ Class: Hulls 75306, 75309, 75310) (0711)
WORK ITEM 1: Sewage Holding Tank(s), Clean and Inspect - Tender
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TABLE 1 – TANKS
TYPE OF TANK LOCATION CAPACITY - 95%
(Gallons)
LOW SUCTION (Gallons)
Sewage Collection Tank Forward hold 2-7-0-A 1000 50
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 75 WLIC 123-2, Rev-, Sewage Tank
Coast Guard Drawing 75 WLIC 593-3, Rev, A, Diagram Sewage Treatment & Discharge
System
Coast Guard Drawing 75 WLIC 593-4, Rev, B, Arrgt Sewage Treatment & Discharge
System
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet
Gaskets
14 (Rev-1)
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.1 Plug all inlet and outlet piping in the tank(s) to prevent contaminants from entering. Use plugs with an attached lanyard, ring or other system that will ensure plugs are not lost in the pipe openings.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std
Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Piping.
Pump(s).
3.1.5 Plug log. The Contractor shall keep a written record of all plugs put in any tank vents. A separate list shall be kept for each tank being entered.
3.1.5.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.1.5.2 The plug log shall be available to the Coast Guard Inspector when the inspector is performing his close-out inspection on each tank.
3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast
Guard personnel perform an operational pre-test to demonstrate all tank TLIs' existing operational condition. Submit a CFR.
3.3 Service disruption. When sewage collection service is disrupted due to contractor repairs, the
Contractor shall refer to SFLC Standard Spec 0000 par 3.2.11 to provide required temporary facilities.
3.4 Cleaning and inspection requirements. The Contractor shall accomplish the following for the tank(s) listed in paragraph 1.1 (Intent), referring to Coast Guard Drawings 75 WLIC 123-2, 75
WLIC 593-3, and 75 WLIC 593-4 for guidance:
3.4.1 Content removal. Remove and dispose of all contents, fluids, and/or residues in accordance with all applicable Federal, state, and local regulations
15 (Rev-1)
3.4.2 Cleaning requirements. Remove manhole cover(s). Clean all tank structure’s interior surfaces free of all foreign materials, sediment, and sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations. Clean all tank vent lines. Remove and clean the eductors and level switches inside of the tank(s). Reinstall the eductors and level switches upon completion of tank cleaning. Use new gaskets and o-rings to install/reinstall all removed/disturbed components.
3.4.3 Inspection. Visually inspect all interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
Tank structural condition.
Inaccessible areas.
Condition of tank coating, including measurements, percentage, location, and type of coating failure (not applicable for stainless steel tanks).
Tank level indicator (TLI), vacuum and/or float switch condition.
Suction and discharge piping and vent line condition.
Fastener material (stainless steel) and condition.
Zinc anode condition (remaining percentage).
3.4.4 Control panel assembly. Open and vacuum clean the control panel assembly. Inspect the control panel assembly for any indications of overheating or loose wiring or connections. Submit a CFR
3.5 Closing. The Contractor shall notify the COR at least 24 hours prior to closing the tank(s).
After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close the manhole cover(s) with new gasket material conforming to ASTM D1330.
3.5.1 Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing fasteners. Existing undamaged fasteners may be reused. For purpose of bid, assume 10% of existing fasteners will require renewal. Renew all nylon insert nuts.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.6 Operational test – post repairs. After completion of work, the Contractor shall accomplish the following in the presence of the Coast Guard Inspector, and submit a CFR:
3.6.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.
3.6.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.
16 (Rev-1)
3.6.3 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tank(s) to the limit of the ship’s installed pumps.
4. NOTES
This section is not applicable to this work item.
