417_F_Shackles_and_Swivels.pdf

PDF 453 KB Posted

Attached to
Farication of Swivels
Solicitation number
70Z08418RBHQ00400
Issued by

About this file

Specification No. 417, Revision F

View the file

Other files

File Type Posted
Questionnaire_Rev2.pdf PDF
Questionnaire_Rev._1.pdf PDF
SOW_for_swivels.doc DOC document
Questionnaire.docx DOCX document
Attchament_121080-C.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specification 417F Nov 2017

UNITED STATES COAST GUARD

SHORE INFRASTRUCTURE LOGISITICS CENTER

WATERWAYS OPERATIONS PRODUCT LINE

NOVEMBER 2017

SPECIFICATION FOR FABRICATION

OF

SHACKLES, MODEER SHACKLES, AND SWIVELS

SPECIFICATION NO. 417

REVISION F

Specification 417F Nov 2017

1. SCOPE

1.1 Purpose. This specification describes the requirements for shackle assemblies, shackle pins, swivels, and split keys used as mooring fittings on aids to navigation buoys. Also included herein are the requirements for Modeer shackle assemblies used for handling stud link chain.

1.2 Classification. Items covered by this specification are described by class, type, and style as defined below.

1.2.1 Class. Shackle assemblies, shackle pins, Modeer shackle assemblies, and swivels are of the classes listed below. The class of an item is based on the item’s size, which is defined as the nominal diameter of the bar stock used in the manufacture of the item. In addition, a split key is considered to be of the same class as the shackle pin with which it mates.

Class Shackle Size (in.)

Swivel Size (in.)

Modeer Shackle Size (in.)

1st 2 2 1-3/4 2nd 1-3/4 1-3/4 1-5/8 3rd 1-1/2 1-1/2 - 4th 1 1-1/4 -

Special 2-1/2 - -

1.2.2 Type. The term “type” refers to shackle pins. Two types of shackle pin are covered by this specification: rivet pin and split key pin.

1.2.3 Style. The term “style” refers to swivels. Two styles of swivel are covered by this specification: upset head and threaded nut.

1.3 Definitions.

1.3.1 Batch. A batch consists of all items of the same class, type, and style, made from the same heat of steel, and submitted for inspection at the same time.

2. APPLICABLE DOCUMENTS

2.1 General. The documents listed in this section are referenced in sections 3 and 4 of this specification. This section does not include documents cited in other sections of this specification which are recommended for additional information or used as examples. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements cited in sections 3 and 4 of this specification, whether or not the referenced documents are listed here.

Specification 417F Nov 2017

2.2 Industry Publications. The latest revision of the following documents form a part of this specification to the extent referenced herein.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM A666 Austenitic Stainless Steel Sheet, Strips, Plate and Flat Bar for Structural Applications

ASTM D5168 Standard Practice for Fabrication and Closure of Triple-Wall Corrugated Fiberboard Containers

AMERICAN SOCIETY FOR QUALITY (ASQ)

ASQ Q9001 Quality Management Systems – Requirements – T860E

ANSI/ASQC-C1-1996 Specification of General Requirements For a Quality Program

INTERNATIONAL STANDARDS ORGANIZATION (ISO)

ANSI/NCSL Z540-3.2006 Requirements for the Calibration of Measuring and Test Equipment

2.2.1 Military Specifications

MIL-STD-129R 18 February 2014, Military Marking for Shipment and Storage

2.3 Drawings. The latest revision of the following United States Coast Guard Ocean Engineering drawings form a part of this specification to the extent referenced herein, and shall be referred to as "the drawings" throughout this specification:

Number Title 121079 Shackles 121080 Modeer Shackles 121081 Swivels

2.4 Source of Documents. The documents may be obtained from the following sources:

Industry Publications.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

1916 Race Street Philadelphia, PA 19103-1187

Specification 417F Nov 2017

AMERICAN SOCIETY FOR QUALITY CONTROL (ASQC)

(Application for copies should be addressed to the American Society for Quality Control

(ASQC),

310 West Wisconsin Avenue Milwaukee, Wisconsin 53203

Military Specifications.

(Unless otherwise indicated, copies of the above specifications and standards are available from the Defense Printing Service Detachment Office, Bldg. 4D (NPM- DODSSP), 700 Robbins Avenue, Philadelphia, PA 19111-5094.)

Coast Guard Documents.

