USCGC GREENBRIER (WLR 75501)

USCG 130 BARGE (13075)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2018

Developed By: Alessandra K. Twomey

(Rev-0, 20 December 2017)

USCGC GREENBRIER (WLR-75F) DRYDOCK AVAILABILITY FY2018

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics - Tender .............................................................................................................. xii Principal Characteristics - Barge ............................................................................................................... xiii General Requirements WORK ITEM 1: Hull Plating (U/W Body), Inspect- Tender WORK ITEM 2: Hull Plating (U/W Body), Inspect - Barge WORK ITEM 3: Hull Plating (U/W Body), Ultrasonic Testing - Tender WORK ITEM 4: Hull Plating (U/W Body), Ultrasonic Testing - Barge WORK ITEM 5: Tanks (Mp Fuel Stowage And Overflow), Clean And Inspect - Barge WORK ITEM 6: Voids (Non-Accessible), Leak Test - Tender WORK ITEM 7: Voids (Non-Accessible), Leak Test - Barge WORK ITEM 8: Voids (Non-Accessible), Internal Surfaces, Preserve - Tender WORK ITEM 9: Voids (Non-Accessible), Internal Surfaces, Preserve - Barge WORK ITEM 10: Tanks (MP Fuel Service), Clean and Inspect - Tender WORK ITEM 11: Propulsion Shafting; Remove, Inspect, and Reinstall WORK ITEM 12: Propulsion Shafting, Straighten WORK ITEM 13: Propeller Shaft Sleeve(s), Renew WORK ITEM 14: Propulsion Shaft Bearings (External), Check Clearances WORK ITEM 15: Propulsion Shaft Bearings (External), Renew WORK ITEM 16: Propellers, Remove, Inspect, and Reinstall WORK ITEM 17: Propeller, Minor Repairs and Reconditioning, Perform WORK ITEM 18: Keel Coolers, Clean, Inspect and Hydro - Tender WORK ITEM 19: Keel Coolers, Clean, Inspect and Hydro - Barge WORK ITEM 20: Fathometer Transducer, Renew – Tender WORK ITEM 21: Fathometer Transducer, Renew – Barge WORK ITEM 22: Rudder Assembly; Remove, Inspect and Reinstall WORK ITEM 23: Rudder(s), Preserve (“100%”) WORK ITEM 24: Hull Fittings (Weight Handling Rigging Hardware), Inspect and Test - Barge WORK ITEM 25: Spuds, Overhaul - Tender WORK ITEM 26: Spuds, Overhaul - Barge WORK ITEM 27: Spud Wells, Preserve - Tender WORK ITEM 28: Spud Wells, Preserve - Barge WORK ITEM 29: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 30: U/W Body, Preserve (100%) - Tender WORK ITEM 31: U/W Body, Preserve (100%) - Barge WORK ITEM 32: Superstructure, Preserve “100%” WORK ITEM 33: Cathodic Protection / Magnesium Anodes, Renew - Tender WORK ITEM 34: Cathodic Protection / Magnesium Anodes, Renew - Barge WORK ITEM 35: Drydock - Tender WORK ITEM 36: Drydock - Barge WORK ITEM 37: Temporary Services, Provide - Tender WORK ITEM 38: Sea Trial Performance, Support, Provide WORK ITEM 39: Boat Davit Winch, Shrink Wrap WORK ITEM 40: Buoy and Cargo Handling Crane, Shrink Wrap WORK ITEM 41: Navigation Light and Panel, Upgrade iii (Rev-0)

WORK ITEM 42: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) - Tender iv (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

v (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::

www.gpoaccess.gov

The Government is aware of the following internet web links where contractors may procure commercial specifications:

American Welding Society (AWS): http://www.awspubs.com/index.php

ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

NFPA: http://www.nfpa.org

SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 75F WLR 070-001, Rev 2, Booklet Of Gen Plans, Sheet 4 of 8 (Main Deck

Arrangement)

Coast Guard Drawing 130 CGB 111-002, Rev 9, Details, Side Shell Plating and Framing

Coast Guard Drawing 130 CGB 530-002, Rev 3, Cooling Water Piping Schematic

Coast Guard Drawing 130 CGB 633-001, Rev -, Cathodic Protection

Coast Guard Drawing 130 CGB 71-77 085-001, Rev B, General Arrangements and Profile