17 (Rev-1)
59320_0618_FLT
REC_59320_FLT_75 WLIC (‘D’ Class: Hulls 75306, 75309, 75310) (1113)
WORK ITEM 2: Grey Water Piping, Clean And Flush
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the grey water piping system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 75D WAGL 4804-1 F.W. Piping & Flushing Sys
Coast Guard Drawing 75D WAGL 4804-2 Fresh WTR & Waste Piping Plan
Coast Guard Drawing 75D WAGL 4804-3 Fresh WTR & Waste Piping Sects
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
18 (Rev-1)
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std
Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Piping
Wire Runs
3.2 Contamination prevention. The Contractor shall take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.
3.3 Personnel qualification. The Contractor shall ensure that personnel accomplishing this work are qualified and experienced in operating the pressurized water system and handling the chemicals. For each operator/cleaning technician, submit documentation of applicable experience and training obtained within the last twelve months along with the Cleaning Plan (see paragraph
3.5.2 (Plan Submittal)).
3.4 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast
Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.5 Piping hydrojet cleaning. The Contractor shall perform the following work:
3.5.1 The Contractor shall clean and flush the entire grey water system piping shown on Coast
Guard Drawing 75D WAGL 4804-1, -2, and -3 approx 110 linear feet.
3.5.2 Prior to commencing work, coordinate with the Coast Guard Inspector. Determine required down times for affected piping system. Determine the feasibility/need for the piping system to be split to minimize system down time.
3.5.3 With the aid of ship’s force, split the plumbing drain system fore and aft by closing isolation valves in the drainage system. Work on only one section of the plumbing drain system at a time to allow use of toilet and shower facilities in the other section of the system by the ship’s duty section.
3.5.4 Using the referenced Coast Guard drawings as guidance, hydro blast the internal surfaces of all of the plumbing drain piping. Hydro blast pressure shall be at least 2500 psig at the discharge nozzle in all piping to ensure removal of all salts and scale from piping internal surfaces.
3.5.4.1 Ship’s force will provide an assistant to the Contractor to show the Contractor the location of clean-out connections within the plumbing drain system.
3.5.4.2 Open each of the clean out connections as required to clean and hydro blast all of the internal piping within the system. Catch any fluid that drains from the clean out connections when it is opened and clean up any spills using bleach to disinfect the spill after cleaning.
19 (Rev-1)
3.5.4.3 It may be necessary for the Contractor to install additional clean-out connections to access all portions of the plumbing drain system. If additional clean-out connections are needed, a separate specification item in this specification package shall be authorized to install additional clean-out connections.
3.5.4.4 Hydro blast cleaning water may be collected in the ship’s sewage system and disposed of via the ship’s sewage shore tie connections.
3.5.5 Clean until all of the following conditions are met:
All visible calcium carbonate deposits, solid deposits and build-up are removed from pipe walls.
Discharge water from the piping being cleaned is free of all visible scale and deposits.
3.5.5.1 Inspect the piping interior using a borescope in the presence of the COR, to verify that all solid deposits visible to the unmagnified eye have been removed. Continue the cleaning process until all visible solid deposits are removed from the pipe walls.
3.5.6 In the event that hydroblasting alone does not clean piping to required conditions, Contractor shall use chemical cleaning methods.
3.5.6.1 Ensure that chemical cleaners do not damage the environment, heat exchanger or the vessel.
3.5.6.2 Submit the written plan for chemical cleaning to the COR for approval. The procedure shall include products to be used, safety precautions, disposal requirements, sequence of events, etc.
CAUTION
Submit a MSDS to the COR for all chemicals proposed for use.
3.5.6.3 Chemical cleaning waste water disposal. Dispose of all cleaning fluids and debris in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item. Do not drain any fluids
(including fresh water) into any space, bilge, or exterior location.
Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.
3.6 Valves. The Contractor shall replace system tank valve(s) with temporary spool piece(s).
Visually inspect system valve(s); and submit a CFR. Upon completion of work, reinstall the removed tank valve(s) with new gaskets.
3.7 Gasket renewal. The Contractor shall reinstall all removed valves and fittings with new gasket material conforming to applicable referenced drawings.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
20 (Rev-1)
3.8 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition.
Submit a CFR.
3.8.1 Leak test. After all system components are reinstalled, the Contractor shall test all disturbed piping for leaks, as follows, and submit a CFR:
Plug all system openings (except the highest) and fill system with water to the point of overflow. Ensure that the water level does not go down (without adding any water) for sufficient time to inspect the entire system (no less than 15 minutes).