United States Coast Guard Shore Infrastructure Logistics Center Waterways Operations Product Line 300 East Main Street Norfolk, VA 23510-9104 http://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-to-Engineering- Logistics-CG-4-/Logistic-Centers/Waterways-Operation-Product-Line/

2.5 Precedence. In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.

3. REQUIREMENTS

3.1 General. Shackle bodies and pins, Modeer shackle bodies and pins, and swivels shall be manufactured of carbon steel, and shall be either forged or cast. Split keys shall be manufactured of corrosion resistant steel. The slot in the split key pin shall have a rounded slot or rectangular shape.

3.1.1 Batch Number. The Contractor shall assign a unique sequential number to each batch submitted under this specification.

3.1.2 Assemblies. Swivels shall be furnished assembled, as shown on the drawings. Shackle assemblies shall consist of shackle components furnished assembled as described below, in the manner shown on the drawings.

3.1.2.1 Rivet Pin Shackle Assembly. A rivet pin shackle assembly shall consist of the specified class of shackle body and the identical class of rivet pin, assembled. In addition, a retaining wire shall be inserted through the 3/16-inch hole in the rivet pin, so that the pin will remain with the shackle body during shipment.

Specification 417F Nov 2017

3.1.2.2 Split Key Shackle Assembly. A split key shackle assembly shall consist of the specified class of shackle body, the identical class of split key pin, and the identical class of split key, assembled. The legs of the split key shall not be spread more than 5 degrees after the split key has been inserted in the pin.

3.1.2.3 Modeer Shackle Assembly. A Modeer shackle assembly shall consist of the specified class of Modeer shackle body and the identical class of Modeer shackle pin, assembled.

3.2 Material.

3.2.1 Shackle Bodies. Shackle Pins, Swivels. Shackle bodies and pins, Modeer shackle bodies and pins, and swivels shall be made of carbon steel of uniform quality. The chemical composition of the steel shall be determined at the steel mill for each heat of steel, and shall conform to the values listed in Table I.

Table I Chemical Composition of Steel

Element Wt. Percent Carbon 0.28 - 0.55

Manganese 0.60 - 1.00 Silicon 0.80 max.

Phosphorus 0.05 max.

Sulphur 0.05 max.

3.2.1.1 Alloying Elements. Additional alloying elements may be added to the steel as necessary to meet the proof load and breaking load requirements specified herein. If alloying elements are added, they shall not exceed the values listed in Table II.

Table II Alloying Elements

Element Wt. Percent

Chromium 0.6 max.

Nickel 0.7 max.

Molybdenum 0.25 max.

3.2.2 Split Keys. Split keys shall be class 316 or class 316L plate or strip corrosion resistant steel conforming to ASTM A666.

3.2.4 Traceability. The Contractor shall maintain the traceability of steel and corrosion resistant steel throughout the production, inspection, and testing processes. Each item offered under this specification shall be traceable by batch number to the heat of steel or corrosion resistant steel from which it was made.

Specification 417F Nov 2017

3.3 Design. Items covered by this specification shall conform to the configurations, dimensions, and tolerances shown on the drawings. Swivels shall rotate freely, and may be furnished as either the upset head style or the threaded nut style as shown on the drawing. Shackles shall be easily assembled and disassembled. When rivet pins are furnished alone, and not as part of rivet pin shackle assemblies, the 3/16-inch hole shown on the drawings may be omitted.

3.4 Proof Load. Each shackle assembly, shackle pin, Modeer shackle assembly, and swivel offered for acceptance shall have been subjected to the applicable proof load specified in Table III without rupture or deformation.

3.5 Breaking Load. Shackle assemblies, shackle pins, Modeer shackle assemblies, and swivels shall be capable of withstanding the applicable breaking load specified in Table III for a minimum of 15 seconds without rupture.

Table III Proof and Breaking Loads

Item Proof Load

(lb.)

Breaking Load

(lb.)

Shackle Assemblies and Shackle Pins

1st Class 115,000 230,000 2nd Class 90,000 180,000 3rd Class 65,000 130,000 4th Class 30,000 60,000

Special Class 180,000 360,000

Modeer Shackle Assemblies

1st Class 90,000 180,000 2nd Class 65,000 130,000

Swivels

1st Class 82,000 164,000 2nd Class 60,000 120,000 3rd Class 45,000 90,000 4th Class 30,000 60,000

3.6 Heat Treatment. Items submitted under this specification shall be heat treated by a suitable process as required to meet the proof load and breaking load requirements specified herein.