Coast Guard Drawing 130 CGB67 111-001, Rev 9, Hull Details – Bottom & Main Deck Plating and

Framing Details

Coast Guard Drawing 130 CGB68 111-001, Rev 3, Hull Details – Bottom & Main Deck Plating and

Framing Details

Coast Guard Drawing 130 CGB69 111-001, Rev 3, Hull Details – Bottom & Main Deck Plating and

Framing Details

Coast Guard Drawing 130 CGB70 111-001, Rev -, Hull Details – Bottom & Main Deck Plating and

Framing Details

Coast Guard Drawing 130 CGB71-77 085-004, Rev 1, Docking Plan

Coast Guard Drawing 130 CGB71-77 085-005, Rev -, Body Plan

Coast Guard Drawing 130 CGB71-77 085-006, Rev -, Curves of Form

Coast Guard Drawing 130 CGB71-77 111-001, Rev -, Hull Details – Bottom & Main Deck Plating and

Framing Details

Coast Guard Drawing 130 CGB71-77 123-001, Rev -, Spud Well Bhds & Spud Details http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace vi (Rev-0)

Coast Guard Drawing 130 CGB71-77-085-004, Rev 1, Docking Plan

Coast Guard Drawing 130 CGB74-77 111-001, Rev A, Hull Details – Bottom & Main Deck Plating and

Framing Details

Coast Guard Drawing 130-CGB67 123-2, Rev 2, Transducer Well Details

Coast Guard Drawing 75F WLR 070-001, Rev 2, Booklet Of Gen Plans (75307)

Coast Guard Drawing 75F WLR 085-001, Rev A, Curves of Form

Coast Guard Drawing 75F WLR 085-008, Rev 2, Lines Plan

Coast Guard Drawing 75F WLR 085-012, Rev -, 75FT “F” Class Towboat Docking Block Arrangement

Coast Guard Drawing 75F WLR 085-012, Rev -, Docking Block Arrangement (‘F’ Class)

Coast Guard Drawing 75F WLR 085-012, Rev-, 75FT “F” Class Towboat Docking Block Arrangement

Coast Guard Drawing 75F WLR 110-001, Rev 3, Shell Expansion

Coast Guard Drawing 75F WLR 116-001, Rev 5, Longitudinal Structural Framing

Coast Guard Drawing 75F WLR 117-003, Rev 2, Transverse Structural Frames 15-16-17-19-20

Coast Guard Drawing 75F WLR 117-004, Rev 2, Transverse Structural Frames 21-22-23-24-25-26

Coast Guard Drawing 75F WLR 121-001, Rev 2, Longitudinal Structural Bulkheads

Coast Guard Drawing 75F WLR 122-001, Rev 4, Transverse Structural Bulkhead

Coast Guard Drawing 75F WLR 243-001, Rev 3, Shafting Arrangement

Coast Guard Drawing 75F WLR 243-002, Rev 5, Shaft Details

Coast Guard Drawing 75F WLR 243-002, Rev 6, Shaft Details

Coast Guard Drawing 75F WLR 245-003, Rev 2, Propeller, Fairwater & Guard (6-blade)

Coast Guard Drawing 75F WLR 532-002, Rev 3, Engine Cooling Details

Coast Guard Drawing 75F WLR 532-003, Rev 1, Keel Cooler Details

Coast Guard Drawing 75F WLR 562-001, Rev 1, Rudder Arrangements

Coast Guard Drawing 75F WLR 562-003, Rev 4, Steering Rudders & Stocks

Coast Guard Drawing 75F WLR 562-003, Rev 4, Steering Rudders and Stocks

Coast Guard Drawing 75F WLR 562-005, Rev 6, Flanking Rudders & Stocks

Coast Guard Drawing 75F WLR 562-005, Rev 6, Flanking Rudders and Stocks

Coast Guard Drawing 75F WLR 582-002, Rev 2, Mooring and Spud Arrangements

Coast Guard Drawing 75F WLR 582-003, Rev 5, Spud Details

Coast Guard Drawing 75F WLR 633-001, Rev -, Cathodic Protection

Coast Guard Drawing 75F-WLR-330-002, Rev G, Navigation Lights Diagram

Coast Guard Drawing FL 1204-3, Rev A, Welded Padeyes & Links

Coast Guard Drawing FL 6713-203, Rev -, CRP-V850 Transducer (SS505) Adapter Assembly