Closely monitor the system for leaks. Repair all leaks detected.
Repeat test and inspection until no leaks are detected.
21 (Rev-1)
59321_0418_FLT
REC_59320_FLT_75 WLIC (‘D’ Class: Hulls 75306, 75309, 75310) (1113)
WORK ITEM 3: Sewage Piping, Clean And Flush
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage piping system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 75 WLIC 593-3, Rev, A, Diagram Sewage Treatment & Discharge
System
Coast Guard Drawing 75 WLIC 593-4, Rev, B, Arrgt Sewage Treatment & Discharge
System
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet
Gaskets
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
3.1.1 CIR.
3.1.2 Tech Rep.
22 (Rev-1)
Not applicable.
3.1.3 Protective measures. The and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std
Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Sewage pumps
Toilets
Overhead piping
Cable runs
Light fixtures
Water-mist system
3.2 Contamination prevention. The Contractor shall take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.
3.3 Personnel qualification. The Contractor shall ensure that personnel accomplishing this work are qualified and experienced in operating the pressurized water system and handling the chemicals. For each operator/cleaning technician, submit documentation of applicable experience and training obtained within the last twelve months along with the Cleaning Plan.
3.4 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast
Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.5 Cleaning plan. The Contractor shall establish a plan for cleaning the designated piping system, listing the step by step procedures necessary to ensure that all foreign debris is removed from the piping system.
CAUTION
Although the Coast Guard prefers pressurized water as the cleaning fluid, the Contractor may propose chemical cleaning as an alternative, providing that the proposed chemical cleaning agent conforms to
DOD-STD-2187 (where applicable), is environmentally safe, and pre-approved by the COR. Due to the fact that system piping has historically been difficult to clean by pressure washing only, chemical cleaning is usually required to successfully complete the cleaning process.
Submit a MSDS to the COR for all chemicals proposed for use.
3.5.1 Procedure requirements. The Contractor shall ensure that the procedure includes the following:
23 (Rev-1)
Methods of cleaning.
All safety precautions required during cleaning operations.
List of qualified personnel who will operate machinery or handle chemicals (see paragraph 3.3 (Personnel qualification) herein).
Locations in the sewage piping where cleaning will take place, and any additional fittings necessary.
Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.
3.5.2 Plan submittal. The Contractor shall submit the written plan to the COR for approval at least
48 hours prior to commencing cleaning operations.
3.6 Clean and flush. The Contractor shall clean and flush the entire sewage system piping shown on Coast Guard Drawing 75 WLIC 593-3 and 75 WLIC 593-4 approx 60 linear feet.
3.6.1 Pumps and valves. Replace system tank valve(s) with temporary spool piece(s) before cleaning. Visually inspect system pumps and valve(s); and submit a CFR. Upon completion of work, reinstall the removed tank valve(s) with new gaskets.
3.6.2 Cleaning. Continue cleaning until all of the following conditions are met:
All visible calcium carbonate deposits, solid deposits and build-up are removed from pipe walls.
Discharge water from the piping being cleaned is free of all visible scale and deposits.
3.6.3 Inspect the piping interior using a borescope in the presence of the COR, to verify that all solid deposits visible to the unmagnified eye have been removed. Continue the cleaning process until all visible solid deposits are removed from the pipe walls.
3.7 Waste disposal. The Contractor shall dispose of all cleaning fluids and debris in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from
USCG property immediately upon completion of work item. Do not drain any fluids (including fresh water) into any space, bilge, or exterior location.
3.8 Gasket renewal. The Contractor shall reinstall all removed valves and fittings with new gasket material conforming to ASTM D1330.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.9 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition.
Submit a CFR.
3.9.1 Leak test. After all system components are reinstalled, the Contractor shall test all disturbed piping for leaks, as follows, and submit a CFR:
24 (Rev-1)
Plug all system openings (except the highest) and fill system with water to the point of overflow. Ensure that the water level does not go down (without adding any water) for sufficient time to inspect the entire system (no less than 15 minutes).
Closely monitor the system for leaks. Repair all leaks detected.
Repeat test and inspection until no leaks are detected.