3.7 Welding. Welding is required in the design of the threaded nut style swivel, as shown on the drawings. This welding shall be performed by an electric welding method. The welds shall not contain cracks, craters, undercutting, overlap, porosity, or lack of fusion.

Specification 417F Nov 2017

3.8 Finish. All items shall be submitted in natural color and finish. Varnish or other coatings shall not be used.

3.9 Surfaces. All items offered shall be free from cracks, mill defects, burrs, flaws, rough surfaces, or other defects which might adversely affect their serviceability and handling.

3.10 Identification Marking. For tracking purposes, each item offered under this specification (with the exception of split keys) shall be identified by an identification marking. The marking shall be stamped, engraved, or otherwise permanently affixed to each item, and shall include the manufacturer’s name or trademark, the batch number, and the year code and last three digits of the contract number (for example, a contract numbered “ HSCG40-XX-P-TCB018” would be marked as (“XX-018”). Shackle assemblies and Modeer shackle assemblies shall be marked on the bodies and on the pins.

3.11 Documentation.

3.11.1 Quality Assurance Inspection Form. The Contractor shall develop and provide a Quality Assurance Inspection Form (QAIF). The QAIF shall be used to document the inspections and tests performed during the fabrication process. The form shall be printed on standard (i.e., 8½ x 11 inch) white paper. Inspection results may be handwritten on the form. The form shall be prepared in the Contractor's format and shall be legible, in English, and suitable for reproduction.

The form shall be made available to the Contracting Officer’s Representative (COR) for review.

3.11.1.1 QAIF Content. At a minimum the QAIF shall include:

a) Item

b) Batch number (paragraph 3.1.1)

c) Serial numbers of items inspected

d) Date of test or inspection

e) Test or inspection to be performed (list every test and inspection required by paragraph 4.5)

f) Result of test or inspection

g) Accept/Reject criteria for each test or inspection

h) Corrective action taken (if any)

i) Notes

j) Initials or signatures of Contractor’s test personnel

3.11.2 Mill Reports. The Contractor shall furnish a mill report from the steel mill for each heat of steel. The report shall indicate the heat number, steel designation, chemical composition (including any added alloying elements), and quantity of steel represented by the report. Mill reports containing the above information shall also be furnished for each heat of corrosion resistant steel used in split keys.

Specification 417F Nov 2017

3.11.3 Material Inspection and Receiving Report (DHS Form 700-21). A form DHS-700-21 shall be used as a certification of product quality assurance, as a packing list, and as a certification of acceptance. The Contractor shall prepare a separate DHS-700-21 for each shipping lot. Prior to shipment, the DHS-700-21 must be signed by the COR.

4. VERIFICATION

4.1 General. The Contractor's quality assurance program shall meet the requirements of ASQ Q9001. However, the Contractor does not have to be Q9001 certified.

4.1.1 Contractor’s calibration system. The Contractor shall maintain a calibration and maintenance system to control the accuracy of measurement and test equipment used in the fulfillment of the requirements of this specification listed in section 2.2. The system shall include, as a minimum, prescribed calibration intervals, source of calibration, and a monitoring system to ensure adherence to calibration schedules. All testing equipment shall have been calibrated traceable to the National Standards within 12 months prior to the testing. At the time of Coast Guard inspection, documentation in support of this requirement shall be made available to the COR.

4.2 Classification of Inspections. The inspection requirements specified herein are classified as follows:

a. Contractor production inspection (paragraph 4.2.1)

b. Coast Guard inspection (paragraph 4.2.2)

4.2.1 Contractor Production Inspection. The tests and inspections required by this specification are not intended to supplant any controls, examinations, inspections, or tests normally employed by the Contractor to assure product quality. The Contractor shall perform the tests and inspections specified in paragraph 4.5 to ensure conformance to this specification. The Contractor shall provide space, personnel, and test equipment to conduct all inspection and test requirements.

4.2.2 Coast Guard Inspection. The Coast Guard reserves the right to observe, verify, or perform the tests and inspections outlined in paragraph 4.5. During the Coast Guard inspection, the COR will use the defect categories, rejection criteria, and sampling plans outlined in paragraphs 4.3 and 4.4 (and all associated sub-paragraphs).

4.3 Defect categories. The defect categories listed below will be used during the Coast Guard inspection.

4.3.1 Major. Failure to comply with the requirements of the following paragraphs will constitute major defects:

3.2 Material (and all associated subparagraphs)

3.4 Proof load

3.5 Breaking load

Specification 417F Nov 2017

4.3.1.1 Rejection for major defects. If a major defect is found in any batch, the entire batch will be rejected. A batch thus rejected shall not be reworked or resubmitted.