Coast Guard Drawing75F WLR 070-001, Rev 2, Booklet of General Plans, Sheet 6/8

Coast Guard Fleet Drawing FL 2602-10, Rev J, Spud Arrangements and Details

NAVSEA Drawing 803-2145807, Rev C, Propulsion Shafting And Components

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Technical Publication (TP) 3173, SWBS 324, Navigation Light Panel vii (Rev-0)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2014, Shipboard

Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary

Machine Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary

Services

OTHER REFERENCES

American Bureau of Shipping (ABS) 2, Rule Requirements for Survey After Construction, 2014, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings

ASTM International (ASTM) B 843, 2007, Standard Specification for Magnesium Alloy Anodes for

Cathodic Protection

ASTM International (ASTM) D1709, 2008, Standard Test Methods for Impact Resistance of Plastic Film by the Free-Falling Dart Method

ASTM International (ASTM) D1922, 2008, Standard Test Method for Propagation Tear Resistance of

Plastic Film and Thin Sheeting by the Pendulum Method

ASTM International (ASTM) D3951, Reapproved 2010, Standard Practice for Commercial Packaging

ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component

Adhesives (An)

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component

Adhesives (AN)

ASTM International (ASTM) D882, 2009, Standard Test Method for Tensile Properties of Thin Plastic

Sheeting

Code of Federal Regulations (CFR) Title 29, Part 1915, Section 15, 2007, Shipyard Employment

Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene

Glycol (For Caterpillar applications, use CAT Extended Life Pre-Mix coolant.)

Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene

Glycol (For Caterpillar equipment applications, use CAT Extended Life Pre-Mix coolant.)

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-

Petrolatum

Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert

Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections

Federal Standard (FED-STD) 595, 2008, Colors Used in Government Procurement

Fernstrum Gridcooler Installation and Maintenance Manual, 2013, Form 175 viii (Rev-0)

International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller -

Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive

International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller -

Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive

MIL PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of

Reliability Is Required

MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application

MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application

MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application

MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)

MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main

Propulsion Shafting

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough

Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning ix (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM

DESCRIPTION

NSN/PN QTY ESTIMATED

COST

($/UNIT)

11 Y **Propulsion Tail

Shaft NSN: 3040-01-501-2508 2 ea.

16,000.00

13 N **Sleeve, Shaft, Aft & Fwd NSN: 2010-01-501-5183 1 ea.

4,000.00

16 Y **Propeller, RH NSN: 2010-01-501-5459 1 ea. 14,000.00

16 Y **Propeller, LH NSN: 2010-01-501-5465 1 ea. 14,000.00

16 N **Fairwater Nut P/N: 75-WLR-F-PROPNUT 2 ea. 4,200.00

16 N Seal Ring, Hub, Propeller NSN: 2010-01-644-6873 2 ea. 625.00

16 N Seal Ring, Hub, Propeller NSN: 2010-01-644-6886 2 ea. 700.00

20 N ***Fathometer

Transducer, Shallow Water, 50-

200 kHz (Airmar

Technology

SS505)

NSN: 5845-01-518-7245 1 ea. 343.63

21 N ***Fathometer

Transducer, Shallow Water, 50-

200 kHz (Furuno

520-BLD)

NSN: 5845-01-521-8278 2 ea. 197.23

22 Y **Steering Rudder NSN: 2040-01-503-0291 2 ea. 2,700.00

22 Y **Flanking Rudder NSN: 2040-01-501-9601 4 ea. 2,700.00

41 N J-Box Navigation

Light Panel

P/N:

NLFM15DUG24DCGDFLMOWL

1 ea. 4,580.00

41 N Iota Engineering

DLS-27-15 Battery

Charger / Power

Converter

P/N: DLS-27-15 FSC: 6130 1 ea. 230.00

41 N McDermott

Masthead Lt, 5 nm vis

TB5LED-MAST-24-P-DH-30FT 1 990.00

41 N McDermott PORT

Running Lt, 2 nm vis

TB2D-PORT-24-P-DH-30FT 1 660.00

41 N McDermott STBD

Running Lt, 2 nm vis

TB2D-STAR-24-P-DH-30FT 1 660.00

x (Rev-0)

41 N McDermott Stern

Lt, 2 nm vis

TB2D-STERN-24-P-DH-30FT 1 660.00

41 N McDermott Amber

Signal Lt, 3 nm vis

TB3D-78-AMBER-24-P-30FT 2 363.00

41 N McDermott Red

Signal Lt, 3 nm vis

TB3-78-RED-24-P-30FT 2 363.00

41 N McDermott White

Signal Lt, 3 nm vis

TB3-78-WHITE-24-P-30FT 2 363.00

41 N McDermott PORT

Running Lt, 2 nm vis

TB3-PORT-24-P-DH-30FT-

BRKT

1 549.00

41 N McDermott STBD

Running Lt, 2 nm vis

TB3-STAR-24-P-DH-30FT-

BRKT

1 549.00

41 N McDermott Barge

Special Flashing

Lt, 2 nm vis

TB-266-TOW-24-P-DH-180-

30FT-BRKT

1 549.00

41 N Enersys Backup

Battery

PN: NP7-12 NSN: 6140-01-365-

2 30.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xi (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

3 Hull Plating (U/W Body), Ultrasonic Testing - Tender

4 Hull Plating (U/W Body), Ultrasonic Testing - Barge

5 Tanks (Mp Fuel Stowage And Overflow), Clean And Inspect - Barge

6 Voids (Non-Accessible), Leak Test - Tender

7 Voids (Non-Accessible), Leak Test - Barge

10 Tanks (MP Fuel Service), Clean and Inspect - Tender

11 Propulsion Shafting; Remove, Inspect, and Reinstall

14 Propulsion Shaft Bearings (External), Check Clearances

15 Propulsion Shaft Bearings (External), Renew

22 Rudder Assembly; Remove, Inspect and Reinstall

30 U/W Body, Preserve (100%) - Tender

31 U/W Body, Preserve (100%) - Barge xii (Rev-0)

PRINCIPAL CHARACTERISTICS - TENDER

75’ WLR (F-CLASS), INLAND RIVER BUOY TENDER

PHYSICAL

Length overall 75' 8-5/8"

Depth 8' 0"

Maximum beam 24' 0"

Height of highest projection N/A

Full load draft 5' 0 7/16" LCF Draft

Full load displacement 176.25 Long Tons SW

Shore tie voltage requirements 220VAC/3PH/60HZ/200AMP

Frame spacing 1' 6"

MACHINERY

Number of propellers 2

Number of blades 6

Diameter of propeller 46"

Pitch 51" fixed

RPM 450

xiii (Rev-0)

PRINCIPAL CHARACTERISTICS - BARGE

130' CGB, BARGE

PHYSICAL

Length overall 130' 0"

Depth 7' 6"

Maximum beam 30' 0"

Frame spacing 15" - 30"

Full load draft 4’ 3" (LCF Draft)

Full load displacement 240.76 Long Tons SW

Shore tie voltage requirements 220VAC/3PH/60HZ/100AMP

1 (Rev-0)

00000_1216_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at

Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For

Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.

3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".

3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for

Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel

Surfaces by Stripe Coating”

3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-

STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.

3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line

Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3:

SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE

WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".

3.7.2 SFLC Standard Specification 0000 General Requirements.

3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing

Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.2.2 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph

3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC

Std Spec 6310 (Critical drying time requirements)).”