25 (Rev-1)
S18_010_51700_CKN_0818_75306
WORK ITEM 4: Boiler and Piping, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the specified boiler and piping.
1.2 Government-furnished property.
None
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 75D-WAGL 3801-1, Rev B, Vent Heating & A/C (75306-75307)
Coast Guard Drawing 75D-WAGL 3901-1, Rev A, Insulation & Sheathing Sched
(75306-75307)
Coast Guard Drawing 75B-WAGL 3802-1, Rev -, Heating System Mods
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 1882, Manufacturer's Instruction Book-SWBS
Group(s) 233-551
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Preserve Ship Structures
OTHER REFERENCES
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3
(SSPC-SP 3), 2004, Power Tool Cleaning
3. REQUIREMENTS
3.1.1 CIR.
26 (Rev-1)
3.1.2 The Contractor shall inspect the ship’s Boiler system, and submit a CFR.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec
0000, paragraph 3.3.5 (Interferences):
Insulation.
Piping/ Hand rail.
Electric cables.
Bulkhead/overhead/Ladder well
Battery bank.
3.1.5 Work locations. The Contractor shall be aware that work areas shall primarily include but not be limited to the following:
Tender Engine Room (2-18-0-E).
3.1.6 Disconnect any interferences and necessary piping, and remove all valves. Install blank flanges with gaskets over the pipe openings, securing with at least four bolts, 90 degrees apart.
Pipe plugs or other closures may be used to prevent contamination of the system, depending on the valve removed. Blank flanges shall be at least ¼" thick.
3.2 Boiler Removal – Remove the Boiler from the designated work area(s). Dispose in accordance with local, state, and federal laws and regulations.
3.3 In the presence of the Coast Guard Inspector, inspect all prepared surfaces for deterioration or damage. Submit a CFR to the Coast Guard Inspector.
3.4 Installation – Install new in kind Boiler unit, control system in accordance with referenced
CG Drawing 75B-WAGL 3802-1 and General Requirements.
MAKE AND MODEL TYPE/SIZE MAX OUTPUT DEVIVERY RATE WEIGHT
WAY WOLFF 2128-8C
SERIAL #3651
SHIP
BOILER/2128-8C
210,000BTU
125 GPH normal
200 GPH max
700 Lbs
3.4.1 Renew 20 feet of 1 ½ copper pipe, 3 globe valves and 12 associated unions, tees and elbows in according with CG Drawing 75B-WAGL 4804-2. Insulation and paint as required.
3.5 Surface Preparation – Prepare all steel surfaces where insulation was removed by power tool cleaning in accordance with SSPC-SP 33.4.1 .
27 (Rev-1)
3.6 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel) of all items or shipboard devices that have been disturbed, used, repaired, altered, or installed, to prove that they are in satisfactory operating condition in according to General Requirements.
3.7 Compartment Restoration. Restore all affected work areas to a clean condition.
28 (Rev-1)
63110_0717_FLT
REC_12314_FLT_75 WLIC (‘D’ Class: Hulls 75306,75309, 75310) (0611)
WORK ITEM 5: Tanks (Potable Water), Preserve “100%” - Tender
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to prepare and coat
100% of the surfaces of the following tank(s):
TYPE OF TANK LOCATION CAPACITY - 95%
(GALLONS)
LOW SUCTION
(GALLONS)
Potable Water 2-15-0-W, Tender 1,382 80
Potable Water 2-35-0-W, Tender 1,279 80
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary Hull Accesses
OTHER REFERENCES
American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects
American National Standards Institute/American Water Works Association
(ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
29 (Rev-1)
3.1 General. The Contractor shall ensure the following:
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the
Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std
Spec 0000, paragraph 3.3.5 (Interferences).
3.1.5 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph
3.2.4.2 (In-process QC measures for “critical-coated” surfaces).
NOTE
Surfaces being preserved are considered “critical-coated surfaces”.
3.1.6 Temporary access openings. Due to limited access to work areas, the Contractor may, with express permission of the KO (via submission of a CFR), cut access holes to facilitate accomplishment of the work specified herein.