4.3.2 Minor. Failure to comply with the requirements of the following paragraphs will constitute minor defects:

3.3 Design

3.7 Welding

3.8 Finish

3.9 Surfaces

3.10 Marking

4.3.2.1 Rejection for minor defects. Batches rejected for minor defects may be reworked and resubmitted for inspection when they are in compliance with the requirements of this specification. Resubmitted batches shall be clearly identified as such, and shall be kept separate from new batches.

4.4 Sampling. Samples for inspections and tests performed during the Coast Guard inspection will be randomly selected from batches by the COR, according to the sampling plans described below.

4.4.1 Sampling plan for inspection of minor defects. The unit of inspection will be one shackle assembly, one shackle pin, one Modeer shackle assembly, one swivel, or one split key. The number of samples and accept/reject values will be in accordance with Table IV.

Table IV

Sampling for Minor Defects

No. Items In Batch

No. of Samples

Minor Defects Accept Reject

2 to 15 2 0 1 16 to 50 5 1 2 51 to 90 8 2 3 91 to 150 13 3 4

151 to 280 20 5 6 281 to 500 32 7 8 501 to 1200 50 10 11

1201 to 3200 80 14 15 3201 and above 125 21 22

4.4.2 Sampling plan for proof load and breaking load tests. The unit of inspection will be one shackle assembly, one shackle pin, one Modeer shackle assembly, or one swivel. The number of samples and accept/reject values will be in accordance with Table V. In addition to the deliverables required by the solicitation, additional units shall be manufactured and processed with each batch in the quantities required by Table V for the breaking load tests.

Specification 417F Nov 2017

Table V Sampling for Proof Load and Breaking Load

No. Items in Batch

Proof Load Breaking Load No.

Samples Accept Reject No.

Samples Accept Reject

2 to 15 2 0 1 2 0 1 16 to 50 5 0 1 2 0 1 51 to 90 8 0 1 2 0 1 9l to l50 13 0 1 3 0 1 151 to 280 20 0 1 3 0 1 281 to 500 32 0 1 3 0 1 501 to 1200 50 0 1 4 0 1

1201 to 3200 80 0 1 4 0 1 3201 and above 125 0 1 4 0 1

4.5 Inspections and tests.

4.5.1 General. The following inspections and tests shall be performed to comply with the requirements of this specification. They are not intended to limit or supplant any inspections and tests normally performed by the Contractor.

4.5.2 Documentation Review. The documentation required by paragraph 3.11 shall be reviewed for conformance with this specification and provided to the COR upon request.

4.5.3 Visual inspection. Each item shall be visually inspected to verify conformance with paragraphs 3.3, 3.7, 3.8, 3.9, and 3.10. Items failing to comply with the requirements of this specification shall be rejected.

4.5.3.1 Proof load test. The Contractor shall proof test each shackle assembly, shackle pin, Modeer shackle assembly, and swivel manufactured under this specification. Items which fail this proof testing prior to being offered for Coast Guard inspection may be reworked, or screened for defectives, and re-tested. This process shall be recorded on the QAIF (3.11.1). At the time of Coast Guard inspection, every shackle assembly, shackle pin, Modeer shackle assembly, and swivel offered shall have successfully passed the proof load test as specified in paragraph 3.4.

The Contractor shall certify this by submitting a Certificate of Performance (Appendix A) for each batch offered. In addition, at the time of Coast Guard inspection, the Contractor shall proof test the samples chosen in accordance with paragraph 4.4.2 in the presence of the COR. If any item fails the proof test at this time, it shall be considered a major defect.

4.5.3.2 Method of proof load testing. Shackle assemblies, Modeer shackle assemblies, and swivels shall be proof tested assembled. These items may be proof tested individually or in a series. When shackle pins are to be furnished alone, they may be proof tested individually, or by inserting them into shackle bodies of the appropriate class and tested as assemblies. Application of the proof load shall be at the centerline of the sample. The diameter of the attachments used in the proof tests shall not be greater than the size of the sample being tested.

Specification 417F Nov 2017

4.5.3.3 Breaking load test. The Contractor shall perform breaking load tests in the presence of the COR, using samples chosen in accordance with paragraph 4.4.2. Shackle assemblies, Modeer shackle assemblies, and swivels shall be break tested assembled. When shackle pins are to be furnished alone, they may be break tested individually, or by inserting them into shackle bodies of the appropriate class and tested as assemblies. Application of the breaking load shall be at the centerline of the sample. The diameter of the attachments used in the breaking load tests shall not be greater than the size of the sample being tested.

