Replc_pg_8_to_A0006.docx

DOCX document 14 KB Posted

Attached to
CCTV Security Systems Federal contract opportunity
Solicitation number
70Z08419QBB700500
Issued by
Department of Homeland Security US Coast Guard

About this file

Replacement page 8 to RFQ

View the file

Other files for this federal contract opportunity

Other files attached to CCTV Security Systems, newest first.
File Type Posted
A0006_to_RFQ_70Z08419QBB700500.docx DOCX document
Responses_To_Questions.docx DOCX document
A0005_to_RFQ_70Z08419QBB700500.docx DOCX document
Attachment_2_to_A0004.docx DOCX document
A0004_to_RFQ_70Z08419QBB700500.docx DOCX document
A0003_to_RFQ_70Z08419QBB700500.docx DOCX document
A0002_to_RFQ_70Z08419QBB700500.docx DOCX document
A0001_to_RFQ_70Z08419QBB700500.docx DOCX document
Attachment_1_Past_Performance_Work_Sheet.docx DOCX document
Solicitation_dtd_15_Aug_2019.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION SHEET FOR:

STANDARD FORM 1449

REFERENCE NO. OF DOCUMENT BEING CONTINUED
PAGE

Replacement Page 8 of 65

70Z08419QBB700500 – Amendment 0006

STATEMENT OF WORK

1.0 GENERAL

1. 1 Background As a result of Hurricane Maria, the U.S. Coast Guard (USCG) Detachment Borinquen has identified a requirement for a vendor to execute repairs and improvements to the current security systems at the Housing Area as well the Hangar area. The existing system is not supported by a Service Maintenance Agreement. The existing camera system is composed mostly of Bosch Cameras, the new equipment shall be compatible with the existing cameras and equipment.

1. 2 Scope Work under this order shall consist of the effort required to repair the CCTV system installed at the USCG’s Detachment Borinquen located in Aguadilla, Puerto Rico including the Housing area located within 3 miles from the Base. The surveillance system and network shall be standalone from the existing base infrastructure and capable of seamless integration with electronic Access Control systems (ACS) and Intrusion Detection systems (IDS) that may be considered for future expansion. Contractor is to provide and install the systems providing goods, equipment, designs, and work covered by this Scope of Work. Currently the Hangar Guard shack is under construction, the new equipment shall be installed inside the new guard shack and connected to the net barrier system.

2.0 PERIOD OF PERFORMANCE.

A post award meeting will be conducted within five business days of date of award. The Contractor shall provide a project schedule, contact list, safety plan, list of equipment, systems, circuits, components, piping, and valves that require isolation so that tag-outs/lock outs can be accomplished (see paragraph 5.7.5) within 5 business days following the post award meeting. Installation shall commence within 10 business days following the Government’s approval of receipt of the list of items above. The period of performance of the project shall be one hundred and twenty (120) days from the construction notice to proceed.

3.1 Contractor Personnel

Contractor will provide in advanced a list of employees working on the project. All employees shall be wearing clothes with proper identification of the company. The Employees will report to work with a valid State or Federal ID and will be required to get a Coast Guard contractor security badge. The badge will be visible at all times. Our background check will consist of verifying they have no want’s or warrants, legally inside U.S. along with no derogatory information (Terror watch lists or other watch lists) provided by the national maritime center in Virginia who we will run the names thru.”

3.2 Access to Government Facilities and Services.

The Government will provide access to the base facilities for the Contractor as required in the performance of the tasks identified in this SOW to include: restroom use, site and building electrical power as currently available, security response, and fire protection.

4.0 Contractor Furnished Property

The Contractor shall furnish all materials, equipment, and labor, including safety related processes and materials, necessary to fulfill the requirements of this contract.

5.0 REQUIREMENTS.

The installation shall be executed in 4 phases:

Phase 1: Plaza Network Room, Security Office, Housing gates Phase 2: Repairs at the Hangar Site, Crown road and Wing road