4 (Rev-0)

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM # WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

8 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

10 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

COATING MFG PRODUCT NAME

BATCH

INDUCTION

TIME

COATING SYSTEM SEQUENCE

(PRIMER/TOUCHUP/3RD COAT, ETC.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS, CONVENTIONAL SPRAY,

ROLLED)

AVERAGE DFT

11 (Rev-0)

11000_1016_FLT

REC_11000_UWHIB_FLT_75 WLR (‘F’ Class: Hulls 75500-75501) (1211)

WORK ITEM 1: Hull Plating (U/W Body), Inspect- Tender

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 75F WLR 085-012, Rev -, 75FT “F” Class Towboat Docking

Block Arrangement

Coast Guard Drawing 75F WLR 562-003, Rev 4, Steering Rudders and Stocks

Coast Guard Drawing 75F WLR 562-005, Rev 6, Flanking Rudders and Stocks

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

OTHER REFERENCES

The Society for Protective Coatings (SSPC), January 2015, Paint Application

Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating

Thickness Requirements

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

12 (Rev-0)

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in

Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the

UWHIB in assessing the condition of the designated U/W hull components and systems:

A hull repair supervisor and a marker.

Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, sea beam arrays, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing

13 (Rev-0) devices.

3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

3.2.6 Zinc anodes.

3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, sea beam array, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.

3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection

Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition

B”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a

SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector

– see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

3.2.7.2 Dry film thickness (DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.

4. NOTES

4.1 Definitions.

4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to

33% of the entire U/W body.

4.1.2 "Partial - Condition B": The condition that exists where the coating system has incurred damage, but the substrate is not exposed in any location.

4.1.3 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.

14 (Rev-0)

4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

15 (Rev-0)

11000_1016_FLT

REC_11000_UWHIB_FLT_130’ Barge (ALL) (1211)

WORK ITEM 2: Hull Plating (U/W Body), Inspect - Barge

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 130 CGB71-77-085-004, Rev 1, Docking Plan

Coast Guard Drawing 130 CGB67 111-001, Rev 9, Hull Details – Bottom & Main Deck

Plating and Framing Details

Coast Guard Drawing 130 CGB68 111-001, Rev 3, Hull Details – Bottom & Main Deck

Plating and Framing Details

Coast Guard Drawing 130 CGB69 111-001, Rev 3, Hull Details – Bottom & Main Deck

Plating and Framing Details

Coast Guard Drawing 130 CGB70 111-001, Rev -, Hull Details – Bottom & Main Deck

Plating and Framing Details

Coast Guard Drawing 130 CGB71-77 111-001, Rev -, Hull Details – Bottom & Main

Deck Plating and Framing Details

Coast Guard Drawing 130 CGB74-77 111-001, Rev A, Hull Details – Bottom & Main

Deck Plating and Framing Details

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

OTHER REFERENCES

The Society for Protective Coatings (SSPC), January 2015, Paint Application

Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating

Thickness Requirements

16 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in

Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the

UWHIB in assessing the condition of the designated U/W hull components and systems:

A hull repair supervisor and a marker.

Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.

NOTES

1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.

3.2.1 Hull plating.

3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.

3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.

3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, sea beam arrays, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on

17 (Rev-0) bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.

3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.

3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade; inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.

3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.

3.2.6 Zinc anodes.

3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, sea beam array, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.

3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.

3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection

Board (UWHIB). Document the condition found as “Partial - Condition A”, “Partial - Condition

B”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.

NOTE

The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a

SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector

– see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.

3.2.7.2 Dry film thickness (DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.

4. NOTES

4.1 Definitions.

4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to

18 (Rev-0)

33% of the entire U/W body.

4.1.2 "Partial - Condition B": The condition that exists where the coating system has incurred damage, but the substrate is not exposed in any location.

4.1.3 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.

4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.

19 (Rev-0)

11010_UT_0617_FLT

REC_11010_UT_FLT_75 WLR (‘F’ Class: Hulls 75500-75501) (0911)

WORK ITEM 3: Hull Plating (U/W Body), Ultrasonic Testing - Tender

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of U/W hull plating.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 75F WLR 085-012, Rev-, 75FT “F” Class Towboat Docking Block

Arrangement

Coast Guard Drawing 75F WLR 110-001, Rev 3, Shell Expansion

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:

3.2 (UT measurements).

20 (Rev-0) off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurements. The Contractor shall perform a total of 300 UT measurements of U/W hull surfaces, in locations designated by the Coast Guard Inspector, using Coast Guard Drawings

75F WLR 085-012 and 75F WLR 110-001 for guidance, in accordance with SFLC Std Spec

0740, Appendix C. Mark up a copy of…