4.6 Inspection of packaging and marking. The Coast Guard inspection to determine compliance with the requirements of paragraph 5 will be performed at the point of destination. Items received at the point of destination which are not packaged and marked in accordance with the requirements of paragraphs 5 will be rejected.

5. PACKAGING AND MARKING

5.1 Shipping Containers.

5.1.1 Shackle Assemblies, shackle pins, swivels. Shackle assemblies, shackle pins, Modeer shackle assemblies, and swivels shall be packed in clean steel drums or barrels (30, 55 or 80 gallon capacity). The top of each drum or barrel shall be fitted with a cover or laced with wire rope to prevent spilling of the contents. Covers shall not be welded in place. The contents of a drum or barrel shall be limited to a single National Stock Number.

5.1.2 Split Keys. Split keys, when purchased alone, and not as part of split key shackle assemblies, shall be packed in triple-wall fiberboard boxes conforming to ASTM D5168, utilizing either metallic or non-metallic strapping. The contents of each box shall be limited to a single National Stock Number. A maximum of 250 split keys of any class shall be packed per box. The split keys shall be cushioned, braced, or blocked to prevent excessive movement.

5.1.3 Disposition of shipping containers. Shipping containers described in the preceding paragraphs, as used, shall become the property of the U.S. Coast Guard.

5.2 Marking. See MIL-STD-129R, Section 5, Detailed Requirements, page 22. See Appendix B for examples of location and placement.

5.2.1 Shipping Containers. Steel drums or barrels shall be legibly stenciled in 3/4 – inch high letters with the information listed below. Boxes of split keys shall be legibly marked with the same information.

Shipping Destination National Stock Number Part Number Item Description Quantity Contract Number Date of Manufacture

Specification 417F Nov 2017

Contractor’s Name Weight

5.2.2 Palletized shipments. Palletized shipments shall normally be confined to a single National Stock Number per pallet. Mixed pallets shall be clearly and legibly marked “MIXED STOCK”.

5.3 Bar coding. Bar coding in accordance with MIL-STD-129R, ISO/IEC 16388:2007, Code 39 Symbology is required. See Appendix B for location and placement on labels.

5.4 Shipping. All items shall be shipped FOB Destination.

5.4.1 Shipping address.

US Coast Guard Surface Forces Logistics Center 2401 Hawkins Point RD, Receiving Room - Bldg 88 Curtis Bay, MD 21226

NOTE

Normal delivery hours at the warehouse are Monday through Friday 0730 - 1300.

Specification 417F Nov 2017

APPENDIX A

CERTIFICATE OF PERFORMANCE

Contract No. ______________________________

Item ________________________ Batch No.___________________

I hereby certify that all items in the above numbered batch submitted for the above numbered contract have successfully passed the proof load test as specified in paragraph 3.4 of U.S. Coast Guard Specification No. 417F.

Signed_______________________ Date_________________________

Title ____________________________

Specification 417F Nov 2017

SPECIFICATION FOR FABRICATION OF SHACKLES, MODEER SHACKLES, AND

SWIVELS

SPECIFICATION NO. 417

Revision F

NOVEMBER 2017

Prepared by:

Michael J. Beimel Equipment Specialist

Approved by:

30 November 2017

Mr. Wayne S. Danzik Date Deputy Product Line Manager

Specification 417F Nov 2017

APPENDIX B

NOTE: For identification bar code specific marking locations.

Placement of identification and address marking on barrels, drums, and other cylindrical containers.

Note

For this specification, note the location of the identification markings on the steel drum only.

Specification 417F Nov 2017

Note

The label on a steel drum will only utilize the EXTERIOR CONTAINER Label format.

Swivel Size
Shackle Size
Class
(in.)
Title
(in.)
Swivels
Element
Wt. Percent
Table I
Table II
Table III
Modeer Shackle Assemblies
Swivels
Table IV
Minor Defects
Accept
Reject
Proof Load
Breaking Load
SPECIFICATION NO. 417
Revision F
NOVEMBER 2017
Michael J. Beimel
2017-11-30T06:38:02-0500
BEIMEL.MICHAEL.JOSEPH.1316952271
2017-11-30T08:04:29-0500
DANZIK.WAYNE.S.1273020744

File details come from the government source that posted it.